第一篇:腳手架搭設(shè)施工方案
Xxxx工程
外墻腳手架施工方案
目
錄
一、工程概況.......................................................................1
二、腳手架的搭設(shè)方案.......................................................1
三、腳手架搭設(shè)要點(diǎn)...........................................................4
四、桿件搭設(shè)順序...............................................................5 五、一般規(guī)定.......................................................................5
六、腳手架拆除...................................................................6
七、腳手架的使用規(guī)定.......................................................7
八、安全要求.......................................................................8
九、文明施工及成品保護(hù).................................................10
十、計(jì)算書.........................................................................10
十一、腳手架搭設(shè)示意圖.................................................16
0 Xxxx工程
外墻腳手架施工方案
一、工程概況 工程名稱:
興建單位:
監(jiān)理單位:
施工單位:
XXXX工程位于XXXXXXXX,D、E座18層(含首、二層裙樓),建筑高度69.05m。外墻腳手架由(±0.00)開始搭設(shè),屬落地式腳手架,當(dāng)施工完裙樓,外腳手架即搭設(shè)在裙樓的頂板上。
每6層樓設(shè)一次腳手架卸荷和按實(shí)際需要每4層設(shè)一道安全斜檔板。每棟樓設(shè)一道施工梯及搭設(shè)落地式卸料平臺(tái)1個(gè)。
二、腳手架的搭設(shè)方案
1、腳手架基礎(chǔ)(見附圖一)
腳手架地基應(yīng)平整夯實(shí),上鋪150厚C20砼,靠建筑物邊設(shè)2003300排水溝一道。腳手架立桿不能直接立于砼面上,應(yīng)加設(shè)木墊板,墊板尺寸不得小于2003200320。
2、立桿(見附圖二)
立桿鋼管采用φ4833.5(外徑3壁厚),鋼管立桿縱距1.8m,步距1.9m,內(nèi)排立桿離墻(20)㎝,小橫桿內(nèi)距0.7m,垂直偏差不大于架高的1/300,并同時(shí)控制其絕對(duì)偏差值,所有立桿采用單根鋼管搭設(shè)。相鄰立桿的接頭位置應(yīng)錯(cuò)開布置在不同的步距內(nèi),與相近大橫桿的距離不宜大于步距的三分之一。立桿與大橫桿必須用直角扣件扣緊,不得隔步設(shè)置或遺漏。立桿頂端應(yīng)高出建筑物檐口上皮高度1.5米。立桿四角應(yīng)垂直,保證腳手架外觀 Xxxx工程
外墻腳手架施工方案
整齊。
3、橋架的搭設(shè)
橋架每層步距約1.9m,中間用鋼管設(shè)水平桿一道,橋架排距寬度為70cm,內(nèi)立竿距墻面20cm,橋架兩邊大橫桿用鋼管,中間鋪設(shè)竹排。橋架每平方米荷載≤300Kg,不得在同一位置、上下層同時(shí)堆放過多材料。橋架兩側(cè)的大橫桿用十字扣件裝設(shè)在立桿上,內(nèi)外大橫桿要求平行,同一排橫桿的水平偏差不大于該片腳手架總長(zhǎng)度的1/250,且不大于50mm。上下橫桿的接長(zhǎng)位置應(yīng)錯(cuò)開布置在不同的立桿縱距中,與相近立桿的距離不大于縱距的三分之一。每二步距設(shè)紅白擋腳板一道。
4、小橫桿
小橫桿貼近立桿并布置在大橫桿之下,用直角扣緊,在相鄰立桿之間根據(jù)需要加設(shè)1根或2根,在任何情況下均不得拆除作為基本結(jié)構(gòu)桿件的小橫桿,同時(shí)要求小橫桿懸掛端離墻面不能小于15cm。
5、剪刀撐
腳手架應(yīng)根據(jù)確保整體穩(wěn)定和抵抗側(cè)力作用的要求,按照以下規(guī)定要求設(shè)置剪刀撐。
⑴、每隔4~6根立柱(約8~10米)沿長(zhǎng)度和高度布置雙向連續(xù)剪刀撐。剪刀撐應(yīng)沿架高連續(xù)布置。剪刀撐的斜桿兩端用旋轉(zhuǎn)扣件與腳手架的立桿或大橫桿扣緊外,剪刀撐接頭搭接不小于1.0米,用2個(gè)旋轉(zhuǎn)扣件。
⑵、剪刀撐應(yīng)聯(lián)系5~7根立桿,剪刀撐的斜桿與水平面的交角(或地面)在45°~60°夾角之間。
6、連墻桿
連墻桿采用剛性錨固,應(yīng)盡量設(shè)置在立桿和大橫桿的交叉位置,且每 Xxxx工程
外墻腳手架施工方案
層錯(cuò)開布置,每層樓面平面每隔6m以內(nèi)設(shè)置一錨固點(diǎn),豎向每層設(shè)一道,布置點(diǎn)設(shè)置在混凝土梁等剛性較大部位,用Φ12螺絲舉行預(yù)埋,Φ48短鋼管進(jìn)行連接,防止棚架擺動(dòng),起到穩(wěn)定作用,同時(shí)設(shè)置拉結(jié)點(diǎn),用Φ8鋼筋預(yù)埋在混凝土梁等剛性部位,每層錯(cuò)開,控制腳手架向外傾斜。腳手架上部未設(shè)置連墻桿的自由高度不得大于6m。連墻桿及拉結(jié)筋在外墻裝修時(shí)不得隨意拆除,如需拆除需得到上級(jí)主管部門的批準(zhǔn),并進(jìn)行相應(yīng)加固。
7、安全擋板
安全擋板設(shè)置在腳手架外側(cè),用鋼管由內(nèi)立柱到外立柱向外飄出2米,呈250角,面上鋪扎密篙竹加鋪安全網(wǎng),第一層搭設(shè)高度約15米,以上每15米搭設(shè)一層。
8、安全圍蔽
在腳手架平橋內(nèi)四周用已送檢合格的阻燃式密目安全網(wǎng)全封閉,上、中、下共設(shè)三點(diǎn)綁扎,順橋架走向每50cm綁扎一點(diǎn),四角要垂直,每搭設(shè)完一層橋架,安全網(wǎng)必須滿掛,橋架嚴(yán)禁堆放模板、木枋、鋼筋等。
9、施工梯設(shè)置
在腳手架外側(cè)搭設(shè),跟平橋高度搭設(shè)成單邊梯上落,即上完一層施工梯轉(zhuǎn)向內(nèi)橋面,到梯臺(tái)時(shí)再往上一層行走,上落梯臺(tái)規(guī)格為1.5m31m,梯級(jí)用鋼管加木板用鐵釘鋪設(shè),施工梯必須設(shè)置兜底安全網(wǎng)、側(cè)網(wǎng),施工梯兩邊高度約1.2米用鋼管各設(shè)1條欄桿扶手,每級(jí)步高不得超過30cm,坡度宜采用1:3,每棟搭設(shè)一樘。
10、腳手架卸荷
用φ16鋼筋做成雙曲鉤吊環(huán),在樓層邊梁預(yù)埋,預(yù)埋入砼邊梁內(nèi)48cm與梁鋼筋連接,外露15cm,用φ14鋼絲繩連接吊環(huán)向下斜拉吊置腳手架應(yīng) Xxxx工程
外墻腳手架施工方案
吊置位置(用鋼絲繩穿過大小橫桿底部,即兜底),每一條立竿吊拉1條(間距約1.8m),必須拉緊吊實(shí),每條鋼絲繩端部應(yīng)不小于2個(gè)扎頭,由裙樓面開始每隔6層設(shè)1道卸荷。
11、吊料平臺(tái)設(shè)置
采用落地式搭設(shè),每層樓面設(shè)1個(gè)開口,平臺(tái)規(guī)格按現(xiàn)場(chǎng)實(shí)際要求搭設(shè),面層鋪設(shè)竹排,平臺(tái)外側(cè)設(shè)1.5米高護(hù)攔加安全網(wǎng),吊料平臺(tái)上方必須預(yù)埋吊環(huán)用鋼絲繩斜吊,下方1.8m處設(shè)安全網(wǎng),并懸掛限荷1.5噸標(biāo)志牌。
12、腳手架的防雷
采用避雷針與大橫桿連通,接地線與整幢建筑物樓層內(nèi)避雷系統(tǒng)通過立桿連成一體的措施。避雷針采用φ12鍍鋅圓鋼制作,高度不小于1米,設(shè)置在腳手架四角立柱上,并將所有最上層的大橫桿全部連通,形成避雷網(wǎng)格。
13、欄桿、腳手板
欄桿和擋腳板應(yīng)搭設(shè)在外排立柱的內(nèi)側(cè),欄桿上皮高度0.9m,居中設(shè)置,擋腳板高度不應(yīng)小于180mm。
三、腳手架搭設(shè)要點(diǎn)
1、桿件連接構(gòu)造一般規(guī)定
鋼管腳手架左右相鄰立桿和上下相鄰平桿的接頭應(yīng)相互錯(cuò)開并置于不同的構(gòu)架框格內(nèi)。
鋼管腳手架搭接桿件接頭長(zhǎng)度應(yīng)≥0.8m。
2、架桿配件的一般規(guī)定
鋼管件采用Ф4833.5焊縫鋼管,鋼管的端部切口應(yīng)平整。禁止使用有明顯變形、裂紋和嚴(yán)重銹蝕的鋼管。Xxxx工程
外墻腳手架施工方案
應(yīng)使用與鋼管管徑相配合的、符合我國(guó)現(xiàn)行標(biāo)準(zhǔn)的可鍛鑄鐵構(gòu)件。
四、桿件搭設(shè)順序
其搭設(shè)順序?yàn)椋旱鬃祈拧U→水平掃腳桿→大橫桿→小橫桿→加設(shè)臨時(shí)剪刀撐→連墻桿→護(hù)攔桿→剪刀撐→綁扎架橋→張掛安全網(wǎng)→循環(huán)搭設(shè)。五、一般規(guī)定
1、在搭設(shè)之前,必須對(duì)進(jìn)場(chǎng)的腳手架桿配件進(jìn)行嚴(yán)格的檢查,禁止使用規(guī)格和質(zhì)量不合格的桿配件。
2、腳手架的搭設(shè)作業(yè)必須在統(tǒng)一指揮下,嚴(yán)格按照規(guī)定程序進(jìn)行。
3、按施工設(shè)計(jì)方案設(shè)置立桿位置。
4、周邊腳手架應(yīng)從一個(gè)角部開始并向兩邊延伸交圈搭設(shè)。
5、應(yīng)按定位依次豎起立桿,將立桿與縱桿、橫桿與掃地桿連接固定,然后安裝縱向和橫向平桿,隨校正立桿垂直之后予以固定,并按此要求繼續(xù)向上搭設(shè)。在設(shè)置第一排連墻件前,應(yīng)設(shè)置必要的固定措施,以確保構(gòu)件穩(wěn)定和架上作業(yè)人員的安全。
6、剪刀撐、斜桿等整體拉結(jié)桿件和連墻件應(yīng)隨搭升的架子一起及時(shí)設(shè)置。
7、扣件要扣緊,并注意擰緊程度要均勻適當(dāng),杜絕使用變形的桿和不合格扣件。
8、隨時(shí)校正桿件的水平偏差和垂直偏差,保證腳手架質(zhì)量和整齊。
9、下班和臨時(shí)停工應(yīng)采取臨時(shí)措施,保證腳手架整體的安全和穩(wěn)定。
10、扣件安裝:開口朝向應(yīng)合理,避免雨水流入。立桿大橫桿和小橫 Xxxx工程
外墻腳手架施工方案
桿的相接點(diǎn)到扣件中心距離不大于150mm,桿件的對(duì)伸長(zhǎng)度不小于100 mm,底部斜桿與立桿的連接扣件離地不大于500 mm。
11、連墻桿:是關(guān)系腳手架安全和穩(wěn)定的保證,應(yīng)盡量設(shè)置在立桿和大橫桿的交叉位置。
12、所有鋼管接駁位應(yīng)錯(cuò)開布置,并用直駁扣擰緊。
13、在所有外腳手架及安全擋板上滿掛(鋪)密目式防火安全網(wǎng),接縫嚴(yán)密,不允許出現(xiàn)孔洞。首層外腳手架平橋與建筑物之間的空隙用安全網(wǎng)密封。安全網(wǎng)需經(jīng)檢驗(yàn)合格后方能用于本工程。
六、腳手架拆除
1、拆除說明
腳手架的拆除作業(yè)應(yīng)按正確的拆除程序進(jìn)行。連墻件應(yīng)在位于其上的全部可拆桿件都拆除之后才能拆除。在拆除過程中,凡已松開連接的桿配件應(yīng)及時(shí)拆除運(yùn)走,避免誤扶和誤靠已松脫連接的桿件。拆下的桿配件應(yīng)以安全的方式運(yùn)出和吊下,嚴(yán)禁向下拋擲。在拆除過程中,應(yīng)作好配合、協(xié)調(diào)動(dòng)作,禁止單人進(jìn)行拆除較重桿件等危險(xiǎn)性作業(yè)。
2、拆除順序
拆除扣件式鋼管腳手架的原則是先搭設(shè)的后拆除,后搭設(shè)的先拆除,具體拆除程序?yàn)椋喊踩W(wǎng)→護(hù)身欄→小橫桿→大橫桿→立桿→連墻桿→剪力撐。
3、一般要求
⑴、先拆除兩層安全網(wǎng),然后按順序逐層由上而下進(jìn)行,嚴(yán)禁上下同時(shí)作業(yè)。
⑵、所有連墻桿件應(yīng)隨腳手架逐層拆除,嚴(yán)禁先將連墻桿件整層或數(shù) Xxxx工程
外墻腳手架施工方案
層拆除后再拆除腳手架,分段拆除高差不應(yīng)大于2步,如高差大于2步,應(yīng)增設(shè)連墻件加固。
⑶、當(dāng)腳手架拆至下部最后一根長(zhǎng)管的高度時(shí),應(yīng)先在適當(dāng)位置搭臨時(shí)拋撐加固后,再拆連墻桿。
⑷、在拆棚過程中嚴(yán)禁單人操作,拆立桿時(shí)必須要有人配合,密切注意馬路面來往車輛和行人動(dòng)向,拿穩(wěn)桿件、扣件和螺絲等零件,拆下的零件應(yīng)用袋裝好放置在室內(nèi)安全的地方,集中運(yùn)至地面,以免散墜下傷人。
⑸、參加搭、拆作業(yè)人員,一律不準(zhǔn)酒后操作,操作時(shí)必須思想集中,不準(zhǔn)說笑,打鬧或擅自離開工作崗位。
⑹、鋼管上的扣件要全部拆除,拆下的各種材料應(yīng)分類堆放。參加拆除腳手架的工作人員必須按安全要求,帶好安全帽系好安全帶,穿好防滑鞋,不穿帶好防護(hù)用具的人不得從事腳手架的搭、拆工作。
七、腳手架的使用規(guī)定
1、作業(yè)層每1m2架面上實(shí)用的施工荷載(人員、材料和機(jī)具重量)不得超過以下的規(guī)定值或施工設(shè)計(jì)值。
2、施工荷載(作業(yè)層上人員、器具、材料的重量)的標(biāo)準(zhǔn),結(jié)構(gòu)腳手架采取2KN/m2。
3、不準(zhǔn)在架板上堆放標(biāo)準(zhǔn)磚、砂漿和容器、施工設(shè)備等。
4、嚴(yán)禁上架人員在架面上奔跑、退行。
5、作業(yè)人員在架上的最大作業(yè)高度應(yīng)以可進(jìn)行正常操作為度,禁止在架板上加墊器物或單塊腳手板以增加操作高度。
6、在作業(yè)中,禁止隨意拆除腳手架的基本構(gòu)架桿件、整體性桿件、連接緊固件和連墻件。確因操作要求需要臨時(shí)拆除時(shí),必須經(jīng)主管人員同 Xxxx工程
外墻腳手架施工方案
意,采取相應(yīng)彌補(bǔ)措施,并在作業(yè)完畢后,及時(shí)予以恢復(fù)。
7、工人在架上作業(yè)中,應(yīng)注意自我安全保護(hù)和他人的安全,避免發(fā)生碰撞、閃失和落物。嚴(yán)禁在架上戲鬧和坐在欄桿上等不安全處休息。
8、人員上下腳手架必須走安全防護(hù)的出入通(梯)道,嚴(yán)禁攀援腳手架上下。
9、每班工人上架作業(yè)時(shí),應(yīng)先行檢查有無影響安全作業(yè)的問題存在,在排除和解決后方可開始作業(yè)。在作業(yè)中發(fā)現(xiàn)有不安全的情況和跡象時(shí),應(yīng)立即停止作業(yè)進(jìn)行檢查,解決以后才能恢復(fù)正常作業(yè);發(fā)現(xiàn)有異常和危險(xiǎn)情況時(shí),應(yīng)立即通知所有架上人員撤離。
10、在每步架的作業(yè)完成之后,必須將架上剩余材料物品移至上(下)步架或室內(nèi);每日收工前應(yīng)清理架面,將架面上的材料物品堆放整齊,垃圾清運(yùn)出去;在作業(yè)期間,應(yīng)及時(shí)清理落入安全網(wǎng)內(nèi)的材料和物品。在任何情況下,嚴(yán)禁自架上向下拋擲材料物品和傾倒垃圾。
八、安全要求
為確保腳手架的構(gòu)架和防護(hù)設(shè)施達(dá)到使用安全的要求,應(yīng)做好以下幾個(gè)方面:
1、桿件Φ48鋼管的質(zhì)量和允許缺陷進(jìn)行全面檢查,確保桿件符合搭設(shè)要求。
2、嚴(yán)格按照腳手架搭設(shè)設(shè)計(jì)方案要求施工,使搭設(shè)尺寸以及對(duì)誤差的控制須滿足方案要求。
3、附墻桿的設(shè)置方式、布點(diǎn)間距以及對(duì)連墻點(diǎn)的結(jié)構(gòu)加強(qiáng)均要嚴(yán)格按照方案施工,確保附墻桿起到有效作用。
4、對(duì)作業(yè)層進(jìn)行鋪板,做好防護(hù)措施。Xxxx工程
外墻腳手架施工方案
5、對(duì)腳手架實(shí)際使用荷載進(jìn)行控制,包括腳手架上施工人數(shù)、材料堆放數(shù)量和位置以及多層同時(shí)作業(yè)時(shí)的控制。
6、對(duì)施工過程中需要臨時(shí)拆除桿部件和拉結(jié)件的限制以及在恢復(fù)前的安全彌補(bǔ)措施要落實(shí),同時(shí)要落實(shí)檢查工作,消除施工安全隱患。
7、腳手架地基要嚴(yán)格按照方案處理。
8、安全網(wǎng)以及其它防護(hù)措施均要嚴(yán)格按照要求設(shè)置。
9、搭拆過程中注意問題:
⑴、不能隨意改變構(gòu)架結(jié)構(gòu)及其尺寸,特別是立桿間距、附墻點(diǎn)數(shù)、卸荷數(shù)量等。杜絕使用不合格的桿配件和材料。
⑵、不能隨意減少鋪板數(shù)量、防護(hù)桿件和設(shè)施。在不符合要求的地基和支持物上不采取措施搭設(shè)腳手架,不得在六級(jí)以上大風(fēng)、雷雨天繼續(xù)作業(yè)。⑶、不按質(zhì)量要求搭設(shè),立桿偏斜,拉結(jié)點(diǎn)松弛,起不到有效拉結(jié)作用。不按規(guī)定的程序和要求進(jìn)行搭設(shè)和拆除作業(yè),包括在搭設(shè)時(shí)未及時(shí)設(shè)置拉撐桿件,在拆除過程中過早地拆除拉結(jié)桿件。
⑷、在搭設(shè)和拆除架體過程中,未采取或未有效采取安全防護(hù)措施,包括不設(shè)置防護(hù)和使用安全防護(hù)用品。⑸、不按規(guī)定設(shè)置安全網(wǎng)。
⑹、隨意增加上架的人員和材料,引起超載。⑺、任意拆除構(gòu)件的桿配件和拉結(jié)措施。⑻、任意抽掉、減少作業(yè)層腳手板。
⑼、站在不具備操作條件的橫桿上或單塊板上操作。
⑽、加強(qiáng)管理人員和施工人員的教育,提高自我保護(hù)意識(shí)和素質(zhì)。
Xxxx工程
外墻腳手架施工方案
九、文明施工及成品保護(hù)
(1)、作業(yè)人員必須持證上崗,進(jìn)入施工現(xiàn)場(chǎng)要戴好安全帽,著裝整齊。
(2)、對(duì)施工場(chǎng)地的物料進(jìn)行及時(shí)堆放,做到工完料清。
(3)、在腳手架搭設(shè)及拆過程中,嚴(yán)格按操作程序施工,對(duì)重點(diǎn)部位進(jìn)行嚴(yán)格保護(hù),確保成品安全。
十、計(jì)算書
1、計(jì)算說明:
⑴計(jì)算參考書為《建筑施工腳手架實(shí)用手冊(cè)》,計(jì)算中的公式與查表數(shù)據(jù)均由手冊(cè)中查得。
⑵搭設(shè)尺寸:根據(jù)本章表4—7推薦的腳手架常用尺寸,試選搭設(shè)尺寸如下:步距=1.9m,柱距=1.8m,連墻件豎向間距H1 =3m,水平間距L1=6m,安全網(wǎng)尺寸為3.5cm×3.5cm,繩徑3.2mm,并取整個(gè)腳手架的步距,柱距及連墻件間距相等或相近,先按以上尺寸對(duì)立柱進(jìn)行穩(wěn)定驗(yàn)算。腳手架搭設(shè)高度Hd=51.5m,采用φ48×3.5鋼管,材料為Q235(3號(hào))鋼,腳手架排距Lb=0.7m,腳手架用于外墻裝修,按照兩層同時(shí)作業(yè)計(jì)算。
3.立柱穩(wěn)定驗(yàn)算
本腳手架以相等的步距、柱距、排距、連墻件間距搭設(shè),底層的立柱段所受壓力最大,為腳手架的驗(yàn)算部位。(1)?w計(jì)算
驗(yàn)算部位應(yīng)根據(jù)風(fēng)荷載產(chǎn)生彎曲壓應(yīng)力大小分析確定,故先計(jì)算風(fēng)荷載產(chǎn)生壓應(yīng)力?w Xxxx工程
外墻腳手架施工方案
立網(wǎng)封閉的擋風(fēng)系數(shù)及風(fēng)荷體型系數(shù)參照《建筑結(jié)構(gòu)荷載規(guī)范》近似按以下方法計(jì)算:???3.5?3.5??0.32?1.05?0.19
23.5?3.其中 1.05為考慮筋繩的影響。
?s?1.2??1.2?0.192?0.23
立網(wǎng)傳給立柱的風(fēng)荷載標(biāo)準(zhǔn)值按式(4—4)計(jì)算,風(fēng)壓高度系數(shù)?z按表4—19中B類取
值,當(dāng)H=51.5m時(shí),?z=1.67,計(jì)算風(fēng)荷載:
?k?0.7?z?s?0 =0.7 ×1.67×0.23×0.50=0.14kN/m 2
作用于立柱的風(fēng)線荷載標(biāo)準(zhǔn)值;
qwk =?k×l=0.14×1.8=0.252KN/m
風(fēng)荷載產(chǎn)生的彎矩按式4—33計(jì)算
MW1.4qwk?h2?=1.4*0.252*1.92/10=0.127 KN.m 10
在51.5m高度處立柱段風(fēng)荷載產(chǎn)生彎曲壓應(yīng)力:
?w=MW=0.127*106/(5.08*103)=25 N/mm 2 W
以上計(jì)算結(jié)果說明,風(fēng)荷產(chǎn)生的壓應(yīng)力雖在50m高度處稍大,但此處的腳手架結(jié)構(gòu)自重產(chǎn)生的軸壓應(yīng)力很小,且?w的絕對(duì)值也不大,根據(jù)以上分析,仍應(yīng)驗(yàn)算底層立柱段的穩(wěn)定性。
(2)底層主柱段的軸心壓力
1)腳手架結(jié)構(gòu)自重產(chǎn)生的軸心壓力NGK:
由表4—38查得一個(gè)柱距范圍內(nèi)每米高腳手架結(jié)構(gòu)自重產(chǎn)生的軸心壓力標(biāo)準(zhǔn)值:
gK=0.125KN/m2 Xxxx工程
外墻腳手架施工方案
則51.5高的腳手架結(jié)構(gòu)自重產(chǎn)生軸心壓力標(biāo)準(zhǔn)值:
NGK=H·gK =51.5×0.125=6.44KN
2)腳手架活荷載產(chǎn)生的軸心壓力:
根據(jù)腳手架高度51.5m,按本章4.4.2之四要求,腳手板共15層,查表4—39得腳手板產(chǎn)生軸心壓力:
NQ1K=0.5?lb?0.3??l?QP=0.5(0.70+0.3)×1.2×0.3×15=2.7KN 腳手架的防護(hù)材料產(chǎn)生軸心壓力,查表4-40得: NQ2K`=0.228KN,安全網(wǎng)自重:0.01×1.5×50=0.75KN 則NQ2K=0.228KN+0.75KN=0.978 KN 根據(jù)裝修用途腳手架,兩層同時(shí)操作,施工均布荷載Qk=2×2.0=4.0kN/m2,查表4—41得施工荷載產(chǎn)生軸心壓力: NQ3k=4.06KN
根據(jù)公式(4—32),荷載產(chǎn)生軸心壓力標(biāo)準(zhǔn)值為
?Ni?1nQiK = NQ1k + NQ2k + NQ3k=2.7+0.978+4.06=7.738 KN
3)根據(jù)公式(4—31)立柱軸心壓力設(shè)計(jì)值,n1.2N=NGK?1.4?NQiK=1.2*6.44/0.75+1.4*7.738=21.13KN k1i?1(分母k1根據(jù)H=51.5m,查表4-35得k1=0.75)
(3)立柱穩(wěn)定性驗(yàn)算
立網(wǎng)封閉時(shí),根據(jù)公式(4—32),立柱穩(wěn)定應(yīng)滿足下式:N≤?A?fc??w?
查手冊(cè),φ48×3.5鋼管,對(duì)?=0.336,A=4.890cm2,fc=180N/mm2,W=5.08 cm3,代入上式:
?A?fc??w?=O.336×4.89×102(180-8.96)×10-3 Xxxx工程
外墻腳手架施工方案
=28.10KN>N=21.13kN 立柱滿足要求。
(4)連墻桿采用φ48×3.5鋼管,連墻桿的計(jì)算長(zhǎng)度可取腳手架的離墻距離,lh=500 mm,因此長(zhǎng)細(xì)比?=
lh=51.5/1.58=32.6,查表4-37A,?=0.912,i風(fēng)荷載產(chǎn)生的水平力設(shè)計(jì)值:Hw =?kAW=1.4×3.6×4.5=3.1752KN NH =Hw+3.0=3.1752 +3.0=6.1752 KN
≤?Afc=0.912×4.89×102×210=93.653 KN 連墻桿穩(wěn)定荷載能力夠。
φ8鋼筋的受拉力:N=Afc=50.27×210=10556 N =10.556 KN
≥Hw+3.0=3.1752 +3.0=6.1752 KN
4.鋼絲繩驗(yàn)算
鋼絲繩拉吊按實(shí)際卸荷最大高度為2~7層共六層樓高,即3.036=18米,n1=18/1.9=10步架高,平橋也共12步,按兩層同時(shí)施工計(jì)算。1)腳手架結(jié)構(gòu)自重產(chǎn)生的軸心壓力NGK:
由表4—38查得一個(gè)柱距范圍內(nèi)每米高腳手架結(jié)構(gòu)自重產(chǎn)生的軸心壓力標(biāo)準(zhǔn)值:
gK=0.125KN/m2
則18米高的腳手架結(jié)構(gòu)自重產(chǎn)生軸心壓力標(biāo)準(zhǔn)值:
NGK=H·gK =18×0.125=2.25KN 2)腳手架活荷載產(chǎn)生的軸心壓力:
腳手板共6層,查表4—39得腳手板產(chǎn)生軸心壓力:
NQ1K=0.5(0.70+0.3)×1.2×0.3×6=1.08KN Xxxx工程
外墻腳手架施工方案
腳手架的防護(hù)材料產(chǎn)生軸心壓力,查表4-40得: NQ2K`=0.228KN,安全網(wǎng)自重:0.01×1.5×18=0.27KN 則NQ2K=0.228KN+0.27KN=0.498KN 根據(jù)裝修用途腳手架,兩層同時(shí)操作,施工均布荷載Qk=2×2.0=4.0kN/m2,查表4—41得施工荷載產(chǎn)生軸心壓力:NQ3k=4.06KN
根據(jù)公式(4—32),荷載產(chǎn)生軸心壓力標(biāo)準(zhǔn)值為
?Ni?1nQiK = NQ1k + NQ2k + NQ3k=1.08+0.498+4.06=5.638 KN
3)根據(jù)公式(4—31)立柱軸心壓力設(shè)計(jì)值,n1.21.2?2.25?1.4?5.638=11.493KN N=NGK?1.4?NQiK=0.75k1i?1則取P1=P2=5.75KN,T2=P15.755.75 ===5.98 KN cos?cos?90?74?0.96查建筑施工手冊(cè)2,本工程選用規(guī)格為6319,繩芯Ⅰ型鋼絲繩,查手冊(cè)表14-2選φ14,F(xiàn)g ——鋼絲繩鋼絲破斷拉力總和, φ14鋼絲繩公稱抗拉強(qiáng)度1400 N/mm2為125 KN。
K—— 鋼絲繩使用安全系數(shù),按規(guī)范取
K=6
?——考慮鋼絲繩鋼絲受力不均勻的鋼絲破斷拉力換算系數(shù),查手冊(cè)選a=0.85 ?Fg0.85?125
則:Fg≥= =13.28 KN
8K大于鋼絲繩的最大拉力5.98 KN,安全。5.吊環(huán)驗(yàn)算 Xxxx工程
外墻腳手架施工方案
工程結(jié)構(gòu)上預(yù)埋吊環(huán)的計(jì)算: 根據(jù)《混凝土結(jié)構(gòu)設(shè)計(jì)規(guī)范》(GBJ10—89)第7、8、9條規(guī)定,吊環(huán)應(yīng)用Ⅰ級(jí)鋼筋制作,嚴(yán)禁使用冷加工鋼筋,吊環(huán)焊接在鋼板上的封閉環(huán),每個(gè)吊環(huán)可按兩個(gè)截面計(jì)算,吊環(huán)拉應(yīng)力不應(yīng)大于50N/㎜2。
一個(gè)吊環(huán)承受內(nèi)、外立柱上兩條鋼絲繩的拉力,安全系數(shù)取3.5倍,本工程選用φ16鋼筋吊環(huán),吊環(huán)鋼筋截面積201㎜2, 210N/m23201㎜2=42210N=42.210 KN
≥3.5311.493㎜2 =40.223 KN
所以,安全。
PPP2T2P27002002
Xxxx工程
外墻腳手架施工方案
吊環(huán)拉結(jié)筋鋼絲繩
十一、腳手架搭設(shè)示意圖
腳手架墊板厚砼墊層排水溝夯實(shí)地基附圖一 腳手架基礎(chǔ)
Xxxx工程
外墻腳手架施工方案
剪刀撐滿掛阻燃密目式安全網(wǎng)拉結(jié)筋短鋼管排柵立桿20045°外腳手架搭設(shè)立面外排柵拉結(jié)大樣滿掛阻燃密目式安全網(wǎng)外腳手架搭設(shè)平面示意附圖二
吊料平臺(tái)立面圖 Xxxx工程
外墻腳手架施工方案
第二篇:腳手架搭設(shè)施工方案
腳手架搭設(shè)施工方案
一、編制說明
為了確保武漢佳源花都三期27#樓工程的施工安全,給操作人員創(chuàng)造一個(gè)良好的操作環(huán)境,避免事故發(fā)生,保證外腳手架搭設(shè)使用安全管理,同時(shí)在本工程的腳手架搭拆過程中,更好地利用規(guī)范規(guī)定的要求,達(dá)到穩(wěn)固、美觀。
本方案作為武漢佳源花都三期27#樓工程腳手架工程搭拆施工的指導(dǎo)和安排。
二、編制依據(jù)
1、《建筑施工扣件式鋼管腳手架安全技術(shù)規(guī)范》(JG130-2002);
2、《建筑施工安全檢查標(biāo)準(zhǔn)》(JGJ59-99);
3、《建筑安裝工人安全技術(shù)操作規(guī)程》(JGJ22-85);
4、《鋼管腳手架扣件》(JGJ22-85);
5、本工程的《施工組織設(shè)計(jì)》;
三、概要說明
本工程五層向下為落地架,五層以上采用14#工字鋼挑架,落地架與挑架搭設(shè)參數(shù)一致,落地架搭設(shè)雙排架,內(nèi)立桿距離結(jié)構(gòu)外墻皮400mm,與主體結(jié)構(gòu)連接點(diǎn)的距離,按二步三跨布置,每根連墻桿控制腳手架的面積不超過40平方米,腳手架鋼管采用直徑為48mm,壁厚3.5mm。
四、管理目標(biāo)
1、安全目標(biāo):本腳手架在搭設(shè)過程中,安全事故為“零”。
2、質(zhì)量目標(biāo):按照《建筑施工扣件式鋼管腳手架安全技術(shù)規(guī)范》(JGJ130-2002)的要求,搭設(shè)規(guī)范、穩(wěn)固、連接牢固、拉結(jié)到位、外型美觀,驗(yàn)收一次合格。
3、文明施工目標(biāo):做到工完料盡場(chǎng)地清,達(dá)到“省級(jí)文明工地”的驗(yàn)收標(biāo)準(zhǔn)。
五、搭設(shè)措施
1、組織措施:
項(xiàng)目部成立懸挑架搭設(shè)安全領(lǐng)導(dǎo)小組,設(shè)組長(zhǎng)一人,成員二人,具體分工如下:組長(zhǎng):項(xiàng)目經(jīng)理李艷明,負(fù)責(zé)腳手架搭設(shè)所需資源的配備,協(xié)調(diào)和技術(shù)交底參加驗(yàn)收。副組長(zhǎng):項(xiàng)目部技術(shù)負(fù)責(zé)人李英強(qiáng),負(fù)責(zé)腳手架工程的施工方案技術(shù)交底,進(jìn)行過程監(jiān)督,按規(guī)范標(biāo)準(zhǔn)組織驗(yàn)收。
成員:項(xiàng)目部安全員孔慶雄,負(fù)責(zé)腳架搭設(shè)的指導(dǎo),安全教育,過程控制,參加驗(yàn)收,
第三篇:腳手架搭設(shè)施工方案(中英文)
目
錄 Directory
一、施工地點(diǎn):Job location....................................................................................1
二、參照標(biāo)準(zhǔn): Basis of compiling...................................................................2
三、材料標(biāo)準(zhǔn):Material streamlined specification.......................2
(一)鋼管:Steel pipe..............................................................................................2
(二)扣件:Fastener.................................................................................................3
(三)腳手板:Scaffold board..............................................................................3
(四)安全網(wǎng):Protecting net................................................................................3
四、施工工藝:Construction technique...................................................3
(一)施工準(zhǔn)備:Preparations for construction..........................................3
(二)腳手架搭設(shè)的要求:Requirement of scaffold...............................4
A、立桿構(gòu)造要求:Vertical.......................................................................5 B、縱向水平桿的構(gòu)造要求:Longitudinal horizontal bracing....5 C、橫向水平桿的構(gòu)造要求:Transverse horizontal bracing........6 D、腳手板的設(shè)置:Scaffold board laying..............................................6 E、剪刀撐:X-bracing.......................................................................................7 F、扣件:Fastener................................................................................................7
(三)腳手架的使用:Requirement of use the scaffold..........................8
(四)腳手架的拆除:Demolition the scaffold...........................................8
五、注意事項(xiàng):Notice proceeding.................................................................8
一、施工地點(diǎn):Job location ****化工區(qū)工業(yè)氣體二期管道設(shè)備保溫工程
**** caojing HYCO1 STEP-2 insulation project
二、參照標(biāo)準(zhǔn): Basis of compiling JGJ130-2001
建筑施工扣件式鋼管腳手架安全技術(shù)規(guī)范
《Steel pipe scaffold safety code of building construction with the fastener》
三、材料標(biāo)準(zhǔn):Material streamlined specification
(一)鋼管:Steel pipe
1、腳手架鋼管采用外徑48mm,壁厚3.5mm,橫向水平桿≤2200mm,其他桿≤6500mm,每根鋼管不應(yīng)大于25kg。
2、鋼管表面應(yīng)平直光滑,不應(yīng)有裂縫、結(jié)疤、分層、錯(cuò)位、硬彎、毛刺、壓痕和深的劃道。
3、鋼管的外徑、壁厚、端面等的偏差,應(yīng)分別符合《建筑施工扣件式鋼管腳手架安全技術(shù)規(guī)范》(JGJ130-2001)的有關(guān)規(guī)定。
1.The external diameter of the steel pipe is 48mm, and thickness of pipe wall is 3.5mm.Transverse horizontal bracing shall be less than 2200mm,others less than 6500mm,and every steel pipe shall be less than 25kg.2.The surface of the steel pipe shall be smoothness, and has not the crack, dogs ear, delaminating, burr and deep nick etc.3.The deviation of the steel pipe, as the external diameter, thickness of pipe wall, port etc, shall be accord the code 《Steel pipe scaffold safety code of building construction with the fastener》
(二)扣件:Fastener
1、扣件采用48型??奂念愋桶ǎ褐苯强奂⑿D(zhuǎn)扣件、對(duì)接扣件、防滑扣件。
2、腳手架采用的扣件,其材質(zhì)應(yīng)符合國(guó)家現(xiàn)行標(biāo)準(zhǔn)。
1.Fastener adopt the type of 48,and the types include the right-angle, circumgyrate, butt joint, and slip-resistance.2.The fastener of the scaffold shall be accord the GB code.(三)腳手板:Scaffold board
1、腳手板采用木質(zhì),每塊質(zhì)量不宜大于30kg。
2、木腳手板應(yīng)采用杉木或松木制作,其材質(zhì)應(yīng)符合國(guó)家現(xiàn)行標(biāo)準(zhǔn)。
3、腳手板的寬度不宜小于200mm,厚度不應(yīng)小于50mm,兩端應(yīng)各設(shè)直徑4mm的鍍鋅鐵絲綁扎兩道。
1.Every scaffold’s quality shall be less than 30kg.2.Scaffold board shall be make of the fir or deal, and accord the GB code.3.The width of the scaffold board shall be over 200mm and thickness over 50mm.On the ends with the 4mm galvanized wire fixing the board.(四)安全網(wǎng):Protecting net 在腳手架施工操作面和護(hù)欄四周圍上防護(hù)網(wǎng)。
It shall be laying safety netting on the operating platform and protecting fence.四、施工工藝:Construction technique
(一)施工準(zhǔn)備:Preparations for construction
1、工程負(fù)責(zé)人應(yīng)按施工組織設(shè)計(jì)中有關(guān)腳手架的要求,向架設(shè)和使用人員進(jìn)行技術(shù)交底。
2、應(yīng)對(duì)所有進(jìn)場(chǎng)材料按規(guī)范進(jìn)行驗(yàn)收,不合格產(chǎn)品不得使用。
3、經(jīng)檢驗(yàn)合格的構(gòu)配件應(yīng)按品種、規(guī)格分類、堆放整齊、平穩(wěn),堆放場(chǎng)地不得有積水。
4、當(dāng)腳手架基礎(chǔ)下有設(shè)備基礎(chǔ)、管溝時(shí),必須采取加固措施。
1.The project manager shall be show the regulations for technical operation on the operation worker, about scaffold in this scheme.2.All the material must be check and acceptance, and no qualification no use.3.The qualification material shall be stack-up regularity and firmness.The place shall be no water.4.When it has equipment foundation, pipe duct under the base of scaffold, it must to be consolidation.(二)腳手架搭設(shè)的要求:Requirement of scaffold
1、所搭設(shè)的腳手架要堅(jiān)固、穩(wěn)定,保證在施工期內(nèi)及各種載荷和氣候條件下不產(chǎn)生變形,不傾斜、不搖晃,安全可靠。
2、根據(jù)搭設(shè)空間,選用適宜的腳手架鋼管長(zhǎng)度。必須有足夠的空間,滿足操作、材料堆放及行人的要求。
3、腳手架的搭設(shè)寬度根據(jù)構(gòu)造要求不能小于1-1.3m,作業(yè)層大橫桿間隔La/2m,小橫桿間隔不能大于縱距的1/2,立桿橫距不能大于1-1.3m,立桿縱距不能大于1.5-2.0m。
4、K201-K202整體腳手架重大約16T,搭設(shè)面長(zhǎng)10.3米寬4.6米高度30米,搭設(shè)時(shí)層面和作業(yè)平臺(tái)連接.支撐以減少整體負(fù)荷, 施工人員上下可利用原有設(shè)施,作業(yè)平臺(tái)和施工平面須使用梯子上下。
1.The scaffold must be firmness, steadiness.During the useful time, it must be no deformation, no inclination, no sway and safety on the kind of load and climate.2.The pipe of the scaffold must be select the suitable length by the building space, and the space must be enough to suitable for operate, material stack-up and passage.3.The width of the scaffold shall be more than 1-1.3m.In the operating lay, the big traverse bar shall be distance La/2m, and the small traverse bar shall be less than 1/2 of longitudinal distance.The traverse distance of vertical shall be less than 1-1.3m, and longitudinal less than 1.5-2.0m.4.The scaffold weight of the equipment K201-K202 is about 16T,length about 10.3m, width 4.6m, and height about 30m.When it’s building, the operating lay join the platform to reduce the load.The worker may be use the device, when they up and down, but on operating lay must be use the ladder.A、立桿構(gòu)造要求:Vertical
1、腳手架必須調(diào)協(xié)縱、橫向掃地桿。縱向掃地桿應(yīng)用直角扣件固定在距底座上皮不大于200mm處的立桿上,橫向掃地桿應(yīng)用直角扣件固定在緊靠縱向掃地桿下方的立桿上。
2、當(dāng)立桿基礎(chǔ)不在同一高度上時(shí),必須較高處的縱向桿向低處延長(zhǎng),與立桿固定,高低差不應(yīng)大于1m。
3、立桿接長(zhǎng)除頂層頂步可采用搭接外,其余各層各步接頭必須采用對(duì)接扣件連接。
1.When the scaffold build, it shall be harmonize the vertically and horizontally pipe.The vertically pipe shall be fix the base with the right-angle fastener and less than 200mm.The horizontally pipe shall be fix under the vertically pipe tightly with the right-angle fastener.2.When the vertical base is not on the same plane, it shall be extend from highness to lowness, and the gap shall be less than 1m.3.When the vertical join each other, it must be use the butt joint fastener, but the top.B、縱向水平桿的構(gòu)造要求:Longitudinal horizontal bracing
1、縱向水平桿宜設(shè)置在立桿內(nèi)側(cè),其長(zhǎng)度不宜小于3跨。
2、縱向水平桿接長(zhǎng)宜采用對(duì)接扣件連接,也可采用搭接。
3、當(dāng)使用木腳手板時(shí),縱向水平桿應(yīng)作為橫向水平桿的支座,用直角扣件固定在立桿上。
1.Longitudinal horizontal bracing shall be inside the vertical and length shall be more than 3 span.2.Longitudinal horizontal bracing may be use the butt joint or lap joint with the fastener.3.When use the scaffold board, longitudinal horizontal bracing is the base of the transverse horizontal bracing, and fix the vertical with the right-angle fastener.C、橫向水平桿的構(gòu)造要求:Transverse horizontal bracing
1、主節(jié)點(diǎn)處必須設(shè)置一根橫向水平桿,用直角扣件扣緊且嚴(yán)禁拆除。
2、主節(jié)點(diǎn)處兩個(gè)直角扣件的中心距不應(yīng)大于150mm。
3、作業(yè)層上非主節(jié)點(diǎn)處的橫向水平桿,宜根據(jù)支承腳手板的需要等間距設(shè)置,最大間距不應(yīng)大于縱距的1/2。
1.The central node must be set one transverse horizontal bracing and forbid backout.2.The two right-angle fastener of the central node shall be less than 150mm each other.3.The transverse horizontal bracing of the other node on the operating lay which is not the central, shall be set base on needs, and the max distance shall be less than 1/2 of the longitudinal.D、腳手板的設(shè)置:Scaffold board laying
1、作業(yè)層的腳手板應(yīng)鋪滿、鋪穩(wěn)。
2、腳手板應(yīng)設(shè)置在三根橫向水平桿上。當(dāng)腳手板的長(zhǎng)度小于2m時(shí),可采用兩根橫向水平桿支承,但應(yīng)將腳手板兩端與其可靠固定,嚴(yán)防傾翻。
3、腳手板可采用對(duì)接平鋪或搭接鋪設(shè)。
4、作業(yè)層上端部腳手板探頭長(zhǎng)度應(yīng)取150mm,其板長(zhǎng)度兩端均應(yīng)與支承桿可靠固定,可用直徑3.2mm的鍍鋅鐵絲固定在支承桿桿上。1.The scaffold board of the operating lay shall be pave the all and fixedness.2.The scaffold board shall be lay on three transverse horizontal bracing, when length less than 2m, it may be use the two, but must fix on the ends.3.The scaffold board may be butt joint or lap joint.4.The ends of the scaffold board on the operating lay shall be overstep about 150mm and fix it on the knighthead with the 3.2mm galvanized wire.E、剪刀撐:X-bracing
1、腳手架的兩端、轉(zhuǎn)角處及每隔5-7個(gè)立桿必須設(shè)剪刀撐,并由底至頂連續(xù)設(shè)置,斜桿與地面的夾角為45°-60°,中間各道剪刀撐之間的凈距不應(yīng)大于15mm。
2、剪刀撐斜桿的接長(zhǎng)宜采用搭接。
1.The scaffold must set the X-bracing on the ends, turns and alternation 5-7 vertical.It must be from bottom to top.The diagonal’s angle is 45-60°to the ground.Each X-bracing distance shall be less than 15mm.2.The distance of X-bracing shall be use the lap joint.F、扣件:Fastener
1、扣件規(guī)格必須與鋼管外徑相同。
2、對(duì)接扣件開口應(yīng)向上或向內(nèi)。
3、各桿件端頭伸出扣件蓋板邊緣的長(zhǎng)度不應(yīng)小于100mm。
1.The spec of fastener must be same as the external diameter of pipe.2.The open of butt joint fastener shall be up or entad.3.The length shall be more than 100mm, which overstep the fastener on the ends of pipe.(三)腳手架的使用:Requirement of use the scaffold
1、沒有經(jīng)過驗(yàn)收的腳手架一律嚴(yán)禁使用。
2、腳手架使用前,必須認(rèn)真檢查腳手架是否完好、牢固,如有異常應(yīng)立即提出整改,合格后方能使用。
3、應(yīng)定期檢查安全防護(hù)措施是否符合要求,扣件螺栓是否松動(dòng)及是否超載等。1.The scaffold must be check and acceptance.2.Before use the scaffold, it must to checked.If it has abnormity, it must to refit.3.It must check the means of safety termly, and must be up to the mustard.(四)腳手架的拆除:Demolition the scaffold
1、應(yīng)根據(jù)現(xiàn)場(chǎng)情況及業(yè)主要求,及時(shí)進(jìn)行腳手架的拆除工作。
2、腳手架拆除前,應(yīng)清除腳手架上雜物及地面障礙物。
3、拆除作業(yè)應(yīng)由上而下逐層進(jìn)行,嚴(yán)禁上下同時(shí)作業(yè)。
4、拆下的腳手架材料應(yīng)及時(shí)運(yùn)走,不亂堆亂放。
5、拆除后,應(yīng)及時(shí)對(duì)現(xiàn)場(chǎng)清理,保持場(chǎng)地清潔。
1.It shall be dismantle the scaffold in time, by the requirement of the owner and case of the locale.2.Before dismantle the scaffold, it must be clean the sundries on scaffold and the abattis on the ground.3.Dismantle the scaffold shall be from up to down.Prohibit labour at one time.4.The material which is dismantle shall be carry out in time.5.After finish, it shall be clean the locale in time, keep up the cleanness.五、注意事項(xiàng):Notice proceeding
1、安裝鋼腳手架時(shí),禁止使用彎曲、壓扁或有裂縫的鋼管,連接部分要完整無損,以防傾倒或移動(dòng)。
2、鋼腳手架的立桿,必須垂直穩(wěn)放在墊木的鋼板上,在安置墊木前要將地面夯實(shí)、整平,并采取防滑措施。
3、搭設(shè)腳手架人員必須按規(guī)定穿戴好防護(hù)用品。
4、安全網(wǎng)應(yīng)按有關(guān)規(guī)定搭設(shè)和拆除。
5、在腳手架使用期間,禁止拆除主節(jié)點(diǎn)處縱、橫向水平桿和縱、橫向掃地桿。
6、搭拆腳手架時(shí),地面應(yīng)設(shè)圍欄和警戒標(biāo)志,并派專人看守,嚴(yán)禁非操作人員入內(nèi)。
1.When build the scaffold, that pipe which has bend, bruising or crack, is prohibit to use.And the part of join shall be intactness.2.When build the vertical, the ground shall be tamp, flattening and avoid slip.3.The workers, who build the scaffold shall be dress the protective measure that necessary.4.Safety netting must be accord the code when it building and demolition.5.During the scaffold use, prohibit demolition the vertically and horizontally bracing on the central node.6.When demolition the scaffold, it shall be set up the sign, and prohibit come into who is not the workers.2013年9月
Sep.9.2013
第四篇:基坑施工腳手架搭設(shè)方案(定稿)
邊坡施工腳手架搭設(shè)方案
一、工程概況
本工程位于……..,屬于高邊坡施工。
根據(jù)實(shí)際情況,以邊坡施工為編制對(duì)象最高為8~10米的外腳手架,密目網(wǎng)圍護(hù)。
二、搭設(shè)材料
1、搭設(shè)腳手架全部采用ф48mm,壁厚3.5mm的鋼管,其質(zhì)量符合現(xiàn)行國(guó)家標(biāo)準(zhǔn)規(guī)定。
2、腳手架鋼管的尺寸、橫向水平桿最大長(zhǎng)度2.2m,其它桿最大長(zhǎng)度為6.5 m,每根鋼管的最大質(zhì)量不小于25KG。
3、鋼管表面平直光滑,無裂縫、結(jié)疤、分層、錯(cuò)位、硬彎、毛剌、壓痕和深的劃痕。
4、鋼管上嚴(yán)禁打孔,鋼管在便用前先涂刷防銹漆。
5、扣件材質(zhì)必須符合《鋼管腳手架扣件》(GB15831)規(guī)定。
①新扣件具有生產(chǎn)許可證,法定檢測(cè)單位的測(cè)試報(bào)告和產(chǎn)品質(zhì)量合格證。對(duì)扣件質(zhì)量有懷疑時(shí),按現(xiàn)行國(guó)家規(guī)定標(biāo)準(zhǔn)《鋼管腳手架扣件》(GB15831)規(guī)定抽樣檢測(cè)。對(duì)不合格品禁止使用。
②舊扣件使用前,先進(jìn)行質(zhì)量檢查,有裂縫、變形的嚴(yán)禁使用,出現(xiàn)滑絲的螺拴進(jìn)行更換處理。
③新、舊扣件均進(jìn)行防銹處理。
6、腳手片用毛竹腳手片,無發(fā)霉、腐蝕。
7、密目式安全網(wǎng)必須有建設(shè)主管部門認(rèn)證的產(chǎn)品。
三、地基與基礎(chǔ)
1、腳手架地基與基礎(chǔ)的施工,根據(jù)腳手架搭設(shè)高度,原土或回填土必須事先進(jìn)行夯實(shí),(地基能承受0.8kg/c㎡的壓力)后用C20砼澆筑厚度大于10cm硬化,2m平面沿桿基礎(chǔ)周邊位置,基礎(chǔ)和能承受上澡結(jié)構(gòu)荷載。
2、腳手架底面標(biāo)高高于自然地坪50mm
3、立桿基礎(chǔ)外側(cè)設(shè)置截面20cm×20cm的排水溝。
四、腳手架設(shè)計(jì)尺寸
1、腳手架底步距為1m,其余每步為1.8m。
2、立桿縱距為1.5m,橫距為1.2m。邊坡上縱、橫距均為1.5m。
3、踢腳桿、防護(hù)桿從第二步起設(shè)置分別為0.3m和1.2m,頂排防護(hù)欄不少于二道,高度分別為0.9m、1.3m。
4、剪刀撐設(shè)置為間距為9m(6跨)一排剪刀撐。
5、連墻桿件設(shè)置為豎向每層、水平向?yàn)樗目纭?/p>
五、縱向、橫向水平桿、腳手板、防護(hù)欄桿、踢腳桿
1、縱向水平桿設(shè)置在立桿內(nèi)側(cè),其長(zhǎng)度不小于3跨。縱向水平桿接長(zhǎng)采用對(duì)接扣件連接,交錯(cuò)布置,兩根相鄰縱向水平接頭設(shè)置相互錯(cuò)開不小于500mm,各接頭中心至最近主節(jié)點(diǎn)的距離不大于縱距的1/3。
2、縱向搭接長(zhǎng)度不小于1米,并等間距設(shè)置3個(gè)旋轉(zhuǎn)扣件固定,端部扣件蓋板邊緣至搭接縱向水平桿桿端的距離不小于100mm。
3、縱向水平桿的各節(jié)點(diǎn)處采用直角扣件固定在橫向水平桿上。
4、橫向水平桿的各個(gè)節(jié)點(diǎn)處必須設(shè)置并采用直角扣件扣接且嚴(yán)禁拆除。
5、腳手片必須垂直于墻面橫向鋪設(shè),滿鋪到位,不留空位。四角用18鐵絲雙股并聯(lián)綁扎,固定在縱向水平桿上,要求綁扎牢固,交接處平整,無空頭板。
6、腳手片底層滿鋪,中間每隔三層,操作層的上下層頂層都必須滿鋪。
7、腳手片外側(cè)自第二步起必須設(shè)1.2m高同材質(zhì)的防護(hù)欄和30cm高處的踢腳桿。
六、立桿
1、每根立桿垂直穩(wěn)放在墊板上。
2、腳手架里立桿距離邊坡凈距為20cm,大于20cm處的須鋪鳳站人腳手片,并設(shè)置平穩(wěn)牢固。
3、腳手架怕須設(shè)置縱、橫向掃地桿??v向掃地桿采用直角扣件固定在距離底座上不大于200處的立桿上。橫向掃地桿亦采用直角扣件固定在緊靠縱向掃地桿下方的立桿上。當(dāng)立桿基礎(chǔ)不在同一高度上時(shí),必須將高處的縱向掃地桿向低處延伸長(zhǎng)兩跨與立桿固定,高低差不小于1m。靠邊坡上方的立桿軸線到邊坡的距離不小于500mm。
4、立桿必須用連墻件與邊坡可靠連接。
5、立桿接長(zhǎng)除頂層步可采用搭接外,其余各層各步接頭必須用①、對(duì)接扣件連接。對(duì)接、搭接均須符合下列規(guī)定。
立桿上的對(duì)接扣件交錯(cuò)布置,兩根相鄰立桿的接頭相互錯(cuò)開,不設(shè)置在同步內(nèi),同步內(nèi)隔一根立桿的兩個(gè)相隔接頭在高度方向錯(cuò)開的距離不小于500,各接頭中心至主節(jié)點(diǎn)的距離不大于步距的1/3。
②、搭接長(zhǎng)度不應(yīng)小于1m,應(yīng)采用不小于2個(gè)旋轉(zhuǎn)扣件固定,端部扣件蓋板的邊緣至桿端距離不應(yīng)小于100mm.七、連接件
1、連接件數(shù)量的設(shè)置,堅(jiān)向間距為每層,橫向間距為4跨。
2、連接件的布置;
①宜靠近主節(jié)點(diǎn)設(shè)置,偏離主節(jié)點(diǎn)的距離不應(yīng)大于300mm。
②應(yīng)從底層第一步縱向水平桿處開始設(shè)置。
③宜優(yōu)先采用菱形布置,也可采用方形,矩形布置。
④采用錨桿與邊坡錨入連接,可采用Φ48鋼管預(yù)埋打入邊坡中,鋼管與鋼管用扣件連接方式。
八、剪刀撐、安全網(wǎng)
1、每道剪刀撐跨越立桿的根數(shù)6根(小于9m)。
2、與地面的傾角宜在450~600之間。
3、應(yīng)在外側(cè)立面整個(gè)長(zhǎng)度和高差上連接設(shè)置剪刀撐。
4、剪刀撐斜桿的接長(zhǎng)宜采用搭接,搭接長(zhǎng)度不應(yīng)小于1m:兩根撐桿須交錯(cuò)布置,同立桿的交錯(cuò)相同。
5、剪刀斜桿應(yīng)用旋轉(zhuǎn)扣件固定在與相交的橫向水平桿的伸出端或立桿上,旋轉(zhuǎn)扣件中心線至主節(jié)點(diǎn)的距離不宜大于150mm。
6、一字型、開口型雙排腳手架的兩端均必須設(shè)置橫向斜撐,中間宜每隔6跨設(shè)置一道。
7、腳手架外側(cè)必須用建設(shè)主管部門認(rèn)證的合格的密目式安全網(wǎng)封閉,且應(yīng)將安全網(wǎng)固定在腳手架外立桿里側(cè),應(yīng)用18#鉛絲張持嚴(yán)密。
九、斜道
1、采用之字型斜道,宜附著外腳手架或建筑物設(shè)置。
2、人行斜道寬度不宜小于1m,坡度宜采用1:3。
3、拐彎處應(yīng)設(shè)置平臺(tái),其寬度不上于斜道寬度。
4、斜道兩側(cè)及平臺(tái)外圍均應(yīng)設(shè)置欄桿及踢腳桿,欄桿高度應(yīng)為1.2m,踢腳桿高度僅為0.3m,內(nèi)側(cè)應(yīng)掛密目網(wǎng)封閉。
5、腳手板橫鋪時(shí),應(yīng)在橫向水平桿下增設(shè)縱向支托桿,縱向支托桿間距不應(yīng)大于500mm。
6、腳手板上應(yīng)每隔250~300mm設(shè)置一根防滑木條,木條厚度宜為20~30mm。
十、避雷裝置
1、腳手架頂部高于2m,四角設(shè)置(長(zhǎng)度大于35m,應(yīng)中間設(shè)幾根)避雷針。
2、用16mm2黃綠雙色銅芯線作引下線,途中用磁瓶,導(dǎo)線綁扎。
3、接地裝置的接地線應(yīng)采用三根導(dǎo)體,在不同點(diǎn)與接地體作電氣連接,垂直接地體應(yīng)采用5×50角鋼、Φ48鋼管或Φ22圓鋼,長(zhǎng)度2.2m,不得采用螺紋鋼,接地電阻不大于4Ω。
十一、腳手架搭設(shè)質(zhì)量和安全要求
腳手架的搭設(shè)應(yīng)將質(zhì)量要求和安全要求有機(jī)地統(tǒng)一起來,確保搭設(shè)過程以及以后的使用和拆除過程的安全與適用。
(一)、搭設(shè)前的準(zhǔn)備工作
1、搭設(shè)前,單位工程負(fù)責(zé)人應(yīng)按腳手架搭拆方案的要求,對(duì)架子工進(jìn)行安全技術(shù)交底,交義雙方履行簽字手續(xù)。
2、熟悉邊坡圖紙和施工現(xiàn)場(chǎng)看,掌握建筑平面和立面的構(gòu)造特點(diǎn),環(huán)境條件,按照<<建筑施工扣件式鋼管腳手架安全技術(shù)規(guī)范>>(JGJ130-2001)中構(gòu)造要求,決定腳手架步距等等,具體施搭設(shè)步驟。
3、材料準(zhǔn)備。對(duì)進(jìn)場(chǎng)的鋼管、扣件、腳手架、安全網(wǎng)等進(jìn)行檢查驗(yàn)收。
4、搭設(shè)場(chǎng)地準(zhǔn)備。根據(jù)腳手架搭設(shè)高度、搭設(shè)場(chǎng)地土質(zhì)情況與現(xiàn)行國(guó)家標(biāo)準(zhǔn)<<地基與基礎(chǔ)工程施工及驗(yàn)收規(guī)范>>(JBJ202)做好腳手架地基與基礎(chǔ)的施工要求,堅(jiān)實(shí)平整,不積水,砼硬化。經(jīng)驗(yàn)收合格后,按方案的要求放線定位。
5、架子工應(yīng)持有效的特種作業(yè)人員操作證上崗作業(yè)。必須戴好安全帽、佩安全帶、必須穿鞋,嚴(yán)禁穿塑料底鞋,皮鞋等硬底易滑的鞋子登高作業(yè)。操作工具及小零件要放在工具袋內(nèi),扎緊衣袖口,領(lǐng)口以及褲腿口,以防鉤掛發(fā)生危險(xiǎn)。
(二)搭設(shè)過程中的質(zhì)量和安全要求
1、扣件式雙排鋼管腳手架搭設(shè)一般順序是:里立桿→外立桿→小橫桿→大橫桿→掃地桿→腳手片→防護(hù)欄桿和踢腳桿→連墻桿→安全網(wǎng)
2、腳手架必須配合施工進(jìn)度搭設(shè),一次搭設(shè)高度不應(yīng)超過相鄰連墻件以上二步,保證搭設(shè)過程中和穩(wěn)定性。
3、腳手架搭設(shè)中累計(jì)誤差超過允許偏差,難經(jīng)糾正,每搭完一步腳手架后,按規(guī)定校步距、縱距、橫距、立桿的垂直度。
4、豎立桿時(shí)應(yīng)由兩人配合操作。大、小橫桿與立桿連接時(shí),也必須兩人配合。
5、當(dāng)有六級(jí)及六級(jí)以上大風(fēng)和霧、雨或雪雨、雪天氣時(shí),應(yīng)停止腳手搭設(shè)作業(yè)。雨、雪后上架作業(yè)應(yīng)注意防滑,并采取防滑措施。
6、非操作層腳手架上嚴(yán)禁堆放材料,且必須保持清潔,操作層腳手架上材料堆放不能集中,不能超高,堆放要穩(wěn)固,每平方米的堆放不得超過300kg,工作完成后及時(shí)清除干凈。
7、腳手架搭設(shè)后由施工企業(yè)組織分段驗(yàn)收(一般不超過3步架),辦理驗(yàn)收手續(xù)。驗(yàn)收表中應(yīng)寫明驗(yàn)收的部位,內(nèi)容量化,驗(yàn)收人員履行驗(yàn)收簽字手續(xù)。驗(yàn)收不合格和,應(yīng)在整改完畢后重新填寫驗(yàn)收表。腳手架驗(yàn)收合格并掛合格牌后方可使用。
十二、拆除方案
1、外架拆除前應(yīng)由單位工程負(fù)責(zé)人召集有關(guān)人員對(duì)架子工程進(jìn)行全面檢查與簽證確認(rèn),建筑物施工完畢,且不需要使用時(shí),腳手架方可拆除。
2、拆除腳手架應(yīng)設(shè)置警戒,張掛醒目的警戒標(biāo)志,禁止非操作人員通行和地面施工人員能行,并有專人負(fù)責(zé)警戒。
3、長(zhǎng)立桿、斜桿的拆除應(yīng)由二人配合進(jìn)行,不宜單獨(dú)作業(yè),下班時(shí)應(yīng)檢查是否牢固,必要時(shí)應(yīng)加設(shè)臨時(shí)固定支撐,防止意外。
4、拆除外架前應(yīng)將通道口上的存留材料雜物清除,按自上而下先裝后拆,后裝先拆的順序。
5、拆除順序?yàn)椋喊踩W(wǎng)→踢腳桿→防護(hù)欄桿→剪刀撐→腳手片→擱柵桿→連墻桿→大橫桿→小橫桿→立桿,自上而下拆除,一步一清,不得采用踏步式拆除,不準(zhǔn)上、下同時(shí)作業(yè)。
6、如遇強(qiáng)風(fēng)、雨、雪等氣候,不能進(jìn)行外架拆除。
7、拆卸的鋼管與扣件應(yīng)分類堆放,嚴(yán)禁高空拋擲。
8、吊下的鋼管與扣件運(yùn)到地面時(shí)應(yīng)及時(shí)按品種規(guī)格堆放整齊。
第五篇:腳手架搭設(shè)施工方案110
腳手架搭設(shè)施工方案
一、編制依據(jù):
建筑施工安全施工標(biāo)準(zhǔn)JGJ59—99,建筑施工高處作業(yè)安全技術(shù)規(guī)范JGJ80—91,密目式安全網(wǎng)GB16909—1997,河北省建筑工程施工安全管理培訓(xùn)教材《高處作業(yè)腳手架》,》《建筑施工手冊(cè)(第二版)》,工程設(shè)計(jì)圖紙,《施工組織設(shè)計(jì)》。
二、工程概況:
阿爾卡迪亞帝景園3#樓為框架、剪力墻結(jié)構(gòu),陶粒砼空心砌塊填充墻。地下一層,地上十一層帶躍層,使用功能:住宅樓,建筑高度36.69米,由A區(qū),B區(qū),C區(qū)三個(gè)單體組成,占地面積1663.58平方米,總建筑面積21943.33平方米。
開工日期:2004年5月10日,竣工日期:2004年12月15日。
三、防護(hù)形式及施工方法:
防護(hù)形式的確定:根據(jù)現(xiàn)場(chǎng)施工平面布置、各單體結(jié)構(gòu)特點(diǎn),外圍護(hù)采用三層一挑的單排腳手架,待結(jié)構(gòu)主體施工完畢后,將架體拆除,利用吊籃做外墻外保溫,腳手架首層沿主體周圍搭設(shè)水平支撐網(wǎng),外架用密目網(wǎng)全封閉。
材料準(zhǔn)備:按物資計(jì)劃表,將4m、6m長(zhǎng)鋼管、各種形式扣件、腳手板、密目網(wǎng)、水平支撐網(wǎng)準(zhǔn)備好,按規(guī)定刷好油漆,橫桿、立桿均刷黃色,剪力撐用鋼管刷成藍(lán)色,兩端1m范圍內(nèi)均刷成黑色,使用前對(duì)各種材料進(jìn)行質(zhì)量檢查。
預(yù)埋件的埋設(shè):在澆筑的一、四、七、十層頂板前,將加工好的吊環(huán)綁扎于頂板內(nèi)作為挑架支撐,按圖示
小橫桿與柱拉結(jié),與立桿間距不大于30cm預(yù)埋φ14鋼筋1500立桿間距1.2m挑桿間距1.5m,外挑1m
腳手架的搭設(shè)方法:搭設(shè)方法如圖2所示,將4m長(zhǎng)的鋼管穿于樓板留設(shè)的吊環(huán)內(nèi),外挑 m,沿建筑物四周每1.2m一根挑桿布置6m立桿用十字扣件與挑桿連接再用橫桿將立桿連接間距1.5m,形成一個(gè)整體,下設(shè)3m長(zhǎng)拉桿將外架與建筑物連接,外掛密目網(wǎng),下設(shè)水平支撐網(wǎng),架體高于 m時(shí),外側(cè)用剪力墻加固,剪力墻搭接不小于1 m,搭接范圍內(nèi)扣件不少于3個(gè)。
變形縫處腳手架的搭設(shè)及防護(hù):
在變形縫剪力墻處每層支設(shè)剪力墻摸板時(shí)預(yù)留φ80預(yù)留孔間距1000mm。,拆摸后用鋼管穿過兩預(yù)留孔,上面滿鋪5cm厚腳手板。同時(shí)搭設(shè)雙排架至上層頂板處,滿鋪5cm厚腳手板,用以上層支設(shè)剪力墻摸板使用。在無剪力墻處,澆注頂板砼前滿鋪腳手板進(jìn)行防護(hù),澆注完拆除梁摸后,應(yīng)重新鋪板固定加以保護(hù)。
腳手板鋼管雙排架剪力墻剪力墻φ80@1000預(yù)留洞2m鋼管400 1800變形縫處腳手架搭設(shè)與防護(hù)
四、腳手架構(gòu)配件質(zhì)量標(biāo)準(zhǔn) ⒈鋼管及扣件
鋼管采用外徑48㎜、壁厚3.5㎜焊接鋼管,采用力學(xué)性能適中的Q235A鋼,其力學(xué)性能應(yīng)符合國(guó)家現(xiàn)行標(biāo)準(zhǔn)《碳素結(jié)構(gòu)鋼》GBT200中Q235A鋼的規(guī)定,扣件應(yīng)符合GB15831-1995《鋼管腳手架扣件》的規(guī)定。
⒉底座
扣件或鋼管腳手架的底座有標(biāo)準(zhǔn)底座和焊接底座兩種,標(biāo)準(zhǔn)底座的材質(zhì)要求同焊接底座的要求,采用Q235A鋼,焊條應(yīng)采用F43型,幾何尺寸應(yīng)符合圖示要求分別如下:
最邊緣作業(yè)點(diǎn)束筋物圖1-1平網(wǎng)安裝示意圖
五、腳手架的用途及極限荷載值
砌筑腳手架,裝修用腳手架及外圍封閉腳手架搭設(shè)高度48米,腳手架外立桿內(nèi)側(cè)滿掛密目網(wǎng)全封閉,腳手架的荷載:結(jié)構(gòu)架3000N/㎡。
六、⒈搭設(shè)順序
放置縱向掃地桿,自角部起依次向兩邊豎立底立桿,底端與縱向掃地桿扣接固定后,裝設(shè)橫向掃地桿并也與立桿固定(固定立桿底端前,應(yīng)吊線確保立桿垂直)每邊豎起3-4根立桿后,隨即裝設(shè)第一步縱向水平桿(與立桿扣接固定)各橫向水平桿(小橫桿靠近立桿并與縱向水平桿扣接固定)接正立桿垂直和水平桿水平使其符合要求后,按40~60NM力擰緊扣件螺栓,形成腳手架心起始段,按要求依次延伸搭設(shè),直至第一步架交圈完成,交圈后再全面檢查一遍腳手架質(zhì)量和地基情況,嚴(yán)格確保設(shè)計(jì)要求和腳手架質(zhì)量設(shè)置連墻桿(或加機(jī)械撐),按第一步架的作業(yè)程序和要求搭設(shè)第二步、第三步……隨搭設(shè)進(jìn)程及時(shí)裝設(shè)連墻件(或加機(jī)力撐)裝設(shè)作業(yè)層間橫桿,(在腳手架橫向桿之間架設(shè)的用縮小鋪板支撐跨度的橫桿)鋪設(shè)腳手架板和裝設(shè)作業(yè)層程桿擋腳板及密目網(wǎng)全封閉。
⒉一般基礎(chǔ)做法
首先進(jìn)行搭設(shè)場(chǎng)地平整、夯實(shí)工作,從建筑物主體向外圍3-5%找坡,回填土夯實(shí)后上面鋪設(shè)厚5㎝、20㎝以上寬木腳手板建筑物周圍長(zhǎng)裝置之后在木腳手板上放置鋼底座,鋼底座上放置立桿,按設(shè)計(jì)的立桿間距進(jìn)行放線定位,鋪設(shè)木腳手板要平移,不得懸空。
⒊排水措施
在距腳手架外排立桿外側(cè)0.5米外設(shè)置一排水溝在最低點(diǎn)設(shè)置積水坑,水流入坑內(nèi),用潛水泵將水排出,排水溝坡度為3-5%。
⒋構(gòu)造要求
⑴立桿的間距、垂直度
立桿間距用1.5米,允許搭設(shè)偏差±5㎝,立桿垂直度允許搭設(shè)偏差±10㎝。
⑵掃地桿設(shè)置
從墊板往上20㎝處設(shè)置掃地桿,掃地桿采用對(duì)接接長(zhǎng),掃地桿在端頭立桿交接處伸出扣件長(zhǎng)度不小于10㎝。
⑶橫桿間距、平整度
橫桿間距采用1.8米,采用對(duì)接方法接長(zhǎng),橫桿兩端高差,不能超過2㎝,縱向水平桿全長(zhǎng)平整度不能超過±10㎝。
⑷立桿、橫桿接長(zhǎng)的詳細(xì)做法
立桿上的對(duì)接扣件應(yīng)交錯(cuò)布置,兩個(gè)相鄰立桿的接頭不應(yīng)設(shè)在同步同跨內(nèi),兩相鄰立桿接頭在高度方向錯(cuò)開的距離不應(yīng)小于500㎜,各接頭中心距立節(jié)點(diǎn)的距離不應(yīng)大于步距的1/3。
縱向水平桿對(duì)接接頭應(yīng)交錯(cuò)布置,不應(yīng)設(shè)在同步,同跨內(nèi)相鄰接頭水平距離不應(yīng)小于500㎝,并應(yīng)避免設(shè)在縱向水平桿的跨在(見附圖)
水平網(wǎng)橫桿立桿圖1-2 6寬水平網(wǎng) ⒌架體與建筑的結(jié)構(gòu)的拉結(jié)要求 ⑴構(gòu)造形式
采用剛性連接方式,連墻件的連墻桿采用兩根50㎝短管用直角扣件中間夾墊木因定于墻上,具體做法見附圖。安全網(wǎng)鋼絲繩斜桿橫桿鋼絲繩圖1-3層間網(wǎng)支搭示意圖 ⑵布置要求
連墻桿在垂直間距不應(yīng)大于4米,水平間距不大于6米的位置上設(shè)置,設(shè)置時(shí)易靠近立節(jié)點(diǎn),距離不應(yīng)大于30㎝,必須從底部第一根縱向水平桿處開始設(shè)置,布設(shè)形式可以采用花排,也可采用并排,宜優(yōu)先采用花排,門窗洞口采用短向拉結(jié)鋼管長(zhǎng)度過門窗洞口邊緣250㎜以上。
七、剪刀撐的搭設(shè)方法
在建筑物四周轉(zhuǎn)交外必須設(shè)置剪力撐,每道剪力撐跨立柱的根數(shù)宜在5-7根之間,每道剪力撐的寬度不應(yīng)小于4跨,且不小于6米,斜桿與地面的傾角宜化45~60之間,由底部橫向連續(xù)設(shè)置,中間每道剪力撐的凈距不應(yīng)大于15米。
剪刀撐斜桿應(yīng)用旋轉(zhuǎn)扣件固定在與之相交的橫向水平桿的伸出端或立柱上,旋轉(zhuǎn)扣件中心線距端點(diǎn)的距離不應(yīng)大于15㎝,剪力撐接長(zhǎng)采用搭接接長(zhǎng),搭接長(zhǎng)度不小于100㎝,用3個(gè)扣件等距離布置,扣件扣在鋼管端頭處不小于10㎝,剪刀撐下端一定要落地。
八、小橫桿的設(shè)置
每一端點(diǎn)處必須設(shè)置一根橫向水平桿并采用直角扣件扣緊在縱向水平桿上部,端頭處伸出長(zhǎng)度不小于10㎝立桿軸線偏離立節(jié)點(diǎn)的距離不應(yīng)大于150㎝,在雙排架中,靠墻一側(cè)的外伸長(zhǎng)度不應(yīng)大于50㎝。
九、腳手板的防護(hù)欄桿
腳手板一般應(yīng)設(shè)置3根小橫桿上,要鋪滿、鋪密,在兩側(cè)設(shè)置180㎜以上高踢腳板,操作層上部護(hù)欄1.2米高,下部防護(hù)欄距踢腳板0.6米處。
十、腳手架體與建筑物之間封閉辦法 ⒈密目網(wǎng)垂直封閉 ⑴密目網(wǎng)的質(zhì)量要求
要四證齊全,要有阻燃性能,其續(xù)燃、阻燃時(shí)間均不得大于4秒,要符合GB16909的規(guī)定,每10㎝×10㎝=100㎝的面積上有2000個(gè)以上的網(wǎng)目。
0⑵密目網(wǎng)貫穿試驗(yàn)
做耐貫穿試驗(yàn)時(shí)將網(wǎng)與地面成30角拉平,在其中正上方3米處用5㎏重的鋼管(管徑48-51㎜)垂直自由落下,不穿透即為合格產(chǎn)品。
⑶密目網(wǎng)的綁扎方法
用纜繩將密目網(wǎng)綁扎至立桿或大橫桿上,使網(wǎng)與架體牢固的連接在一時(shí)起,纜繩的材質(zhì)應(yīng)符合GB16909的規(guī)定。
⒉兜網(wǎng)封閉
用大眼安全網(wǎng)(平網(wǎng))將腳手架與建筑物之間封閉起來,每隔10米一道。
十一、腳手架的上下通道
腳手架架體要設(shè)置安全通道:⑴馬道寬度不小于1米,坡度比1:3(高:長(zhǎng))為宜;⑵馬道的立桿間距應(yīng)與腳手架相適應(yīng),基礎(chǔ)按腳手架要求處理,立面設(shè)剪刀撐,人行橫道小橫桿間距不超過1.5米;⑶馬道上滿鋪腳手板,板上釘防滑條;⑷設(shè)置護(hù)身欄桿,上部護(hù)身欄桿1.2米,下部護(hù)身欄桿距腳手板0.6米,同時(shí)設(shè)180㎜寬擋腳板。
十二、腳手架的卸料平臺(tái)
卸料平臺(tái)上面掛牌標(biāo)明控制荷載,要有荷載計(jì)算書,要有專門搭設(shè)方案,要嚴(yán)格按照施工方案施工。
十三、腳手架交底與驗(yàn)收
腳手架必須嚴(yán)格按照施工方案搭設(shè),要有嚴(yán)格的技術(shù)交底,要有節(jié)點(diǎn)構(gòu)造詳圖,操作人員必須嚴(yán)格執(zhí)行,所有偏差數(shù)值必須
0控制在允許范圍內(nèi)。
要由專門人員對(duì)已搭設(shè)好的腳手架按照搭設(shè)方案進(jìn)行驗(yàn)收,驗(yàn)收時(shí)要有量的內(nèi)容,如:橫立桿間距的數(shù)值,立桿的垂直度,橫桿的平整度等都應(yīng)詳細(xì)記載在驗(yàn)收記錄當(dāng)中,不能只用符合要求來代替。
十四、腳手架的拆除方法
制定拆除方案:方案應(yīng)包括拆架的步驟和方法,安全措施等,拆除順序應(yīng)遵守由上至下,先搭后拆,后搭先拆的原則,即先拆欄桿,腳手架剪力撐、斜撐,而后小橫桿、大橫桿、立桿并按一步一清的原則依次進(jìn)行,嚴(yán)禁上下同時(shí)進(jìn)行拆除作業(yè),同時(shí)周圍設(shè)圍欄或豎立警戒標(biāo)志并且有專人指揮,以免發(fā)生事故。
十五、腳手架搭設(shè)時(shí)注意事項(xiàng)
⒈外徑48㎜與51㎜的鋼管嚴(yán)禁混合使用;
⒉立節(jié)點(diǎn)處,固定橫向水平桿(或縱向水平桿)剪力撐,橫向支撐等扣件的中必線距立節(jié)點(diǎn)的距離不應(yīng)大于150㎜;
⒊各桿件端頭伸出扣件端頭邊緣的長(zhǎng)度不應(yīng)小于100㎜; ⒋對(duì)接扣件的開口應(yīng)朝向架子的內(nèi)側(cè),螺栓應(yīng)朝上,直角扣件的開口不得朝下,以確保安全。
⒌當(dāng)腳手架外側(cè)遇有低壓電線時(shí),而且外側(cè)邊緣距外電架空線路外側(cè)邊線的安全距離小于規(guī)范規(guī)定時(shí),應(yīng)做專門電防護(hù)方案,并嚴(yán)格執(zhí)行;
⒍上架體作業(yè)人員必須持證上崗,戴安全帽、系好安全帶; ⒎嚴(yán)格按搭設(shè)方案施工,連墻件和剪刀撐應(yīng)及時(shí)設(shè)置,不得滯后超過兩步;
⒏在搭設(shè)過程中,應(yīng)注意調(diào)整腳手架的垂直度,最大允許偏差100㎜。
說
明
施工組織設(shè)計(jì)大全,全套5張光盤,由杭州嘉意德科技有限公司整理銷售。嘉意德公司其他產(chǎn)品介紹如下:
工程竣工資料制作軟件:首家基于word平臺(tái)開發(fā)的資料軟件,具有簡(jiǎn)單易用、功能強(qiáng)大、性能穩(wěn)定等特點(diǎn),涵蓋了施工工程過程中技術(shù)文件、質(zhì)量驗(yàn)收資料、質(zhì)量保證資料、工程管理資料、監(jiān)理資料和安全資料等各類文件、表格的編制和管理。適用于工程中各方主體的相關(guān)人員使用,如工程資料員、監(jiān)理工程師以及工程文件整理、歸檔單位的工程竣工資料管理人員等。嘉意德資料軟件表格樣式齊全,操作簡(jiǎn)便!是全國(guó)版本最全的資料軟件主流品牌,共有70多個(gè)各地方版本及行業(yè)版本,如公路資料、電力資料、節(jié)能資料、水利資料等。
施工安全驗(yàn)算軟件:含腳手架、模板、用水用電、塔吊、基坑支護(hù)、鋼筋支架、結(jié)構(gòu)吊裝、混凝土工程、降排水等九大模塊。是現(xiàn)場(chǎng)安全管理必不可少的軟件之一。軟件將施工安全技術(shù)和計(jì)算機(jī)科學(xué)有機(jī)結(jié)合起來,符合施工現(xiàn)場(chǎng)特點(diǎn)和要求,依據(jù)有關(guān)國(guó)家規(guī)范和地方規(guī)程,根據(jù)常用的施工現(xiàn)場(chǎng)安全設(shè)施類型進(jìn)行計(jì)算和分析,為施工企業(yè)安全技術(shù)管理提供了便捷的計(jì)算工具。同時(shí)生成規(guī)范化專項(xiàng)方案計(jì)算書,為施工組織設(shè)計(jì)的編制提供了可靠的依據(jù)。
標(biāo)書制作與管理軟件:是一個(gè)集標(biāo)書制作與標(biāo)書管理功能于一身的招投標(biāo)軟件,用于快速編制各類標(biāo)書和施工組織設(shè)計(jì)。內(nèi)置模板源自建設(shè)系統(tǒng)各大企業(yè)的實(shí)際工程,設(shè)計(jì)水平高、文字素質(zhì)好。龐大的素材庫(kù)包含工業(yè)、民用、水電、路橋的綜合施工組織總設(shè)計(jì),以及各類結(jié)構(gòu)形式、各種高度的工業(yè)、民用、路橋、水電等單位工程的施工組織設(shè)計(jì),還提供了特種工程、建筑、安裝、乃至鋼結(jié)構(gòu)的施工組織設(shè)計(jì),幾乎囊括了編標(biāo)所需的所有內(nèi)容。
智能網(wǎng)絡(luò)計(jì)劃編制軟件:該軟件系統(tǒng)采用圖形編輯方式,不需畫草圖,不需記住工作的代號(hào),只需用鼠標(biāo)就可以在網(wǎng)絡(luò)圖中進(jìn)行添加、修改工作和調(diào)整邏輯關(guān)系,而不需再去輸入緊前、緊后關(guān)系,并實(shí)時(shí)計(jì)算關(guān)鍵線路,自動(dòng)添加工程標(biāo)尺,橫道圖自動(dòng)生成,非??旖荨⒎奖?。
施工平面圖繪制軟件:本軟件提供了多種繪圖工具,具備強(qiáng)大的繪圖操作功能,并集成了多個(gè)圖遠(yuǎn)庫(kù),包括建筑及構(gòu)筑物庫(kù)、材料及構(gòu)件堆場(chǎng)庫(kù)、施工機(jī)械庫(kù)、交通運(yùn)輸庫(kù)等等,可直接調(diào)用,您只需移動(dòng)鼠標(biāo),就能夠方便繪制出一張完整而又準(zhǔn)確的施工平面圖。
臨時(shí)用電設(shè)計(jì)計(jì)算軟件:是國(guó)內(nèi)第一款對(duì)施工臨時(shí)用電配置設(shè)計(jì)及計(jì)算類軟件,軟件嚴(yán)格按照國(guó)家規(guī)范進(jìn)行編制。采用領(lǐng)先圖形模式進(jìn)行配電設(shè)計(jì),及根據(jù)JGJ46-2005規(guī)范8.1.1條規(guī)定采用三相附和平衡計(jì)算法,使計(jì)算結(jié)果更加合理,軟件還對(duì)配電箱、用電設(shè)備的開關(guān)、漏保、熔斷器等電氣的選擇電流進(jìn)行專門有正對(duì)的計(jì)算(考慮了尖峰電流等情況對(duì)電氣設(shè)備的影響),使選擇的電氣設(shè)備更合理。本軟件采用領(lǐng)先的.Net技術(shù)開發(fā)而成,具有易學(xué)、易用、高效等特點(diǎn)。任何購(gòu)買過施工組織設(shè)計(jì)大全的用戶購(gòu)買以上我公司任一款軟件均按8折優(yōu)惠!