第一篇:監(jiān)理規(guī)劃(閱讀)
都江堰市虹口旅游公路災(zāi) 后 恢復(fù)重建 工程
監(jiān)理規(guī)劃
都江堰市虹口旅游公路災(zāi)后恢復(fù)重建工程監(jiān)理部
編 二 00 八年十二月
標(biāo)準(zhǔn)規(guī)范化施工圖例(一)
標(biāo)準(zhǔn)規(guī)范化施工圖例(二)
目錄
第一篇
監(jiān)理規(guī)劃························································· 1 一、工程概況······························································· 1 1、工程簡(jiǎn)介······························································· 1 2、本項(xiàng)目參建單位························································· 1 3、主要技術(shù)經(jīng)濟(jì)指標(biāo)······················································· 2 4、主要工程數(shù)量··························································· 3 5、材料、試驗(yàn)統(tǒng)計(jì)························································· 4 二、總則································································· 5 1、目的··································································· 5 2、監(jiān)理原則······························································· 5 3、監(jiān)理職業(yè)道德··························································· 5 4、監(jiān)理人員工作守則······················································· 5 5、監(jiān)理目標(biāo)······························································· 5 6、監(jiān)理方針······························································· 5 7、適用范圍······························································· 6 8、改進(jìn)··································································· 6 三、一般規(guī)定······························································ 6 1、監(jiān)理依據(jù)······························································· 6 2、監(jiān)理階段劃分··························································· 6 四、監(jiān)理方案······························································ 8 1、駐地建點(diǎn)及人員安排······················································ 8 2、工作模式······························································· 8 3、監(jiān)理方式······························································· 8 五、監(jiān)理組織機(jī)構(gòu)························································· 9 六、各級(jí)監(jiān)理崗位職責(zé)······················································ 10 1、總監(jiān)理工程師職責(zé)······················································ 10 2、總監(jiān)(總監(jiān)代表)職責(zé)···················································· 10 3、監(jiān)理部道路、結(jié)構(gòu)工程師職責(zé)·············································· 11 4、材試工程師職責(zé)························································· 12 5、測(cè)量工程師職責(zé)························································· 12 6、計(jì)量支付工程師職責(zé)···················································· 13 7、安全監(jiān)理工程師職責(zé)···················································· 13 8、環(huán)保監(jiān)理工程師職責(zé)···················································· 14 9、現(xiàn)場(chǎng)監(jiān)理員職責(zé)························································ 15 七、監(jiān)理制度······························································ 16 1、作息制度······························································· 16 2、請(qǐng)假、考勤制度························································· 16 3、崗前培訓(xùn)制度··························································· 17 4、監(jiān)理部的工作制度······················································· 17 5、會(huì)議制度······························································· 18
6、報(bào)表制度······························································· 18 八、人員進(jìn)退場(chǎng)計(jì)劃························································· 19 九、設(shè)備、設(shè)施進(jìn)退場(chǎng)計(jì)劃···················································· 21 十、各種表格······························································ 21
第二篇
監(jiān)理實(shí)施細(xì)則······················································ 22 通則······································································ 22 一、本項(xiàng)目的重點(diǎn)·························································· 22 二、本項(xiàng)目的難點(diǎn)·························································· 22 三、工程控制······························································ 22 第一章 路基土石方工程···················································· 23 一、范圍··································································· 23 二、路基工程施工監(jiān)理工作流程·············································· 23 三、一般路基施工工作要點(diǎn)·················································· 24 四、路基壓實(shí)······························································ 24 五、路基整形······························································ 25 六、場(chǎng)地清理······························································ 25 七、路基挖方······························································ 27 八、路基填方······························································ 29 第二章
路面工程·························································· 31 一、范圍·································································· 31 二、試驗(yàn)路段······························································ 31 三、路面基層、底基層······················································· 31 四、水泥混凝土路面面層····················································· 33 五、瀝青面層施工監(jiān)理工作要點(diǎn) ············································· 36 第三章
交通工程·························································· 40 一、范圍································································· 40 第四章
橋梁工程························································· 43 一、范圍·································································· 43 二、一般施工監(jiān)理規(guī)則······················································ 43 三、橋梁工程施工監(jiān)理工作流程?!ぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁ?44 四、施工測(cè)量監(jiān)理························································· 44 五、明挖基礎(chǔ)····························································· 46 六、模板································································· 48 七、鋼筋·································································· 48 八、結(jié)構(gòu)混凝土··························································· 48 九、預(yù)應(yīng)力混凝土························································· 51 十、砌體································································· 52 十一、支座······························································· 54 十二、橋梁上部結(jié)構(gòu)安裝···················································· 56 十三、橋面工程··························································· 57 第五章
排水與小型構(gòu)造物·················································· 59 一、范圍·································································· 59 二、施工監(jiān)理的分類(lèi)························································ 59
三、排水與小型構(gòu)造物施工監(jiān)理工作流程······································ 59 四、排水與小型構(gòu)造物的施工監(jiān)理············································ 59 第六章
防護(hù)工程·························································· 63 一、范圍·································································· 63 二、護(hù)坡、護(hù)底(重力式)擋土墻施工監(jiān)理工作流程?!ぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁぁ?63 三、擋土墻································································ 63 第七章 計(jì)量和變更························································· 65 一、計(jì)量流程······························································ 65 二、變更流程······························································ 65 第八章 安全生產(chǎn)和文明施工監(jiān)理措施········································· 67 一、安全生產(chǎn)監(jiān)理措施····················································· 67 二、文明施工和道路保通··················································· 78 附件 1 分項(xiàng)工程監(jiān)理程序使用說(shuō)明············································ 80 附件 2 路基、路面壓實(shí)度評(píng)定··············································· 82 附件 3 水泥混凝土彎拉強(qiáng)度評(píng)定·············································· 84 附件 4 水泥混凝土抗壓強(qiáng)度評(píng)定·············································· 85 附件 5 水泥砂漿強(qiáng)度評(píng)定···················································· 87 附件 6 半剛性基層和底基層材料強(qiáng)度評(píng)定······································ 88 附件 7 路結(jié)構(gòu)層厚度評(píng)定···················································· 89 附件 8 路基、柔性基層、瀝青路面彎沉值評(píng)定·································· 90
第一篇
監(jiān)理規(guī)劃
一、工程概況1、工程簡(jiǎn)介
2008 年“5.12”汶川大地震中,都江堰作為重災(zāi)區(qū)之一,許多公路受地震影響,公路沿線(xiàn)的山體產(chǎn)生了大量的崩塌和滑坡,導(dǎo)致路面開(kāi)裂、交通受損,嚴(yán)重的制約了該區(qū)正常生產(chǎn),對(duì)當(dāng)?shù)厝嗣袢罕娚詈吐糜问聵I(yè)的發(fā)展帶來(lái)了很大影響,為了響應(yīng)國(guó)家盡快救災(zāi)恢復(fù)正常生產(chǎn)的號(hào)召,公司承擔(dān)了都江堰紫坪鋪鎮(zhèn)至麻柳坪附近,路線(xiàn)全長(zhǎng) 25.640 ㎞的公路災(zāi)后重建的監(jiān)理工作,該公路為都江堰市虹口旅游公路。
本項(xiàng)目位于龍門(mén)山斷裂帶上,地震前時(shí)有危巖落石現(xiàn)象發(fā)生。加上受“5.12”特大地震影響,本路破壞嚴(yán)重,其中手爬巖至峽口巖段尤為突出,地震使山體破碎,產(chǎn)生大量的塌方,形成山體坍塌面最高處達(dá) 450M,同時(shí)隨時(shí)伴有嚴(yán)重的危巖、落石發(fā)生,如進(jìn)行徹底整治,難度大。本項(xiàng)目一直沿白沙河左岸進(jìn)行,白沙河岸坡陡峻,河谷水流急,給災(zāi)后重建帶來(lái)一困難。根據(jù)現(xiàn)場(chǎng)勘測(cè)得知,起點(diǎn)至八角廟段原路路基寬度在 7.0M~7.5M 之間,路線(xiàn)基本上能達(dá)到設(shè)計(jì) 30 ㎞/h 的三級(jí)公路標(biāo)準(zhǔn),局部地段路線(xiàn)只能達(dá)到四級(jí)公路標(biāo)準(zhǔn);八角廟至 路線(xiàn)終點(diǎn)原路路基寬度在 4.0M~5.5M 之間,為等外級(jí)景區(qū)公路。
本項(xiàng)目分為三個(gè)標(biāo)段,第一標(biāo)段起于都江堰市紫坪鋪鎮(zhèn),終于久紅村;第二標(biāo)段起于久紅村,終于紅色村;第三標(biāo)段起于紅色村,終于黃坡。全線(xiàn)共設(shè) 2 處斷鏈,斷鏈樁號(hào)(K7+760=K7+843.226,長(zhǎng)鏈 83.226 米,K11+650=K11+655.696,長(zhǎng)鏈 5.696 米)道路起點(diǎn)坐標(biāo)(N=21379.624,E=24969.456;道路終點(diǎn)坐標(biāo)N=8117.203,E=12600.202)本項(xiàng)目起點(diǎn)至八角廟原則上按設(shè)計(jì)速度 30Km/h,路基寬度7.5m,路面寬度6.5m重建;八角廟至項(xiàng)目終點(diǎn),原則上按設(shè)計(jì)速度20Km/h,路基寬度 4.5m,路面寬度 3.5m 的四級(jí)單車(chē)道公路進(jìn)行恢復(fù)重建。兩側(cè)路肩寬50cm,在 K7+661.27 位置有一座加寬的久紅小橋。
按交委要求,本項(xiàng)目為災(zāi)后恢復(fù)重建,即原則上不改變既有路線(xiàn)形和路基寬度的條件下,進(jìn)行邊坡整治、加固,恢復(fù)交通標(biāo)志及標(biāo)線(xiàn)工程,所采取的工程措施主要是增強(qiáng)邊坡的穩(wěn)定性,降低交通事故的發(fā)生概率。本次重建對(duì)既有公路路寬、路等級(jí)不作調(diào)整。2、本項(xiàng)目參建單位:
業(yè)主單位:都江堰市交通局 設(shè)計(jì)單位:中國(guó)華西工程設(shè)計(jì)建設(shè)有限公司 監(jiān)理單位:重慶中宇工程咨詢(xún)監(jiān)理有限公司 施工單位:1、貴州建工集團(tuán)總公司 2、攀枝花公路建設(shè)有限公司 3、攀枝花公路橋梁工程總公司3、主要技術(shù)經(jīng)濟(jì)指標(biāo)
序號(hào) 指標(biāo)名稱(chēng) 單位 數(shù)量 備注 1 2 3 4 5
一、基本指標(biāo)
公路等級(jí) 級(jí) 三級(jí)公路 旅游公路 2 計(jì)算行車(chē)速度
30交通量 輛/晝夜
征用土地 畝
臨時(shí)用地(棄土場(chǎng)用地)畝
預(yù)算總額 萬(wàn)元 9143.96
二、路線(xiàn)路線(xiàn)總長(zhǎng) 公里 25.724路線(xiàn)增長(zhǎng)系數(shù)
1.424平均每公里交點(diǎn)數(shù) 個(gè) 11.984平曲線(xiàn)最小半徑 米 9.4 回頭曲線(xiàn)處 11 回頭曲線(xiàn) 個(gè) 5回頭曲線(xiàn)最小半徑 米 9.4平曲長(zhǎng)占路線(xiàn)總長(zhǎng) % 49.530直線(xiàn)最大長(zhǎng)度 米 486.645最大縱坡 %/處 10.22/1 盤(pán)山公路 16 最短坡長(zhǎng) 米/處 60豎曲線(xiàn)長(zhǎng)占路線(xiàn)總長(zhǎng) % 33.383平均每公里終坡變更次數(shù) 次 8.786豎曲線(xiàn)最小半徑
凸形 米/個(gè) 300/4
凹形 米/個(gè) 300/1
三、路基路面土石方數(shù)量
(1)土方 立方米 720770
(2)石方 立方米 1293950平均每公路土石方
(1)土方 立方米
2812
(2)石方 立方米
5048排水及防護(hù)工程
⑴擋土墻 立方米 20613.5
⑵路基、路面排水 立方米 7906.2路面結(jié)構(gòu)類(lèi)型
⑴水泥混凝土路面平方米 67200
⑵瀝青混凝土路面平方米 89887
四、橋梁涵洞設(shè)計(jì)車(chē)輛荷載
公路 II 級(jí)橋面凈寬 米 11.8小橋 米/座 5.8∕1涵洞 米/道
利用(新建 4 道)平均每公里橋梁長(zhǎng)度
0.225平均每公里涵洞數(shù)量 到/公里 2.527
五、路線(xiàn)交叉平面交叉 處 34
六、沿線(xiàn)設(shè)施及其它 米/處 ∕
安全設(shè)施 千米 25.7244、主要工程數(shù)量
序號(hào) 項(xiàng)目名稱(chēng) 單位 數(shù)量 一 路線(xiàn)總長(zhǎng) 公里 25.724 二 路基挖方 立方米 201.472 三 路基填方 立方米 ∕ 四 硬路肩 立方米 1772.5 五 涵洞 道 65 六 擋土墻 立方米 17170 七 水泥穩(wěn)定級(jí)配碎石基層平方米 30937 八 水泥混凝土路面平方米 30937
九 橋梁 米/座 5.8/15、材料、試驗(yàn)統(tǒng)計(jì)
類(lèi)別 材料 名稱(chēng) 工程數(shù)量(m3)備注 原材料 細(xì)集料 天然砂 /
粗集料 破碎卵石 /
碎石 258571
水泥
硅酸鹽水泥 普通硅酸鹽水泥 /
鋼材(kg)鋼筋 19600
焊接鋼筋 /
錨夾具 /
鋼絞線(xiàn) 7739
標(biāo)準(zhǔn)試驗(yàn) 混凝土配合比 C15 片石砼 5.7∕
C20 6761.3 C25 片石砼 1995 C30 71 瀝青混凝土 橋面鋪裝 7.2 砂漿配合比 M5.漿砌片石 9.1∕
M7.5 漿砌片石 158990
M10 51
土工試驗(yàn) 土 /
外加劑 / 膨脹劑 /
二、總則1、目的為順利完成都江堰市虹口旅游公路災(zāi)后恢復(fù)重建項(xiàng)目監(jiān)理服務(wù)工作,加強(qiáng)工程質(zhì)量管理,合理控制工期和工程費(fèi)用,使施工監(jiān)理工作標(biāo)準(zhǔn)化、規(guī)范化、程序化,特制定本規(guī)劃。2、監(jiān)理原則
各級(jí)監(jiān)理人員應(yīng)按照“嚴(yán)格監(jiān)理、熱情服務(wù)、秉公辦事、一絲不茍”的原則,同時(shí)運(yùn)用“程序、靈活、嚴(yán)謹(jǐn)、效率”的管理手段,認(rèn)真落實(shí)執(zhí)行各相關(guān)政策、法規(guī),明確崗位職責(zé),嚴(yán)格檢查制度,認(rèn)真負(fù)責(zé)做好監(jiān)理工作。3、監(jiān)理職業(yè)道德
(1)、樹(shù)立愛(ài)崗敬業(yè)的職業(yè)道德,盡職盡責(zé),一絲不茍,熱情服務(wù)。
(2)、遵守國(guó)家法律、法規(guī)以及業(yè)主、監(jiān)理制定的管理辦法。
(3)、凡事堅(jiān)持實(shí)事求是的原則,做到深入調(diào)查,科學(xué)嚴(yán)謹(jǐn),依法辦事。
(4)、發(fā)揚(yáng)艱苦奮斗、吃苦耐勞的作風(fēng),刻苦鉆研,努力學(xué)習(xí)。4、監(jiān)理人員工作守則
(1)、自覺(jué)遵守法律、法規(guī)和相關(guān)規(guī)定,秉公辦事,不利用職權(quán)謀取私利,不受賄索賄。
(2)、主動(dòng)積極、勤奮刻苦、虛心謹(jǐn)慎、實(shí)事求是,不弄虛作假。
(3)、不允許從事與監(jiān)理項(xiàng)目服務(wù)內(nèi)容無(wú)關(guān)的設(shè)計(jì)、施工材料和設(shè)備供應(yīng)等業(yè)務(wù)活動(dòng)或做中介人。
(4)、不準(zhǔn)介紹親友到施工單位承包工程。
(5)、嚴(yán)禁參與“黃、賭、毒”等非法活動(dòng)。5、監(jiān)理目標(biāo)
嚴(yán)格遵守《公路工程施工監(jiān)理規(guī)范》,認(rèn)真執(zhí)行同業(yè)主簽定的服務(wù)合同。在工期方面,力爭(zhēng)在 2009 年 4 月底全線(xiàn)貫通;在投資方面,為業(yè)主起到好的參謀和衛(wèi)士作用,力爭(zhēng)將總投資控制在預(yù)算范圍內(nèi);在工程質(zhì)量方面,爭(zhēng)創(chuàng)優(yōu)質(zhì)工程,為都江堰市的交通事業(yè)增添光彩。6、監(jiān)理方針
團(tuán)結(jié)全體監(jiān)理人員,艱苦奮斗、勵(lì)精圖治、科學(xué)管理、優(yōu)質(zhì)服務(wù)、不斷創(chuàng)新、質(zhì)量?jī)?yōu)良。7、適用范圍
本方法使用都江堰市虹口旅游公路災(zāi)后重建工程項(xiàng)目的所有工程 8 8、改進(jìn)
本規(guī)劃應(yīng)在監(jiān)理項(xiàng)目運(yùn)行中根據(jù)實(shí)際情況不斷補(bǔ)充完善和調(diào)整,這也符合監(jiān)理服務(wù)合同和業(yè)主的合理要求。
三、一般規(guī)定1、監(jiān)理依據(jù)
(1)、國(guó)家法律和交通部相關(guān)技術(shù)、經(jīng)濟(jì)法規(guī),工程技術(shù)標(biāo)準(zhǔn)、規(guī)范等。
(2)、《公路工程施工監(jiān)理規(guī)范》。
(3)、業(yè)主與承包商簽定的合同文件和業(yè)主與監(jiān)理單位簽定的施工監(jiān)理服務(wù)合同文件。
(4)、業(yè)主的相關(guān)管理辦法或規(guī)定。
(5)、業(yè)主和監(jiān)理工程師認(rèn)可的在工程實(shí)施過(guò)程中有關(guān)的會(huì)議決定、函電、紀(jì)要以及經(jīng)過(guò)監(jiān)理工程師批準(zhǔn)的所有圖紙、文件(含變更設(shè)計(jì)文件)、監(jiān)理工程師下發(fā)的所有指令等。2、監(jiān)理階段劃分
施工監(jiān)理劃分為三個(gè)階段,即施工準(zhǔn)備階段監(jiān)理、施工階段監(jiān)理、交工及缺陷責(zé)任期階段監(jiān)理。
(1 1)、施工準(zhǔn)備階段監(jiān)理
監(jiān)理服務(wù)合同鑒定后,即進(jìn)入施工準(zhǔn)備階段監(jiān)理。在本階段監(jiān)理工程師應(yīng)做好以下工作:
①、熟悉土建施工合同文件及施工圖設(shè)計(jì)文件。
②、制定詳細(xì)的施工監(jiān)理實(shí)施細(xì)則和工作計(jì)劃。
③、熟悉工地現(xiàn)場(chǎng),檢查承包商占用工程場(chǎng)地,審批承包商提交的施工圖。
④、驗(yàn)收承包商測(cè)定的地面線(xiàn)、施工放洋定線(xiàn)等測(cè)量數(shù)據(jù)資料。
⑤、審批承包商提交的施工組織計(jì)劃。
⑥、檢查承包商的質(zhì)保體系,特別是工地試驗(yàn)室的籌建工作。
⑦、核實(shí)承包商材料來(lái)源和施工人員、設(shè)備進(jìn)場(chǎng)情況。
⑧、審批承包商的標(biāo)準(zhǔn)試驗(yàn)。
⑨、召開(kāi)第一次工地會(huì)議。
⑩、檢查承包商的保險(xiǎn)及擔(dān)保,支付動(dòng)員預(yù)付款。
?、審批施工單位的工程開(kāi)工申請(qǐng)報(bào)告,發(fā)布開(kāi)工令。
(2 2)、施工階 段監(jiān)理
施工階段監(jiān)理是施工監(jiān)理工作的重點(diǎn),應(yīng)集中力量做好工程質(zhì)量、進(jìn)度、費(fèi)用監(jiān)理,搞好合同以及信息管理,加強(qiáng)項(xiàng)目控制,以圓滿(mǎn)實(shí)現(xiàn)既定的計(jì)劃目標(biāo)。
(3 3)、交工及缺陷責(zé)任期階段監(jiān)理
入缺陷責(zé)任期階段監(jiān)理。此階段除應(yīng)完成對(duì)工程缺陷的修補(bǔ)、修復(fù)或重建外,還在工程完工或部分(單位、分部)工程完工后,只要簽發(fā)了交工證書(shū)后即進(jìn)應(yīng)做好如下工作:
①、承包商完成工程竣工結(jié)算。
②、督促承包商在規(guī)定的時(shí)間完成竣工資料的編制和移交。
四、監(jiān)理方案、駐地建點(diǎn)及人員安排 該項(xiàng)目從紫坪鋪鎮(zhèn)往里劃分,分為一、二、三個(gè)合同段,駐地建筑該項(xiàng)目的中點(diǎn)位置虹口鄉(xiāng)一農(nóng)家樂(lè)內(nèi),根據(jù)施工的實(shí)際情況,每標(biāo)段配有一名現(xiàn)場(chǎng)監(jiān)理,專(zhuān)業(yè)監(jiān)理對(duì)三個(gè)標(biāo)段進(jìn)行巡視工作。各個(gè)標(biāo)段不分主次、不分輕重,同時(shí)控制和管理。、工作模式 監(jiān)理工作的開(kāi)展實(shí)行“專(zhuān)監(jiān)為主”的工作模式,即路基路面專(zhuān)監(jiān)和結(jié)構(gòu)專(zhuān)監(jiān)組織、協(xié)調(diào)、安排、落實(shí)相關(guān)工作,測(cè)量、實(shí)驗(yàn)專(zhuān)監(jiān)配合、落實(shí)相應(yīng)工作,前述專(zhuān)監(jiān)配合、落實(shí)計(jì)量專(zhuān)監(jiān)相應(yīng)工作,所有專(zhuān)監(jiān)落實(shí)執(zhí)行總監(jiān)安排的工作??紤]到本項(xiàng)目的特殊情況,各個(gè)合同段各設(shè)置一現(xiàn)場(chǎng)監(jiān)理員分管。路基、結(jié)構(gòu)、試驗(yàn)、測(cè)量等獨(dú)立工作能力較強(qiáng),責(zé)任心較大擔(dān)任全程專(zhuān)監(jiān),同時(shí)監(jiān)理部以總監(jiān)交替巡視各合同段工地的方式管理,以保證管理的一致性和不缺位。、監(jiān)理方式 根據(jù)項(xiàng)目規(guī)模不大,技術(shù)難度高,工期短的特點(diǎn),質(zhì)量檢測(cè)方式以“平行檢測(cè)”為主,即監(jiān)理的抽檢和承包人的自檢同時(shí)進(jìn)行,真正實(shí)現(xiàn)全方位、全過(guò)程的監(jiān)理,監(jiān)理的檢查頻率為 20%。平行實(shí)驗(yàn)采取委托實(shí)驗(yàn)的方式進(jìn)行,抽樣、制件和送樣由監(jiān)理完成,試驗(yàn)和出報(bào)告由委托的試驗(yàn)機(jī)構(gòu)完成。
五、監(jiān)理組織機(jī)構(gòu)
說(shuō)明:
1、監(jiān)理組長(zhǎng)由一名監(jiān)理工程師但任,獨(dú)立完成相應(yīng)的管理工作。
2、專(zhuān)業(yè)監(jiān)理工程師巡視三個(gè)合同段。
3、監(jiān)理員即為現(xiàn)場(chǎng)監(jiān)理,以旁站工作為主,其工作主要由對(duì)應(yīng)的路基路面、結(jié)構(gòu)工程師安排,同時(shí)接受其他專(zhuān)監(jiān)的溝通管理。施工階段的監(jiān)理工作以專(zhuān)監(jiān)為主的模式,各專(zhuān)監(jiān)之間密切配合,及時(shí)溝通。
六、各級(jí)監(jiān)理崗位職責(zé)1、總監(jiān)理工程師職責(zé)
(1)全面主持、監(jiān)督和管理本項(xiàng)目的監(jiān)理工作,任免監(jiān)理部所轄各級(jí)監(jiān)理人員、后勤人員,處理違紀(jì)人員。
(2)審批承包商的總體施工進(jìn)度計(jì)劃。
(3)審批承包商的總體施工方案及重大技術(shù)方案。
(4)簽發(fā)工程開(kāi)工令、支付證書(shū)和其他指令。
(5)審批工程變更。
(6)解釋施工合同文件中出現(xiàn)的含糊和異議,裁決諸如爭(zhēng)議、違約等重大合同糾紛。
(7)簽發(fā)暫停施工及許可復(fù)工的通知、處理延期和索賠。
(8)審查、批準(zhǔn)承包商代表及分包人、發(fā)出撤換承包商代表、承包商不稱(chēng)職人員及分包人的決定。
(9)協(xié)調(diào)各承包商和業(yè)主的關(guān)系。
(10)主持召開(kāi)業(yè)主、監(jiān)理工程師聯(lián)席會(huì)議及監(jiān)理工程師例會(huì)。
(11)簽署需外報(bào)、上報(bào)的有關(guān)報(bào)表報(bào)告及監(jiān)理情況通報(bào)等。
(12)主持審查承包商的總體施工進(jìn)度計(jì)劃及工程變更;主持審查承包商的總體施工方案及重大技術(shù)方案;審查處理承包商提交的中期支付證書(shū)、變更、延期及費(fèi)用索賠的質(zhì)檢資料、技術(shù)方案部分。
(13)檢查、督促、指導(dǎo)駐地辦對(duì)質(zhì)量、進(jìn)度、費(fèi)用的控制及對(duì)合同的管理工作。
(14)負(fù)責(zé)組織監(jiān)理部竣工資料的編制工作,參與、協(xié)助項(xiàng)目法人對(duì)工程的交竣工工作,并組織對(duì)工程質(zhì)量進(jìn)行科學(xué)公正的評(píng)定。
(15)負(fù)責(zé)對(duì)缺陷責(zé)任期的監(jiān)理及驗(yàn)收工作。2、副總監(jiān)(總監(jiān)代表)
職責(zé)
(1)根據(jù)合同文件,對(duì)各合同段工程施工進(jìn)行全面監(jiān)督和管理,負(fù)責(zé)監(jiān)理部的正常工作運(yùn)轉(zhuǎn)及人員、設(shè)施、財(cái)物的管理。
(2)根據(jù)監(jiān)理工作的需要向承包商簽發(fā)有關(guān)指令、指示,并報(bào)總監(jiān)備案。
(3)全面熟悉合同文件糾正設(shè)計(jì)圖紙中明顯的錯(cuò)誤,對(duì)在合同執(zhí)行過(guò)程中發(fā)生的問(wèn)題及時(shí)采取解決措施,需要時(shí)應(yīng)向總監(jiān)報(bào)告。
(4)審查承包商的各種施工進(jìn)度計(jì)劃、施工方案。審簽分項(xiàng)工程開(kāi)工報(bào)告,并監(jiān)督承包商施工計(jì)劃的實(shí)施,對(duì)滯后于計(jì)劃工期的工程,應(yīng)督促承包商采取積極的措施或調(diào)整施工計(jì)劃,并及時(shí)上報(bào)總監(jiān)。
(5)按合同文件嚴(yán)格控制施工質(zhì)量,審批原材料的試驗(yàn)成果報(bào)告及各種混合料配和比的設(shè)計(jì)及試驗(yàn)報(bào)告。
(6)審簽承包商的中間計(jì)量支付證書(shū),上報(bào)總監(jiān)。
(7)審核承包商工地的機(jī)械設(shè)備及人員情況,審批承包商的質(zhì)量保證體系及自檢人員;檢查承包商的現(xiàn)場(chǎng)安全保護(hù)措施,對(duì)不合格的安全措施應(yīng)指示承包商限期改正。
(8)對(duì)承包商的工期延期和索賠提供有關(guān)監(jiān)理記錄和證明材料,提出處理意見(jiàn)報(bào)總監(jiān)。
(9)在授權(quán)范圍內(nèi)審查處理工程變更,對(duì)發(fā)生的延期、索賠、分包等問(wèn)題應(yīng)提出處理意見(jiàn),上報(bào)總監(jiān)。
(10)主持定期和不定期的工地會(huì)議,研究并解決施工中的各種問(wèn)題。
(11)完成報(bào)送總監(jiān)的各種報(bào)表、工作報(bào)告。
(12)審查承包商提交的工程交工驗(yàn)收資料,編制合同段監(jiān)理工作總結(jié)報(bào)告,并負(fù)責(zé)組織缺陷責(zé)任期內(nèi)的監(jiān)理工作。
(13)完成由總監(jiān)交辦的其它工作。2、監(jiān)理部道路、結(jié)構(gòu)工程師職責(zé)
(1)在總監(jiān)的領(lǐng)導(dǎo)下,按規(guī)范的要求負(fù)責(zé)本專(zhuān)業(yè)工程的監(jiān)理工作,制定施工過(guò)程中的監(jiān)理計(jì)劃。
(2)審查承包商提出的工程進(jìn)度計(jì)劃和施工組織計(jì)劃,提出審查意見(jiàn)供總監(jiān)審查時(shí)參考,并對(duì)計(jì)劃的執(zhí)行情況進(jìn)行檢查和監(jiān)督。
(3)核對(duì)設(shè)計(jì)圖紙及設(shè)計(jì)資料,當(dāng)發(fā)現(xiàn)圖紙中標(biāo)高、基線(xiàn)、位置尺寸等有遺漏或錯(cuò)誤時(shí),應(yīng)及時(shí)予以改正,在施工過(guò)程中如發(fā)現(xiàn)設(shè)計(jì)圖紙有局部不盡合理之處,應(yīng)及時(shí)向總監(jiān)反映,根據(jù)工地實(shí)際情況會(huì)同設(shè)計(jì)代表,指示承包商作出處理.(4)在單項(xiàng)工程開(kāi)工前,檢查承包商的機(jī)械設(shè)備、人員、施工組織計(jì)劃、施工工藝、工程用料等,提出是否同意開(kāi)工的意見(jiàn)。
(5)審批承包商提出的單項(xiàng)工程原始斷面圖、施工圖、其它臨時(shí)工程圖及變更設(shè)計(jì)圖,對(duì)工程變更應(yīng)報(bào)告總監(jiān)。
(6)審批承包商的檢驗(yàn)申請(qǐng)單,配合材試、測(cè)量工程師,對(duì)承包商施工的工程進(jìn)行抽檢,簽認(rèn)承包商提供的各種中間質(zhì)檢報(bào)告,簽發(fā)一般工程項(xiàng)目、工序的中間交工證書(shū)。
(7)在工程施工過(guò)程中,要經(jīng)常深入工地,詳細(xì)檢查施工的各部位和環(huán)節(jié),及時(shí)處理承包商施工中出現(xiàn)的問(wèn)題,必要時(shí)要向總監(jiān)報(bào)告。
(8)審核承包商遞交的有關(guān)資料,安排制定控制施工質(zhì)量及施工進(jìn)度的各種圖表,管理好施工監(jiān)理原始記錄、技術(shù)擋案。
(9)當(dāng)施工中發(fā)生涉及工程質(zhì)量、工程延期和費(fèi)用索賠等問(wèn)題時(shí)應(yīng)及時(shí)提出處理措施和意見(jiàn)供總監(jiān)處理時(shí)參考。
(10)審簽承包商報(bào)送的中間計(jì)量支付工程變更報(bào)表。
(11)檢查現(xiàn)場(chǎng)監(jiān)理人員的工作,填寫(xiě)監(jiān)理日志并檢查現(xiàn)場(chǎng)監(jiān)理人員的監(jiān)理日志.(12)辦理總監(jiān)安排的其它工作。3、材試工程師職責(zé)
(1)在總監(jiān)的領(lǐng)導(dǎo)下,負(fù)責(zé)本合同段所有的材料控制和工地試驗(yàn)監(jiān)理工作,監(jiān)督工程使用的材料、配件和成品、半成品符合規(guī)定的質(zhì)量要求。
(2)熟悉合同條件、規(guī)范、設(shè)計(jì)圖紙和試驗(yàn)規(guī)程,監(jiān)督工地試驗(yàn)室,具體規(guī)定各類(lèi)試驗(yàn)的規(guī)程、記錄等,督促承包商提供足夠的儀器設(shè)備和人員以便保證按合同的要求控制采料和工地試驗(yàn)。
(3)監(jiān)督承包商按規(guī)范要求的頻率進(jìn)行試驗(yàn),原則上承包商的工地試驗(yàn)和室內(nèi)試驗(yàn)均須有試驗(yàn)監(jiān)理人員旁站。并保證抽檢頻率不低于 20%。
(4)定期或不定期檢查工地試驗(yàn)儀器設(shè)備運(yùn)轉(zhuǎn)是否正常,檢查各種材料的材質(zhì)和規(guī)格是否滿(mǎn)足規(guī)范設(shè)計(jì)要求。
(5)根據(jù)規(guī)范來(lái)審查和評(píng)價(jià)試驗(yàn)結(jié)果。
(6)依據(jù)中心試驗(yàn)室批準(zhǔn)的試驗(yàn)資料,簽認(rèn)標(biāo)準(zhǔn)試驗(yàn)。
(7)全面負(fù)責(zé)試驗(yàn)監(jiān)理的管理工作;所有試驗(yàn)結(jié)果、報(bào)告和其它有關(guān)資料,必須建立檔案,以便隨時(shí)查閱。
(8)按時(shí)報(bào)送試驗(yàn)報(bào)告和試驗(yàn)匯總表,試驗(yàn)匯總表簽字后報(bào)總監(jiān)。
(9)負(fù)責(zé)安排、檢查和指導(dǎo)試驗(yàn)監(jiān)理人員的各項(xiàng)工作。
(10)完成總監(jiān)交辦的其它工作。4、測(cè)量工程師職責(zé)
(1)在總監(jiān)的領(lǐng)導(dǎo)下,配合道路工程師、結(jié)構(gòu)工程師,嚴(yán)格按規(guī)范要求的精
度監(jiān)督承包商放線(xiàn)、放樣,審查批準(zhǔn)承包商測(cè)量?jī)?nèi)外業(yè)成果及道路和構(gòu)造物幾何尺寸、標(biāo)高等。
(2)負(fù)責(zé)檢查承包商對(duì)導(dǎo)線(xiàn)點(diǎn)、水準(zhǔn)點(diǎn)的護(hù)樁設(shè)施保證不受損壞,如有變更需在圖上說(shuō)明。
(3)承包商進(jìn)行施工前測(cè)量時(shí)必須在場(chǎng),操作時(shí)隨時(shí)抽測(cè);各項(xiàng)測(cè)量記錄要認(rèn)真核對(duì),經(jīng)簽認(rèn)后,承包商才可繪制施工圖。
(4)審查承包商的檢驗(yàn)申請(qǐng),經(jīng)現(xiàn)場(chǎng)檢驗(yàn)校對(duì)后,如符合規(guī)范要求的精度,才能簽字認(rèn)可。
(5)配合道路工程師檢查路基工程的土石分界線(xiàn),并督促承包商標(biāo)繪在橫斷面圖上。
(6)協(xié)助道路、結(jié)構(gòu)工程師審核承包商報(bào)送的施工和竣工圖紙,配合道路、結(jié)構(gòu)等各專(zhuān)業(yè)工程師進(jìn)行收方丈量,審核計(jì)算數(shù)據(jù)。
(7)定期督促檢查承包商使用測(cè)量?jī)x器的精度。
(8)完成總監(jiān)交辦的其它工作。5、計(jì)量支付工程師職責(zé)
(1)在總監(jiān)的領(lǐng)導(dǎo)下,負(fù)責(zé)本合同段的合同管理、計(jì)量支付、計(jì)劃統(tǒng)計(jì)報(bào)表等工作。
(2)全面熟悉合同條件、工程量清單、規(guī)范及設(shè)計(jì)圖紙,緊密配合專(zhuān)業(yè)工程師嚴(yán)格按照合同文件和監(jiān)理程序及時(shí)準(zhǔn)確的作好計(jì)量支付和月進(jìn)度報(bào)表工作。
(3)辦理合同執(zhí)行中的施工延期及費(fèi)用索賠、設(shè)計(jì)變更、合同糾紛等事宜。
(4)深入現(xiàn)場(chǎng),隨時(shí)掌握施工現(xiàn)場(chǎng)的工程進(jìn)展情況,審查承包商的相關(guān)報(bào)表,配和各專(zhuān)業(yè)工程師做到數(shù)量真實(shí),計(jì)算準(zhǔn)確。
(5)審核承包商申報(bào)的支付證書(shū),做到每項(xiàng)工程數(shù)量均有簽認(rèn)的檢驗(yàn)單和工程數(shù)量計(jì)算表。工程變更、價(jià)格調(diào)整、材料預(yù)付款、索賠等均有簽認(rèn)的憑證,報(bào)送的購(gòu)貨發(fā)票等應(yīng)有依據(jù)。
(6)負(fù)責(zé)督促承包商及時(shí)準(zhǔn)確的呈報(bào)工程進(jìn)度報(bào)表,并保證在規(guī)定時(shí)間內(nèi)完成審核和簽認(rèn)工作。
(7)參與單價(jià)變更的審查工作。
(8)配合有關(guān)監(jiān)理工程師審查施工進(jìn)度計(jì)劃。
(9)完成總監(jiān)交辦的其它工作。6、安全監(jiān)理工程師職責(zé)
(1)、工程開(kāi)工前,審查施工單位編制的施工組織設(shè)計(jì)中的安全技術(shù)措施或?qū)m?xiàng)施工方案是否符合強(qiáng)制性標(biāo)準(zhǔn),審查重點(diǎn):
①、安全管理和安全保證體系的組織機(jī)構(gòu)。
②、是否訂制了安全生產(chǎn)責(zé)任制、安全管理規(guī)章制度、安全操作規(guī)程。
③、施工單位的安全防護(hù)用具、機(jī)械設(shè)備、施工機(jī)具是否符合國(guó)家有關(guān)安全規(guī)定。
④、是否訂制了施工現(xiàn)場(chǎng) 臨時(shí)用電方案的安全技術(shù)措施和電氣防火施。
施工場(chǎng)地布置是否符合有關(guān)安全要求。
⑤、生產(chǎn)安全事故應(yīng)急救援預(yù)案的訂制情況,針對(duì)重點(diǎn)部位和重點(diǎn)環(huán)節(jié)制訂的工程項(xiàng)目危險(xiǎn)源監(jiān)控措施和應(yīng)急預(yù)案。
⑥、施工人員安全教育計(jì)劃、安全交底安排。
⑦、安全技術(shù)措施費(fèi)用的使用計(jì)劃。
(2)、監(jiān)理工程師應(yīng)審查分包合同中是否明確了施工單位與分包單位各自在安全生產(chǎn)方面的責(zé)任。
(3)、監(jiān)理工程師在巡視、旁站過(guò)程中應(yīng)監(jiān)督施工單位按專(zhuān)項(xiàng)安全施工方案組織施工。對(duì)危險(xiǎn)性較大的工程作業(yè)等要定期巡視檢查。
(4)、督促施工單位進(jìn)行安全生產(chǎn)自查工作、落實(shí)施工生產(chǎn)安全技術(shù)措施,參加施工現(xiàn)場(chǎng)的安全生產(chǎn)檢查。
(5)、建立施工安全監(jiān)理臺(tái)帳。
(6)、分項(xiàng)、分部工程交工驗(yàn)收時(shí),如安全事故的現(xiàn)場(chǎng)處理未完成,不得簽發(fā)《中間交工證書(shū)》。7、環(huán)保監(jiān)理工程師職責(zé)
(1)、審查施工組織設(shè)計(jì)是否按設(shè)計(jì)文件和環(huán)境影響評(píng)價(jià)報(bào)告的有關(guān)要求制訂了施工環(huán)境保護(hù)措施。
(2)、在巡視、旁站中,應(yīng)隨時(shí)檢查施工單位制訂的環(huán)境保護(hù)措施的落實(shí)情況,檢查內(nèi)容:
①、是否落實(shí)了施工環(huán)境保護(hù)責(zé)任人。
②、是否對(duì)施工人員進(jìn)行了環(huán)保教育。
③、施工場(chǎng)地的布設(shè)是否符合相關(guān)環(huán)保要求。
④、職業(yè)危害的防護(hù)措施是否健全。
⑤、施工現(xiàn)場(chǎng)和料場(chǎng)等是否灑水防塵。
⑥、是否按有關(guān)要求采取降噪措施。
⑦、草料堆場(chǎng)設(shè)置環(huán)境的合理性及采取措施減少運(yùn)輸漏灑情況。
⑧、施工廢水、渣土、生活污水、垃圾的處理是否合理。
⑨、是否按照批準(zhǔn)在擬定的取棄土場(chǎng)取棄土,取土后是否采取了有效的排水防護(hù)和植被恢復(fù)措施。
(3)、如發(fā)現(xiàn)施工中存在有關(guān)違反環(huán)保規(guī)定、未按合同要求落實(shí)環(huán)保措施情況,監(jiān)理工程師應(yīng)書(shū)面指令施工單位整改,情況嚴(yán)重的應(yīng)簽發(fā)《工程暫停令》要求施工單位暫時(shí)停工。
(4)、施工中發(fā)現(xiàn)文物時(shí),監(jiān)理工程師應(yīng)要求施工單位依法保護(hù)現(xiàn)場(chǎng),并報(bào)告有關(guān)部門(mén)和建設(shè)單位。
(5)、監(jiān)理工程師應(yīng)要求施工單位依法取得砍伐許可后方可按照砍伐許可面積、株數(shù)、樹(shù)種進(jìn)行砍伐,并注意保護(hù)野生動(dòng)物、植 物。8、現(xiàn)場(chǎng)監(jiān)理員職責(zé)
(1)在總監(jiān)和道路、結(jié)構(gòu)、試驗(yàn)、測(cè)量工程師等的領(lǐng)導(dǎo)下,負(fù)責(zé)指定施工范圍內(nèi)的旁站監(jiān)理工作。
(2)熟悉合同條件、技術(shù)規(guī)范和設(shè)計(jì)圖紙,做到有效的控制施工質(zhì)量,及時(shí)反映現(xiàn)場(chǎng)發(fā)生的問(wèn)題。
(3)在工程施工過(guò)程中,檢查記錄承包商工、料、機(jī)的情況。
(4)嚴(yán)格執(zhí)行現(xiàn)場(chǎng)旁站監(jiān)督的規(guī)定,檢查和認(rèn)可承包商的每道工序,對(duì)不符合規(guī)定的部位要及時(shí)要求承包商糾正,對(duì)隱蔽部位和要返工時(shí)損失較大的部位應(yīng)切實(shí)監(jiān)督。對(duì)工程質(zhì)量存在的問(wèn)題要及時(shí)上報(bào),并及時(shí)向承包商發(fā)出口頭警告,必要時(shí)由總監(jiān)發(fā)出書(shū)面通知。
(5)在專(zhuān)業(yè)工程師的指導(dǎo)下,審簽質(zhì)檢表,核實(shí)承包商遞交的工程量計(jì)算表。
(6)繪制責(zé)任施工地段或部位的質(zhì)量控制和進(jìn)度的各種圖表,按要求做好監(jiān)理記錄、監(jiān)理日志和應(yīng)上報(bào)的各種報(bào)表,定期或不定期的向總監(jiān)、專(zhuān)業(yè)工程師匯報(bào)工作。
(7)參加現(xiàn)場(chǎng)檢驗(yàn)、測(cè)量等工作。
(8)辦理總監(jiān)、道路、結(jié)構(gòu)、隧道、材料工程師交辦的其它工作。
七、監(jiān)理制度1、作息制度
(1)、作息時(shí)間:
上午:7:30 起床
7:30~8:00 早餐
8:30~12:00
上班時(shí)間(8:00~8:30 臨時(shí)早會(huì))
12:00~12:30
午餐 下午:14:30~18:00
上班時(shí)間(夏季:15:00~16:30)
18:00~18:30
晚餐(夏季:16:30~19:00)
晚上:22:30(夏季:23:00)以后,休息時(shí)間(娛樂(lè)終止時(shí)間)
(2)、作息說(shuō)明:
①、早餐最遲時(shí)間為 8:00,過(guò)時(shí)不候,炊事員有權(quán)收拾餐桌;過(guò)時(shí)未吃早飯者自行解決,由此造成上班遲到者記遲到一次。
②、早會(huì)內(nèi)容為情況反映、工作安排、出車(chē)安排及事情通知等,由總監(jiān)主持;如沒(méi)有必要開(kāi)早會(huì),則要求各有事上工地的監(jiān)理工程師 8:00 上工地,過(guò)時(shí)不候。
③、原則上,午餐、晚餐由于工作原因不能回駐地就餐者,應(yīng)提前至少半個(gè)小時(shí)通知炊事員;在外面就餐的監(jiān)理人員應(yīng)在項(xiàng)目部解決,監(jiān)理部將定期給承包人結(jié)帳;如在項(xiàng)目部以外吃飯,必須經(jīng)總監(jiān)的同意;中午在外就餐,嚴(yán)禁飲酒。
④、晚餐過(guò)后為自由活動(dòng)時(shí)間,以學(xué)習(xí)為主,禁止賭博,可以開(kāi)展形式多樣的健康娛樂(lè)活動(dòng),活動(dòng)截止時(shí)間為 22:30(夏季:23:00)。
⑤、監(jiān)理人員一律不得留宿外面,按時(shí)回監(jiān)理部(臨時(shí)駐地);因特殊原因在外面吃晚飯的監(jiān)理人員必須在 23:00 之前回監(jiān)理部(臨時(shí)駐地)。
⑥、與監(jiān)理部作息時(shí)間安排有出入的情況,都應(yīng)及時(shí)告知總監(jiān),并征得總監(jiān)的同意。2、請(qǐng)假、考勤制度:
(1)、請(qǐng)假的理由必須真實(shí),不得撒謊。
(2)、請(qǐng)假耽擱或休假時(shí)間原則上與國(guó)家法定假日保持一致,特殊情況具體處理。監(jiān)理部人員實(shí)行輪休制,節(jié)假日必須有相應(yīng)的監(jiān)理工程師值班,如工作需要不能離開(kāi)工地,必須服從工作安排。
(3)、請(qǐng)假人應(yīng)按請(qǐng)假的天數(shù)按時(shí)回來(lái)上班,遇特殊情況不能按時(shí)趕回,告
知總監(jiān)說(shuō)明事由,其延續(xù)天數(shù)作事假處理;監(jiān)理部嚴(yán)格考勤制度,請(qǐng)假的天數(shù)將在考勤表上體現(xiàn),考勤情況與當(dāng)月工資掛鉤。
(4)、監(jiān)理部負(fù)責(zé)對(duì)項(xiàng)目部經(jīng)理、總工、實(shí)驗(yàn)室主任嚴(yán)格考勤,其他技術(shù)人員由專(zhuān)監(jiān)考勤。如承包人相關(guān)人員的耽擱未按合同要求請(qǐng)假或超過(guò)了合同規(guī)定天數(shù)且影響到工作,必須嚴(yán)格按合同違約條款進(jìn)行處罰。3、崗前培訓(xùn)制度
監(jiān)理人員和承包人技術(shù)人員在上崗前必須接受 1-2 周的崗前培訓(xùn),尤其是熟讀圖紙,掌握設(shè)計(jì)要求、理解設(shè)計(jì)意圖,了解工程的難點(diǎn)、重點(diǎn)和不同點(diǎn)是做好工作及項(xiàng)目的前提。4、監(jiān)理部的工作制度
((1 1))、分工協(xié)作制度
既分工,又協(xié)作,各專(zhuān)業(yè)工程師之間,各現(xiàn)場(chǎng)監(jiān)理之間,各專(zhuān)監(jiān)與現(xiàn)場(chǎng)之間,注意相互配合、協(xié)作,要以團(tuán)隊(duì)意識(shí)來(lái)看待相互的配合問(wèn)題;每位監(jiān)理人員的所作所為代表的是一個(gè)組織行為,而不僅僅是個(gè)人行為。
((2 2))、驗(yàn)基制度
凡是結(jié)構(gòu)物驗(yàn)基或隱蔽工程的驗(yàn)收,由相應(yīng)專(zhuān)業(yè)工程師負(fù)責(zé)協(xié)調(diào)、組織,并負(fù)責(zé)向總監(jiān)匯報(bào);驗(yàn)基通知由承包人自檢后通知專(zhuān)監(jiān);驗(yàn)基參加人員一般為:專(zhuān)監(jiān)、材試、測(cè)量、計(jì)量、現(xiàn)場(chǎng)監(jiān)理;特殊情況下,若材試或測(cè)量或計(jì)量工程師有事不能參加,則參加的專(zhuān)監(jiān)負(fù)責(zé)提供相應(yīng)數(shù)據(jù),并對(duì)提供的數(shù)據(jù)負(fù)責(zé)。
((3 3))、現(xiàn)場(chǎng)收方和計(jì)量制度
收方以計(jì)量工程師為中心,其他專(zhuān)監(jiān)配合、協(xié)助提供相關(guān)情況,并對(duì)計(jì)量項(xiàng)目共同簽字確認(rèn);一般情況,現(xiàn)場(chǎng)收方由總監(jiān)帶隊(duì);原則上,資料齊全、正確、完善后才能審核計(jì)量表,最終簽字認(rèn)可;特殊情況下,為提高效率,基礎(chǔ)資料的簽認(rèn)、計(jì)量項(xiàng)目工程量的審核工作可以同時(shí)進(jìn)行,但計(jì)量單的簽認(rèn)必須在基礎(chǔ)資料簽認(rèn)完成之后。
((4 4))、專(zhuān)監(jiān)對(duì)現(xiàn)場(chǎng)監(jiān)理的管理制度
各專(zhuān)監(jiān)要切實(shí)履行各自的職責(zé),把各現(xiàn)場(chǎng)監(jiān)理真正管起來(lái),對(duì)現(xiàn)場(chǎng)監(jiān)理的管理既要嚴(yán)格,又要多幫助、多指導(dǎo)、多關(guān)心,真正發(fā)揮現(xiàn)場(chǎng)監(jiān)理的作用,共同努力實(shí)現(xiàn)對(duì)各工序的有效控制。
各專(zhuān)業(yè)工程師負(fù)責(zé)完善和及時(shí)更新各專(zhuān)業(yè)工程臺(tái)帳,及時(shí)完成各專(zhuān)業(yè)的監(jiān)理抽檢資料。
((5 5))、工序質(zhì) 檢制度
各工序(分項(xiàng))工程的檢驗(yàn)嚴(yán)格按程序辦事,承包人不自檢,監(jiān)理拒絕抽檢;承包人不自檢或自檢不合格,監(jiān)理不得同意相應(yīng)工序(分項(xiàng))工程的開(kāi)工或開(kāi)盤(pán);承包人應(yīng)提供自檢資料,現(xiàn)場(chǎng)檢驗(yàn)、現(xiàn)場(chǎng)簽認(rèn)。
((6 6))、隱蔽工程影像制度
按合同規(guī)定,凡是隱蔽工程或關(guān)鍵工序,都要有影像資料;承包人自檢、監(jiān)理抽檢都要形成相應(yīng)的影像資料;隱蔽工程或關(guān)鍵工序如果沒(méi)有影像資料拒絕簽字。
((7 7))、書(shū)面制度
工作中盡量把口頭申請(qǐng)、報(bào)告、指示,要求書(shū)面化,以利工作,也有利于保護(hù)自己;工作指示、現(xiàn)場(chǎng)工作指令必須要回復(fù)(閉合),不管哪一種回復(fù),重在落實(shí)(整改)的結(jié)果(相應(yīng)的影像資料),而不僅僅是提出處理方案或作出承諾而已。
((8 8))、中間交工制度
分項(xiàng)工程完成后,及時(shí)進(jìn)行中間交工驗(yàn)收,由業(yè)主、監(jiān)理、承包人共同完成。中間交工的前提是質(zhì)檢和分項(xiàng)評(píng)定已完成并由承包人提出申請(qǐng)。
((9 9))、一崗多責(zé)的工作制度 專(zhuān)監(jiān)同時(shí)擔(dān)任工程監(jiān)理、工程安全、工程環(huán)保的監(jiān)理工作,并對(duì)總監(jiān)負(fù)責(zé)。工程監(jiān)理和工程環(huán)保是伴隨著工程的實(shí)施而產(chǎn)生的,因此三位一體的工作制度符合實(shí)際情況。
(10)、旁站制度
砼澆注、預(yù)應(yīng)力張拉、注漿三大工序必須全過(guò)程旁站,現(xiàn)場(chǎng)填寫(xiě)旁站記錄,現(xiàn)場(chǎng)簽認(rèn)。5、會(huì)議 制度
(1)、工地例會(huì):每月初召開(kāi)。
(2)、專(zhuān)題會(huì)議:根據(jù)工程需要及時(shí)召開(kāi)。
(3)、內(nèi)部通氣會(huì):在早會(huì)或隨時(shí)召開(kāi)。
以上會(huì)議都必須形成會(huì)議紀(jì)要,以備查。6、報(bào)表制度(1)、周計(jì)劃:承包人每周二上午報(bào)。
(2)、月計(jì)劃:在施工月報(bào)中報(bào)。
(3)、施工月報(bào):承包人報(bào)表,每月的 20 號(hào)報(bào),遇節(jié)假日順延。
(4)、監(jiān)理月報(bào):監(jiān)理報(bào)表,每月的 25 號(hào)報(bào),遇節(jié)假日順延。
八、人員進(jìn) 退 場(chǎng)計(jì)劃
(見(jiàn)后表 1-1)
九、設(shè)備、設(shè)施進(jìn)退場(chǎng)計(jì)劃
(見(jiàn)后表 1-2)
十、各種表格
(單獨(dú)形成電子文檔)
都江堰市虹口旅游公路災(zāi) 后恢復(fù)重建 工程監(jiān)理部進(jìn)場(chǎng)人員計(jì)劃(表 1 1--1 1)
時(shí)間 2008 年
2008 年
2009 年
準(zhǔn)備階段
施工階段
交竣工階段
人員 11 月 12 月 1 月 2 月 3 月 4 月 5 月 6 月 7 月 8 月 9 月 總監(jiān) 到
測(cè)量
到
結(jié)構(gòu)
到
路基
到
材試
到
計(jì)量
到
監(jiān)理員 1
到
監(jiān)理員 2
到
監(jiān)理員 3
到
合計(jì)人員 5 10 10 10 10 10 10 10 10 10
都江堰市虹口旅游公路災(zāi)后恢復(fù) 重建工程 監(jiān)理部主要設(shè)施、設(shè)備進(jìn)退場(chǎng)計(jì)劃(表 1 1--2 2)
序號(hào) 項(xiàng) 目 單位 數(shù)量 進(jìn)場(chǎng)時(shí)間 退場(chǎng)時(shí)間 備注 1 辦公住房 幢 1 2008.11 2009.7 虹口鄉(xiāng) 1 樓,2 電腦 臺(tái) 1 2008.11 2009.7 配和自帶 3 電腦桌 張 2 2008.1 2008.7
打印機(jī) 臺(tái) 1 2008.11 2009.7
文件柜 套 4 2008.11 200.7
取暖器 臺(tái) 3 2008.11 2009.7
復(fù)印機(jī) 臺(tái) 1 2008.11 2009.7
照相機(jī) 部 1 2008.11 2009.7 帶攝像 11 辦公桌 張 12 2008.11 2009.7
辦公椅 張 20 2008.11 2009.7
計(jì)算器 個(gè) 7 2008.11 2009.7
手機(jī)電話(huà) 部 11 2008.11 2009.7車(chē)輛 臺(tái) 2 2008.11 2009.7 四驅(qū) 注:辦公和住宿以虹口鎮(zhèn)為主。
第二篇:監(jiān)理規(guī)劃
一、工程項(xiàng)目概況
1.2.項(xiàng)目建設(shè)情況:
項(xiàng)目單位:施工單位:
二、監(jiān)理工作范圍
三、監(jiān)理工作內(nèi)容
1.隨時(shí)征求業(yè)主對(duì)工程建設(shè)的要求,積極配合為業(yè)主工作。2.主持制定工程項(xiàng)目監(jiān)理規(guī)劃。
3.協(xié)助業(yè)主優(yōu)化設(shè)計(jì)方案和施工圖紙。
4.協(xié)助業(yè)主選擇總、分包單位及供貨商,審查總承包單位選擇的專(zhuān)業(yè)分包單位的資質(zhì)和分包合同。
5.審查施工單位的開(kāi)工報(bào)告。
6.審查施工單位各項(xiàng)施工準(zhǔn)備工作,下達(dá)開(kāi)工通知書(shū)。
7.督促施工單位建立健全施工管理制度和質(zhì)量保證體系,并督促其實(shí)施。8.參加圖紙會(huì)審和設(shè)計(jì)交底。
9.審批施工單位提交的施工組織設(shè)計(jì)、施工技術(shù)方案;審查施工單位的年、季、月施工進(jìn)度計(jì)劃并督促其實(shí)施。
10.檢查施工單位選用的原材料、半成品、成品、構(gòu)配件和設(shè)備的質(zhì)量,并進(jìn)行必要的測(cè)試和監(jiān)控以及簽認(rèn),對(duì)影響工程使用功能的觀感材料進(jìn)行質(zhì)量預(yù)控。11.監(jiān)督施工單位嚴(yán)格按照技術(shù)標(biāo)準(zhǔn)和設(shè)計(jì)文件施工,控制工程質(zhì)量,對(duì)違反設(shè)計(jì)文件、規(guī)范和規(guī)程的工程,責(zé)令施工單位立即改正,必要時(shí)簽發(fā)工程暫停指令。
12.簽認(rèn)隱蔽工程和建筑安裝工程的分部、分項(xiàng)工程的質(zhì)量驗(yàn)收,未經(jīng)簽認(rèn)不得允許施工單位進(jìn)行下道工序施工。
13.參加工程質(zhì)量事故的分析和處理,并督促事故處理方案的實(shí)施。
14.審查施工單位提出的設(shè)計(jì)變更的合理性、可行性;經(jīng)設(shè)計(jì)單位認(rèn)可后下達(dá)設(shè)計(jì)變更通知書(shū)。
15.凡使用新材料、新產(chǎn)品、新工藝、新技術(shù)的項(xiàng)目,應(yīng)由建設(shè)單位批準(zhǔn),要有鑒定證明、產(chǎn)品質(zhì)量標(biāo)準(zhǔn)、使用說(shuō)明和工藝要求,監(jiān)理單位按其質(zhì)量標(biāo)準(zhǔn)進(jìn)行驗(yàn)收。
16.對(duì)現(xiàn)場(chǎng)施工過(guò)程中的安全生產(chǎn)、文明施工進(jìn)行檢查,發(fā)現(xiàn)有不符合要求的,書(shū)面通知施工單位改進(jìn)。
17.簽認(rèn)已完工程的工程量,審核工程進(jìn)度款并簽署工程付款證書(shū)。未經(jīng)監(jiān)理工程師簽認(rèn)的工程量,不應(yīng)計(jì)入已完工程量和用作支付工程款的憑證。審核工程竣工結(jié)算。18.組織工程階段驗(yàn)收和竣工初驗(yàn),并對(duì)工程施工質(zhì)量提出評(píng)估意見(jiàn)和竣工初驗(yàn)報(bào)告。19.分階段進(jìn)行進(jìn)度控制,及時(shí)提出調(diào)整意見(jiàn)。20.處理合同糾紛和索賠事宜。21.檢查施工單位的工程技術(shù)資料,督促施工單位對(duì)工程技術(shù)資料的收集、整理、歸檔,并符合城建檔案的規(guī)定。
22.協(xié)助業(yè)主申報(bào)政府質(zhì)量監(jiān)督部門(mén)對(duì)工程進(jìn)行竣工質(zhì)量核定。23.建立施工過(guò)程中的監(jiān)理檔案。24.按期向業(yè)主報(bào)送監(jiān)理檔案。
25.協(xié)助業(yè)主與施工單位簽訂工程保修合同。
26.組織召開(kāi)每周的監(jiān)理例會(huì),并協(xié)調(diào)參與施工活動(dòng)各方的關(guān)系。27.協(xié)同業(yè)主作好經(jīng)濟(jì)簽證工作。28.按月編制監(jiān)理月報(bào)。
29.在整個(gè)施工過(guò)程中進(jìn)行旁站監(jiān)督和巡視監(jiān)理。30.對(duì)引進(jìn)新科技項(xiàng)目,要求在不改變?cè)馁|(zhì)的基礎(chǔ)上,通過(guò)改良提高其性能,達(dá)到使用要求,但必須有相應(yīng)的檢測(cè)報(bào)告和一年以上的戶(hù)外實(shí)驗(yàn),通過(guò)后方可使用。
四、監(jiān)理工作目標(biāo)
1、工程質(zhì)量監(jiān)理目標(biāo):
本工程總體質(zhì)量目標(biāo)為優(yōu)良。
2、工程建設(shè)工期監(jiān)理目標(biāo):
根據(jù)業(yè)主與施工總承包單位簽訂合同工期總目標(biāo)確定。
3、工程建設(shè)投資監(jiān)理目標(biāo):
根據(jù)業(yè)主與施工總承包單位簽訂合同投資總目標(biāo)確定。
五、監(jiān)理工作依據(jù)
1、建筑法;
2、根據(jù)西藏自治區(qū)發(fā)改委的該項(xiàng)目的批文;
3、《公路工程施工監(jiān)理規(guī)程》JTJ077-95;
4、監(jiān)理合同文件;
5、業(yè)主與承包人簽訂的施工合同、協(xié)議及附件;
6、合同圖紙及說(shuō)明;
7、合同工程量清單及說(shuō)明;
8、合同指定使用的標(biāo)準(zhǔn)圖紙、技術(shù)規(guī)范、工程質(zhì)量檢驗(yàn)評(píng)定標(biāo)準(zhǔn)和試驗(yàn)規(guī)程等;
9、國(guó)家、西藏自治區(qū)頒發(fā)的關(guān)于工程施工、監(jiān)理等法規(guī);
10、西藏自治區(qū)發(fā)布的有關(guān)工程管理的文件;
11、業(yè)主發(fā)布的有關(guān)工程管理的文件。
六、項(xiàng)目監(jiān)理機(jī)構(gòu)的組織形式 監(jiān)理組織框圖如下: 總監(jiān)代表(監(jiān)理組長(zhǎng))
七、項(xiàng)目監(jiān)理機(jī)構(gòu)的人員配備計(jì)劃
根據(jù)本工程工期緊、任務(wù)重的特點(diǎn)。為樹(shù)立好公司形象,贏得業(yè)主信任,設(shè)駐地監(jiān)理組。項(xiàng)目總監(jiān): 耿有平工程師 總監(jiān)代表: 楊華兵 工程師
三標(biāo)段駐地監(jiān)理:萬(wàn)世銀 工程師
余曉東 技術(shù)員
四標(biāo)段駐地監(jiān)理:耿有和 工程師 林輝勇 技術(shù)員
五標(biāo)段駐地監(jiān)理:左華金 助理工程師 胡 江 技術(shù)員
商砼站駐地監(jiān)理:張 亭 技術(shù)員 唐玉平技術(shù)員
試驗(yàn)監(jiān)理:譚素珍、王霞、劉 穎
八、項(xiàng)目監(jiān)理機(jī)構(gòu)的人員崗位職責(zé) 總監(jiān)(副總)監(jiān)理工程師崗位職責(zé)
(1)工程項(xiàng)目實(shí)行總監(jiān)全面負(fù)責(zé)制,副總監(jiān)協(xié)助總監(jiān)工作,總監(jiān)不在場(chǎng)時(shí),由副總監(jiān)代行總監(jiān)處理日常工作;
(2)根據(jù)工程項(xiàng)目的具體內(nèi)容,對(duì)監(jiān)理組成員進(jìn)行分工和考核;(3)編寫(xiě)監(jiān)理規(guī)劃,組織編寫(xiě)監(jiān)理實(shí)施細(xì)則,組織交底工作;
(4)組織監(jiān)理組學(xué)習(xí)規(guī)范、工程設(shè)計(jì)圖紙;并做好會(huì)審記錄,參加工程設(shè)計(jì)圖紙交紙會(huì)議;(5)審查承包商編制的施工組織設(shè)計(jì)和重要施工技術(shù)方案;(6)審查變更設(shè)計(jì);
(7)協(xié)助顧客確認(rèn)承包商選擇的分包單位;
(8)組織監(jiān)理人員實(shí)施對(duì)工程質(zhì)量的控制、審核工程施工保證資料;(9)根據(jù)標(biāo)準(zhǔn)、規(guī)范提出單位工程評(píng)價(jià)意見(jiàn);
(10)協(xié)助顧客組織單位工程中間檢查及工程竣工驗(yàn)收;(11)簽發(fā)各項(xiàng)監(jiān)理指令及業(yè)務(wù)聯(lián)系單;
(12)參與各參建單位現(xiàn)場(chǎng)協(xié)調(diào),參與事故的調(diào)查和處理;(13)審批當(dāng)月合格工程量、計(jì)量支付證書(shū);
(14)審閱監(jiān)理日記,編寫(xiě)監(jiān)理月報(bào),定期向顧客和公司匯報(bào)工程進(jìn)展和存在問(wèn)題;(15)參加顧客召開(kāi)的有關(guān)會(huì)議,主持監(jiān)理例會(huì);(16)編寫(xiě)監(jiān)理工作總結(jié),辦理監(jiān)理業(yè)務(wù)手冊(cè)。測(cè)量監(jiān)理崗位職責(zé)
(1)按工程需要經(jīng)總監(jiān)批準(zhǔn)辦理檢測(cè)設(shè)備的申領(lǐng)手續(xù),并負(fù)責(zé)保管;
(2)負(fù)責(zé)本標(biāo)段的設(shè)計(jì)交樁,復(fù)核基準(zhǔn)線(xiàn)、控制點(diǎn),及時(shí)提出書(shū)面復(fù)核文件送業(yè)主認(rèn)可;(3)復(fù)核承包單位的加密點(diǎn)和臨時(shí)水準(zhǔn)點(diǎn);(4)定期檢查承包單位測(cè)量記錄和測(cè)量?jī)x器。
(5)匯總各項(xiàng)測(cè)量成果,定期向總監(jiān)(副總監(jiān))匯報(bào)測(cè)量情況。(6)做好監(jiān)理日記。
材料(試驗(yàn))監(jiān)理崗位職責(zé)
(1)審查承包單位工地試驗(yàn)室管理制度、設(shè)備及試驗(yàn)人員資質(zhì);(2)核查承包單位的原材料、成品、半成品供應(yīng)單位資質(zhì);
(3)審核承包單位的進(jìn)料計(jì)劃,檢查進(jìn)場(chǎng)材料的質(zhì)量,并核驗(yàn)質(zhì)保單;(4)督促檢查承包單位的原材料復(fù)試,審核試驗(yàn)結(jié)果,并進(jìn)行資料收集;
(5)督促檢查承包單位按規(guī)范要求進(jìn)行工程試驗(yàn),審核試驗(yàn)報(bào)告,并進(jìn)行資料收集;(6)檢查承包單位外加工構(gòu)件質(zhì)保單,并檢驗(yàn)構(gòu)件外觀幾何尺寸;
(7)依據(jù)合同負(fù)責(zé)實(shí)施監(jiān)理對(duì)原材料和工程試驗(yàn)的抽檢工作,并做好臺(tái)帳;(8)及時(shí)匯總原材料復(fù)試和工程試驗(yàn)結(jié)果;(9)做好監(jiān)理日記;
(10)總監(jiān)(副總監(jiān))臨時(shí)交辦的其他工作。內(nèi)業(yè)資料監(jiān)理崗位職責(zé)
(1)建立收發(fā)文記錄、技術(shù)文件清單;
(2)負(fù)責(zé)圖紙、文件、資料的簽收、分發(fā)、保管;
(3)按照檔案及主管部門(mén)的要求,檢查督促承包單位內(nèi)業(yè)資料的管理;
(4)按工程劃分要求,匯總整理質(zhì)量、進(jìn)度、計(jì)量、支付等資料,提供總監(jiān)所需數(shù)據(jù)資料;(5)負(fù)責(zé)監(jiān)理辦公室的內(nèi)勤工作(包括、考勤、打印、文書(shū)、檔案、圖表等);
(6)按公司檔案要求整理監(jiān)理資料,工程竣工核驗(yàn)后送公司監(jiān)理部審查,檔案室驗(yàn)收;
計(jì)量控制監(jiān)理崗位職責(zé)
(1)學(xué)習(xí)工程設(shè)計(jì)文件,熟悉工程設(shè)計(jì)要求;(2)根據(jù)合同文件審核合格工程量或計(jì)量支付單;(3)設(shè)立計(jì)量臺(tái)帳,做好記錄,做好監(jiān)理日記;(4)總監(jiān)(副總監(jiān))交辦的其他工作。安全、文明施工監(jiān)理職責(zé)(1)審查承包商的技術(shù)安全措施及安全保證體系;
(2)審查承包提交的施工現(xiàn)場(chǎng)平面布置;督促承包商定期、不定期檢查用電、消防安全;(3)審查承包商主要施工機(jī)械設(shè)備的數(shù)量、性能、檢修證;督促承包商檢查機(jī)械設(shè)備操作運(yùn)行及保養(yǎng)維修的情況;
(4)審查承包商特殊工種的上崗操作證?,F(xiàn)場(chǎng)質(zhì)量監(jiān)理崗位職責(zé)
(1)堅(jiān)持以旁站、巡視、抽檢、驗(yàn)收相結(jié)合的方法,全方位控制現(xiàn)場(chǎng)施工質(zhì)量;(2)堅(jiān)持按標(biāo)準(zhǔn)辦事,憑數(shù)據(jù)說(shuō)話(huà),以書(shū)面來(lái)往的形式,開(kāi)展監(jiān)理工作。
(3)嚴(yán)格控制施工單位按技術(shù)操作規(guī)程施工,進(jìn)行合格工程量的計(jì)量驗(yàn)收簽證;(4)檢查現(xiàn)場(chǎng)材料、半成品、構(gòu)件質(zhì)量;(5)檢查現(xiàn)場(chǎng)施工技術(shù)安全操作;
(6)檢查現(xiàn)場(chǎng)機(jī)具、設(shè)備(包括數(shù)量規(guī)格和性能)及特殊工種上崗證。(7)按監(jiān)理合同要求頻率,做好各項(xiàng)抽檢工作;
(8)及時(shí)、如實(shí)做好現(xiàn)場(chǎng)監(jiān)理記錄、監(jiān)理日記及各項(xiàng)抽檢原始資料;(9)按分管工程提供監(jiān)理工作小結(jié);(10)總監(jiān)(副總監(jiān))交辦的其他工作。
九、監(jiān)理工作程序: 施工階段的監(jiān)理程序 監(jiān)理合同簽訂
編制委托項(xiàng)目監(jiān)理規(guī)劃 組建監(jiān)理班子進(jìn)駐施工現(xiàn)場(chǎng) 組織召開(kāi)監(jiān)理工作交底會(huì) 監(jiān) 理 準(zhǔn) 備 編制委托項(xiàng)目監(jiān)理細(xì)則
監(jiān)理實(shí)施細(xì)則交底 實(shí)施施工監(jiān)理 工程結(jié)束
編寫(xiě)工程評(píng)估報(bào)告
協(xié)助施工單位組織工程初驗(yàn)
協(xié)助建設(shè)單位組織工程終驗(yàn)(特大型工程協(xié)助建設(shè)單位組織竣工驗(yàn)收)協(xié)助建設(shè)單位申報(bào)工程核驗(yàn) 施工階段工序質(zhì)量控制工作程序 施工準(zhǔn)備:上道工序檢查 本道工序檢查 不合格 監(jiān)理抽檢
合格
工序施工 監(jiān)理巡視抽檢 施工單位自檢 合格
填寫(xiě)工程報(bào)驗(yàn)單
不合格 監(jiān)理抽檢
合格
簽認(rèn)工程報(bào)驗(yàn)單
合格
進(jìn)入下一道工序施工
技術(shù)聯(lián)系工作程序
(一)施工單位 提出聯(lián)系內(nèi)容申報(bào) 否
磋商 總監(jiān)理 磋商 重大問(wèn)題報(bào)
設(shè)計(jì)單位 工程師審核 建設(shè)單位
可
施工單位實(shí)施 技術(shù)聯(lián)系工作程序
(二)設(shè)計(jì)單位 提出聯(lián)系內(nèi)容
建設(shè)單位
總監(jiān)理工程師
施工單位實(shí)施
施工階段計(jì)量與支付工作程序
施工單位提交開(kāi)工報(bào)告 監(jiān)理工程師審核 工序施工完成 施工單位:計(jì)量申請(qǐng) 附:經(jīng)監(jiān)理認(rèn)可的 合格工程計(jì)量資料
不合格 監(jiān)理:計(jì)量審核
合 格
業(yè)主審核
監(jiān)理:計(jì)量簽認(rèn) 發(fā)計(jì)量憑證
施工單位:支付申請(qǐng) 附:各款項(xiàng)的單價(jià)及
數(shù)量、相應(yīng)的證明文件 監(jiān)理:支付證書(shū) 業(yè)主審核
業(yè)主:財(cái)務(wù)復(fù)核后
支付工程款 竣工驗(yàn)收程序
施工單位自檢后 提出初驗(yàn)申請(qǐng)
監(jiān)理單位審查資料 及現(xiàn)場(chǎng)預(yù)檢
協(xié)助組織初驗(yàn),就存在 問(wèn)題提出書(shū)面整改意見(jiàn)
施工單位整改
否
監(jiān)理單位復(fù)驗(yàn)
可
施工單位提交工程檔案 資料并提出竣工驗(yàn)收申請(qǐng)
監(jiān)理單位提出評(píng)估報(bào)告
建設(shè)單位組織竣工驗(yàn)收,施工、監(jiān)理、設(shè)計(jì)及其它有關(guān)單位參加
建設(shè)單位申請(qǐng)核驗(yàn)
進(jìn)入保修階段
保修階段的監(jiān)理程序
有質(zhì)量問(wèn)題 定期對(duì)工程回訪(fǎng)
無(wú)質(zhì)量問(wèn)題
鑒定質(zhì)量責(zé)任
責(zé)任期
結(jié)束時(shí)的檢驗(yàn)
維修工程質(zhì)量檢驗(yàn)
協(xié)助建設(shè)單位與施工單位 責(zé)任期結(jié)束時(shí) 的檢驗(yàn)
辦理終止合同手續(xù)
控制點(diǎn)復(fù)核程序
準(zhǔn)備工作:參加交樁,校核點(diǎn)之記樁
請(qǐng)有關(guān)部門(mén) 位參照物,檢查點(diǎn)位保護(hù)情況,了解 重新交樁 控制點(diǎn)等級(jí)精度,制定復(fù)核方案,校 正測(cè)量?jī)x器,組織測(cè)量人員。
實(shí)地測(cè)量
不合格 復(fù)核結(jié)果
合格
編制復(fù)核成果
交承包商復(fù)核
不合格 復(fù)核結(jié)果
合格
批準(zhǔn)承包商采用
承包商控制點(diǎn)加密方案
不合格 監(jiān)理審核 合格
承包商加密控制測(cè)量
不合格 監(jiān)理復(fù)核
合格
批準(zhǔn)承包商采用
施工放樣復(fù)核程序
準(zhǔn)備工作:熟悉設(shè)計(jì)圖紙,按照?qǐng)D紙要
求計(jì)算測(cè)量放樣復(fù)核數(shù)據(jù)
承包人測(cè)量放樣方案 放樣數(shù)據(jù)內(nèi)業(yè)計(jì)算
不合格 監(jiān)理審核
合 格
承包人測(cè)量放樣
不合格 監(jiān)理復(fù)核
合格
進(jìn)入下一道工序
合格工程量計(jì)量審核監(jiān)理程序
準(zhǔn)備工作:
1、審核承包商統(tǒng)計(jì)工程量。
2、按中期支付方式(表式)要求 進(jìn)行工作量、工程量歸納、分類(lèi)
3、臺(tái)帳記錄表式確定監(jiān)理各工序質(zhì)量簽認(rèn)隱蔽工程檢查單做好臺(tái)帳
承包商提交合格工程量申請(qǐng)表及附件
監(jiān)理根據(jù)臺(tái)帳
不予簽證或整 不合格
修合格后簽證 或沒(méi)完成 進(jìn)行審核
合格
簽證合格部分
工程量申請(qǐng)表
報(bào)業(yè)主審核
十一、監(jiān)理工作方法及措施
1.每周由總監(jiān)召開(kāi)工地例會(huì),施工單位作工作匯報(bào),由業(yè)主、監(jiān)理、施工單位共同解決影響工程質(zhì)量、阻礙工程進(jìn)度的問(wèn)題,確保工程保質(zhì)按期完工。
2.駐地監(jiān)理在日常監(jiān)理中,如實(shí)際情況與原設(shè)計(jì)發(fā)生重大變化,首先要摸清實(shí)情,掌握現(xiàn)場(chǎng)資料,如實(shí)向總監(jiān)匯報(bào),并提出自己的觀點(diǎn)和看法,供總監(jiān)參考。
3.駐地監(jiān)理在工程實(shí)施中對(duì)關(guān)鍵工程、關(guān)鍵工藝,必須全程旁站,對(duì)隱蔽工程的各項(xiàng)工序必須檢驗(yàn)合格后方可進(jìn)行下道工序。、4.試驗(yàn)監(jiān)理工程師對(duì)進(jìn)場(chǎng)的材料進(jìn)行全方位多層次的檢查,并抽檢測(cè)試,施工過(guò)程中的常規(guī)試驗(yàn)按部頒試驗(yàn)規(guī)程進(jìn)行。
5.駐地監(jiān)理對(duì)承包人報(bào)來(lái)的資料要及時(shí)抽檢確認(rèn),不得積壓、拖延,在抽檢過(guò)程中發(fā)現(xiàn)承包人弄虛作假,或名不符實(shí)要果斷地提出整改措施,責(zé)令承包人糾正或改進(jìn),對(duì)報(bào)來(lái)的資料經(jīng)查實(shí)無(wú)誤,應(yīng)及時(shí)確認(rèn),不得用任何方式敲詐和為難承包人。
6.駐地監(jiān)理在監(jiān)控工程質(zhì)量和工程進(jìn)度的同時(shí),要注意工作方法,時(shí)刻平衡好業(yè)主、監(jiān)理、承包商之間的關(guān)系,既要得到業(yè)主的信任,又不能挫傷承包人的積極性,但也千萬(wàn)不能以犧牲工程質(zhì)量為代價(jià),去平衡人際關(guān)系,這些矛盾的平衡是每個(gè)駐地監(jiān)理必備的素質(zhì)。
7.對(duì)承包人報(bào)來(lái)的工程計(jì)量,應(yīng)依據(jù)設(shè)計(jì)實(shí)地核實(shí),已計(jì)量支付的工程,必須是合格工程,留足質(zhì)保金,始終掌握對(duì)承包人的制約權(quán)。
8.項(xiàng)目總監(jiān)要明確工程質(zhì)量標(biāo)準(zhǔn),提出保證工程質(zhì)量、及工程進(jìn)度的措施及手段,經(jīng)常巡視工地,解決駐地監(jiān)理不能解決的問(wèn)題,不定時(shí)對(duì)駐地監(jiān)理的工作進(jìn)行檢查,本著幫助提高的原則,加強(qiáng)監(jiān)理隊(duì)伍的團(tuán)結(jié),提高監(jiān)理水平。
十一、監(jiān)理工作制度 1.資質(zhì)、資格審查制度(1)資質(zhì)審查包括:
A、對(duì)各分包單位的資質(zhì)審查與認(rèn)可。B、對(duì)主要材料、構(gòu)配件、設(shè)備供應(yīng)廠(chǎng)家的資質(zhì)審查。
對(duì)經(jīng)審查不符合有關(guān)資質(zhì)條件規(guī)定的分包單位及廠(chǎng)家,總監(jiān)有權(quán)拒絕其人員進(jìn)入施工現(xiàn)場(chǎng),其產(chǎn)品不能用于工程建設(shè)。(2)資格審查包括:
A、承包單位的資質(zhì)證明(營(yíng)業(yè)執(zhí)照、資質(zhì)等級(jí)),承包單位管理組織及其人員的資格與能力。
B、承包單位施工人員持證情況。C、特殊工種施工人員持證情況。
監(jiān)理單位有權(quán)要求承包單位撤換不勝任本項(xiàng)工程的管理及施工人員;嚴(yán)禁無(wú)證上崗。
2、圖紙資料審核制度
項(xiàng)目總監(jiān)組織有關(guān)專(zhuān)業(yè)監(jiān)理工程師對(duì)設(shè)計(jì)圖紙及有關(guān)技術(shù)資料進(jìn)行審核,并提出監(jiān)理意見(jiàn),內(nèi)容包括:
(1)圖紙會(huì)審:
開(kāi)工前對(duì)設(shè)計(jì)施工圖紙及有關(guān)技術(shù)說(shuō)明進(jìn)行會(huì)審,認(rèn)真熟悉圖紙及設(shè)計(jì)意圖,并參加設(shè)計(jì)交底。
(2)工程洽商和設(shè)計(jì)變更:
設(shè)計(jì)單位的設(shè)計(jì)變更需經(jīng)監(jiān)理工程師審核簽認(rèn)后交施工單位執(zhí)行。施工單位的洽商變更要求需經(jīng)監(jiān)理工程師審核同意后,方能與設(shè)計(jì)單位辦理手續(xù)。重要問(wèn)題監(jiān)理工程師需征得建設(shè)單位認(rèn)可方能簽發(fā)。監(jiān)理工程師的審核工作重點(diǎn)是洽商與變更是否違反有關(guān)規(guī)范、標(biāo)準(zhǔn)及其它技術(shù)文件,是否影響工程安全、使用功能和外觀。施工單位未經(jīng)監(jiān)理工程師簽認(rèn)變更設(shè)計(jì)內(nèi)容,其工程量不計(jì)入已完工程量。
3、施工組織設(shè)計(jì)、施工進(jìn)度計(jì)劃和施工方案:
工程開(kāi)工前,施工單位必須編制施工組織設(shè)計(jì)或技術(shù)方案,并報(bào)總監(jiān)理工程師審查,如有需增加工期、費(fèi)用,應(yīng)報(bào)業(yè)主審批后方可實(shí)施。施工單位編制的總施工進(jìn)度計(jì)劃及年、季、月進(jìn)度計(jì)劃,需經(jīng)總監(jiān)理工程師審批后認(rèn)真實(shí)施,必要時(shí)監(jiān)理工程師應(yīng)及時(shí)調(diào)整進(jìn)度計(jì)劃,確保進(jìn)度目標(biāo)實(shí)現(xiàn)。
4、有關(guān)的施工技術(shù)資料:
施工單位在施工過(guò)程中有關(guān)技術(shù)資料,必須交監(jiān)理工程師審查,主要內(nèi)容包括:
(1)主要材料、構(gòu)配件、設(shè)備產(chǎn)品合格證、出廠(chǎng)證明、村質(zhì)證明、試驗(yàn)報(bào)告、準(zhǔn)用證、防偽標(biāo)志等。
(2)施工試驗(yàn)記錄包括:回填土、混凝土、砂漿、鋼筋及鋼材、鋼筋接頭、原材料復(fù)試等。(3)施工記錄包括:地基勘探及處理記錄、構(gòu)造物控制樁放線(xiàn)、定位放線(xiàn)及高程控制記錄、隱檢記錄、預(yù)檢記錄、閉水試驗(yàn)記錄等。項(xiàng)目竣工前,資料由承包單位整理匯總交監(jiān)理工程師核查。對(duì)可疑問(wèn)題,監(jiān)理工程師有權(quán)進(jìn)行復(fù)驗(yàn)。
5、會(huì)議制度(1)監(jiān)理例會(huì)
為充分發(fā)揮監(jiān)理的組織協(xié)調(diào)作用,加強(qiáng)履約各方勾通情況,交流信息,協(xié)調(diào)處理,研究解決合同履行過(guò)程中存在的各方面問(wèn)題,做好三大目標(biāo)管理的動(dòng)態(tài)跟蹤管理,由項(xiàng)目總監(jiān)理工程師定期組織和主持例行工作會(huì)議。包括:
A、每周召開(kāi)由建設(shè)單位駐工地代表、項(xiàng)目監(jiān)理部總監(jiān)理工程師、總監(jiān)理工程師代表及有關(guān)監(jiān)理工程師、承包單位項(xiàng)目經(jīng)理、技術(shù)負(fù)責(zé)人及有關(guān)專(zhuān)業(yè)人員等三方人員參加的監(jiān)理例會(huì)。每次例會(huì)將針對(duì)近期出現(xiàn)的質(zhì)量、進(jìn)度等重點(diǎn)問(wèn)題協(xié)調(diào)解決,會(huì)議內(nèi)容及決議寫(xiě)成紀(jì)要,經(jīng)各方簽認(rèn)后形成正式文件。B、監(jiān)理例會(huì)的主要議題有: ①檢查上次會(huì)議決議落實(shí)情況,檢查未完事項(xiàng)及其原因。②工程進(jìn)展情況。
③確定下一階段進(jìn)度目標(biāo),研究承包單位人力、設(shè)備等施工資源的投入情況和實(shí)現(xiàn)目標(biāo)的具體措施。
④材料、構(gòu)配件和設(shè)備供應(yīng)情況及存在質(zhì)量問(wèn)題、承包單位應(yīng)采取的改進(jìn)措施、解決方法和改進(jìn)時(shí)間。
⑤工程施工過(guò)程中存在的質(zhì)量缺陷,遇到的技術(shù)方面難題,明確主要的改進(jìn)措施、解決方法和改進(jìn)時(shí)間。
⑥分包單位的管理及協(xié)調(diào)問(wèn)題。
⑦設(shè)計(jì)變更、洽商要求和施工中應(yīng)注意的重點(diǎn)問(wèn)題。⑧工程款的核定及財(cái)務(wù)支付中的有關(guān)問(wèn)題和要求。
⑨違約、工期延期、費(fèi)用索賠的意向及處理方案等事項(xiàng)。⑩施工過(guò)程中遇到的或必須注意的其他事項(xiàng)。項(xiàng)目監(jiān)理部?jī)?nèi)部定期召開(kāi)會(huì)議,及時(shí)收集匯總有關(guān)情況,了解上次會(huì)議的決議落實(shí)情況和存在的問(wèn)題,準(zhǔn)備會(huì)議資料,研究確定有關(guān)事項(xiàng)的處理原則和方案,討論、協(xié)調(diào)各專(zhuān)業(yè)在監(jiān)理工作過(guò)程中發(fā)現(xiàn)的問(wèn)題,為召開(kāi)會(huì)議做好準(zhǔn)備。并與有關(guān)各方通報(bào)情況、交換意見(jiàn),督促其做好準(zhǔn)備。
(2)專(zhuān)題工地會(huì)議
專(zhuān)題工地會(huì)議是為了解決工程過(guò)程出現(xiàn)專(zhuān)門(mén)問(wèn)題、重大技術(shù)難題而召開(kāi)的會(huì)議。專(zhuān)題工地會(huì)議由總監(jiān)理工程師或其授權(quán)的專(zhuān)業(yè)監(jiān)理工程師主持;建設(shè)單位及承包單位技術(shù)負(fù)責(zé)人和有關(guān)專(zhuān)業(yè)技術(shù)人員出席會(huì)議,必要時(shí)邀請(qǐng)有關(guān)專(zhuān)家參加。研究解決存在的技術(shù)和施工難題。
專(zhuān)題工地會(huì)議前,有關(guān)專(zhuān)業(yè)監(jiān)理工程師應(yīng)做好準(zhǔn)備,力爭(zhēng)在本次會(huì)議上解決問(wèn)題;會(huì)上應(yīng)做好會(huì)議記錄,會(huì)后整理成會(huì)議紀(jì)要,經(jīng)與會(huì)代表簽認(rèn)后,由總監(jiān)理工程師簽發(fā)有關(guān)各方。
6、工程質(zhì)量簽認(rèn)制度
為加強(qiáng)質(zhì)量控制,保證質(zhì)量目標(biāo)的實(shí)現(xiàn),下列各項(xiàng)必須監(jiān)理工程師簽認(rèn),這種簽認(rèn)將作為月付款依據(jù):
(1)主要材料、構(gòu)配件、設(shè)備進(jìn)場(chǎng)后,需經(jīng)監(jiān)理工程師驗(yàn)收簽認(rèn),對(duì)于存在有出廠(chǎng)質(zhì)量證明、合格證明等質(zhì)量保證資料內(nèi)容中名實(shí)不符或其它可疑情況者,監(jiān)理工程師有權(quán)拒收或要求復(fù)驗(yàn)。
(2)隱蔽工程在隱蔽前,施工單位應(yīng)進(jìn)行自檢,并將質(zhì)量評(píng)定、驗(yàn)收記錄等資料報(bào)監(jiān)理工程師,需檢查的隱蔽工程,應(yīng)提前二日通知監(jiān)理工程師,經(jīng)監(jiān)理復(fù)驗(yàn)后簽認(rèn)。重要部位或重點(diǎn)部位應(yīng)會(huì)同設(shè)計(jì)、施工單位共同檢查簽認(rèn)。
(3)分項(xiàng)、分部工程在施工單位自評(píng)并符合質(zhì)量目標(biāo)的基礎(chǔ)上,由監(jiān)理工程師檢查并簽認(rèn)。
7、工程支付制度
在施工單位遞交工程量清單及要求支付的明細(xì)表后,并在規(guī)定的期限內(nèi),總監(jiān)組織有關(guān)專(zhuān)業(yè)監(jiān)理工程師,對(duì)已完工程量進(jìn)行核實(shí),并與分項(xiàng)、分部工程簽認(rèn)記錄對(duì)照,確認(rèn)應(yīng)付已完成工程量款,總監(jiān)及專(zhuān)業(yè)監(jiān)理工程師簽認(rèn)后交建設(shè)單位。
8、工程質(zhì)量問(wèn)題、質(zhì)量事故處理制度
(1)工程質(zhì)量問(wèn)題、事故處理按建設(shè)部頒布的關(guān)于《工程建設(shè)重大質(zhì)量事故報(bào)告和調(diào)查程序規(guī)定》及《建筑安裝工程質(zhì)量檢驗(yàn)評(píng)定標(biāo)準(zhǔn)》的規(guī)定和要求執(zhí)行。
(2)監(jiān)理工程師接到承包單位的事故報(bào)告后,應(yīng)立即向總監(jiān)理工程師、建設(shè)單位駐工地代表及上級(jí)有關(guān)部門(mén)報(bào)告。
(3)總監(jiān)理工程師應(yīng)立即簽署《工程部分暫停指令》,責(zé)令承包單位停止施工。并同項(xiàng)目監(jiān)理部的其他監(jiān)理工程師一起,協(xié)同承包單位保護(hù)現(xiàn)場(chǎng),處理善后工作。
(4)承包單位分析質(zhì)量問(wèn)題、質(zhì)量事故的原因,采取措施使損失減少到最低限度;并會(huì)同設(shè)計(jì)單位負(fù)責(zé)制定工程質(zhì)量問(wèn)題、事故的技術(shù)處理方案。(5)項(xiàng)目監(jiān)理部督促承包單位按處理方案實(shí)施。
9、監(jiān)理日記及監(jiān)理月報(bào)制度
(1)現(xiàn)場(chǎng)監(jiān)理工程師按日填寫(xiě)工作日記,記載工程施工部位、質(zhì)量狀況等主要情況,并記載由于環(huán)境因素(天氣、停水、停電等)影響施工進(jìn)度情況,記錄突發(fā)事件發(fā)生的原因、持續(xù)時(shí)間、對(duì)工程的影響程度等,作為審核索賠的依據(jù),監(jiān)理日記將妥善保管,作為歸檔技術(shù)資料。
(2)按月編制監(jiān)理工作月報(bào),報(bào)送建設(shè)單位。
10、監(jiān)理技術(shù)資料管理制度
(1)現(xiàn)場(chǎng)檔案員負(fù)責(zé)收發(fā)、保管日常工作中的來(lái)住文件、通知、報(bào)表,并編目登記、建立收發(fā)檔案。按月整理日記、會(huì)議記錄及有關(guān)圖紙技術(shù)資料。(2)工程竣工后,整理單位工程監(jiān)理檔案資料并歸檔。
十二、監(jiān)理設(shè)施表
序號(hào) 名稱(chēng) 規(guī)格型號(hào) 產(chǎn)地 現(xiàn)狀 數(shù)量臺(tái) 設(shè)備來(lái)源 1 砂石、土壤篩 0.075-50 上虞 1 已有 2 烘箱 2B101-Ⅲ 上海 1 已有 壓力試驗(yàn)機(jī) NYL-2000 無(wú)錫 1 已有 4 電型手動(dòng)擊實(shí)儀 無(wú)錫 1 已有 5 灌砂筒 φ150 天津 2 已有 6 水泥砼試驗(yàn)設(shè)備 無(wú)錫 1 已有 7 砼回彈儀 225型 上海 1 已有 光電液塑限測(cè)定儀 2YS-2 南京 1 已有 9 石子壓碎指標(biāo)儀 標(biāo)準(zhǔn) 上海 1 已有 10 針片狀規(guī)準(zhǔn)儀 標(biāo)準(zhǔn) 上海 1 已有 11 鈣鎂含量自動(dòng)測(cè)量?jī)x 無(wú)錫 1 已有 12 擺式摩擦系數(shù)測(cè)定儀 DM 江蘇 1 已有 電熱恒溫彭風(fēng)干燒箱 101A-2 上海 1 已有 擬在本項(xiàng)目使用的主要儀器、檢測(cè)設(shè)備一覽表
第三篇:監(jiān)理規(guī)劃
湘西州老干活動(dòng)中心綜合樓,住宅樓 監(jiān) 理 規(guī) 劃
工程概況
本工程為州老干活動(dòng)中心綜合樓, 住宅樓工程框混結(jié)構(gòu) 4-7 層(綜合樓 4 層,住宅樓 7 層).總建筑面積 8478m2,工程計(jì) 劃投資 587.82 萬(wàn)元,住宅樓基礎(chǔ)為砼條基,綜合樓為獨(dú)方柱基 礎(chǔ),局部樁基樁徑為 800mm,900mm 兩種,室內(nèi)地面均采用 陶瓷地磚地面,墻面采用“888”陶瓷涂料,外墻采用白色灰色 墻面磚,坡屋面采用藍(lán)色波紋瓦,住宅樓地面采用水泥地面搓 毛,墻面采用“888”防盜涂料,外墻采用白色灰色墻面磚,坡 屋面采用藍(lán)色波紋瓦,工程計(jì)劃開(kāi)工日期 2006 年 5 月 26 日, 計(jì)劃竣工日期為 2007 年 3 月 26 日.
1
第四篇:監(jiān)理規(guī)劃
解放環(huán)路市政工程監(jiān)理規(guī)劃
一、工程項(xiàng)目概況
1、工程簡(jiǎn)況
1)解放環(huán)路是無(wú)錫市城市道路的一環(huán)線(xiàn),它包括解放東路、解放南路、解放西路、解放北路全長(zhǎng)5.48公里。一期工程實(shí)施范圍:勝利門(mén)廣場(chǎng)~朝陽(yáng)廣場(chǎng)~文化宮橋,道路樁號(hào)為K3+625~K5+548.966(K0+000)~K1+325,全長(zhǎng)約3.25公里,其中K0+603.218~K1+126.268為新建段,其余路段為老路面更新改造。整個(gè)工程涉及勝利門(mén)廣場(chǎng)、東林廣場(chǎng)、朝陽(yáng)廣場(chǎng)三個(gè)大型交叉口及工運(yùn)路、縣前東街、崇寧路、學(xué)前東路、文化宮橋等主要交叉口。解放環(huán)路市政工程包括雨污水、自來(lái)水、煤氣、電力、通信等管道,全線(xiàn)分三個(gè)項(xiàng)目組施工,其中: 項(xiàng)目1組:文化宮橋~朝陽(yáng)廣場(chǎng); 項(xiàng)目2組:朝陽(yáng)廣場(chǎng)~東林廣場(chǎng); 項(xiàng)目3組:東林廣場(chǎng)~勝利門(mén)廣場(chǎng);
2)解放環(huán)路道路性質(zhì)為城市主干道,道路紅線(xiàn)在朝陽(yáng)廣場(chǎng)~文化宮橋~人民橋段為36米,其余路段為40米。機(jī)非分隔采用機(jī)非隔離柵分隔。3)路面結(jié)構(gòu)
在解放環(huán)路兩側(cè)的非機(jī)動(dòng)車(chē)道以及朝陽(yáng)廣場(chǎng)~文化宮橋改線(xiàn)道路為4CM瀝青砼(SBS)+8CM瀝青砼(AC-20Ⅰ)+40CM水泥穩(wěn)定碎石基層+15CM10%石灰土底基層(K≥93%);其余路段實(shí)施路表銑刨4CM,上鋪4CM瀝青砼(SBS)+8CM瀝青砼(AC-20Ⅰ)4)雨水管線(xiàn)
實(shí)施新雨水管線(xiàn)1100,其余路段利用原有管線(xiàn),并對(duì)原有管線(xiàn)進(jìn)行清挖疏通,以確保雨水管線(xiàn)的暢通。5)綜合管線(xiàn)
道路兩側(cè)人行道各增設(shè)一根電力管及改建給水管,右側(cè)增設(shè)一根信息管線(xiàn)。6)駁岸工程
靠文化宮橋邊從K1+038.7~K1+230.14有一段新建駁岸,基礎(chǔ)原設(shè)計(jì)為鉆空灌注樁。墻身為漿砌金山石,C25砼壓頂。
2、工程重點(diǎn)和難點(diǎn)分析
1、路基彈軟土質(zhì)處理;
2、新老路基搭接;
3、路基土層壓實(shí)度、灰劑量、灰土拌和均勻性;
4、管道基礎(chǔ)施工、抹帶接縫及溝槽回填;
5、各種老管道及雨污窨井的保護(hù),合理安排管線(xiàn)工程的交叉作業(yè);
6、交叉口、道口的施工;
7、文化宮橋沿河駁岸施工;
8、砼澆筑質(zhì)量;
9、水泥穩(wěn)定碎石施工;
10、SBS瀝青砼面層施工;
3、工程的項(xiàng)目組織
項(xiàng)目業(yè)主:無(wú)錫市重點(diǎn)工程辦公室 設(shè)計(jì)單位:上海市市政工程設(shè)計(jì)院 承 包 商:無(wú)錫市市政工程總公司
監(jiān)理單位:無(wú)錫市市政建設(shè)咨詢(xún)監(jiān)理有限公司
二、監(jiān)理工作的目標(biāo)和范圍
1、監(jiān)理工作的目標(biāo) 監(jiān)理組嚴(yán)格按照業(yè)主的授權(quán)和監(jiān)理服務(wù)合同履行其職責(zé)和義務(wù),我們監(jiān)理工作的目標(biāo)是:根據(jù)國(guó)家監(jiān)理規(guī)范、規(guī)定、運(yùn)行質(zhì)量保證程序,始終堅(jiān)持質(zhì)量第一;嚴(yán)格監(jiān)督承包人履行施工承包合同,確保工程質(zhì)量等級(jí)達(dá)到業(yè)主的要求;樹(shù)立文明服務(wù)意識(shí),全面優(yōu)質(zhì)地履行監(jiān)理合同,監(jiān)理工作達(dá)到合同規(guī)定的各項(xiàng)要求,恪守監(jiān)理單位公約和監(jiān)理工程師職業(yè)道德,為業(yè)主提供優(yōu)質(zhì)高效的監(jiān)理服務(wù)。
2、監(jiān)理工作的范圍
監(jiān)理服務(wù)的工作范圍:在業(yè)主及其代表的宏觀指導(dǎo)下,對(duì)于所轄施工范圍的全部工程自施工準(zhǔn)備期至施工期的質(zhì)量控制、進(jìn)度控制、投資控制、合同管理、信息管理和其它工作協(xié)調(diào)實(shí)施全過(guò)程、全面管理;參與缺陷責(zé)任期的工作。
三、工程項(xiàng)目的監(jiān)理依據(jù) 1.解放環(huán)路工程招投標(biāo)文件。
2.業(yè)主提供的解放環(huán)路工程設(shè)計(jì)圖紙。
3.業(yè)主與監(jiān)理公司簽訂的監(jiān)理合同及監(jiān)理投標(biāo)書(shū)。4.業(yè)主與承包商簽訂的施工合同。
5.國(guó)家有關(guān)技術(shù)質(zhì)量檢驗(yàn)評(píng)定標(biāo)準(zhǔn)及規(guī)范。(1)《中華人民共和國(guó)工程建設(shè)標(biāo)準(zhǔn)強(qiáng)制性條文 城市建設(shè)部分》(2)《建設(shè)工程監(jiān)理規(guī)范》(GB50319-2000)(3)《市政道路工程質(zhì)量檢驗(yàn)評(píng)定標(biāo)準(zhǔn)》(CJJ1-90)(4)《市政橋梁工程質(zhì)量檢驗(yàn)評(píng)定標(biāo)準(zhǔn)》(CJJ2-90)(5)《市政排水管渠工程質(zhì)量檢驗(yàn)評(píng)定標(biāo)準(zhǔn)》(CJJ3-90)(6)《公路路基施工技術(shù)規(guī)程》(JTJ033-95)(7)《公路橋涵施工技術(shù)規(guī)范》(JTJ041-2000)(8)《城市道路路基工程施工及驗(yàn)收規(guī)范》(CJJ44-91)(9)《瀝青路面施工及驗(yàn)收規(guī)范》(GB50092-96)(10)《公路路面基層施工技術(shù)規(guī)范》(JTJ034-94)(11)《公路瀝青路面施工技術(shù)規(guī)范》(JTJ032-94)(12)《公路瀝青瑪脂碎石路面技術(shù)指南》(SHC.F40-01-2002)(13)《給水排水管道工程施工及驗(yàn)收規(guī)范》(GB50268-97)(14)《施工現(xiàn)場(chǎng)臨時(shí)用電安全技術(shù)規(guī)范》(JGJ46-88)(15)《地基與基礎(chǔ)工程施工及驗(yàn)收規(guī)范》(GBJ202-83)(16)《混凝土強(qiáng)度檢驗(yàn)評(píng)定標(biāo)準(zhǔn)》(GBJ107-87)(17)《混凝土質(zhì)量控制標(biāo)準(zhǔn)》(GB50169-92)
四、項(xiàng)目監(jiān)理組織機(jī)構(gòu)和人員調(diào)配計(jì)劃
考慮解放環(huán)路工程的重要性及復(fù)雜性,及其工程呈線(xiàn)性分布以及分項(xiàng)工程交叉覆蓋的特點(diǎn),監(jiān)理公司抽調(diào)公司精干力量,成立以公司總經(jīng)理為總監(jiān),監(jiān)理科長(zhǎng)為總監(jiān)代表的二層次直線(xiàn)制監(jiān)理組織,并且隨著工程的推進(jìn),隨時(shí)增加監(jiān)理人員,以滿(mǎn)足業(yè)主的需要。(具體見(jiàn)監(jiān)理組織圖)
五、監(jiān)理人員的崗位職責(zé)
1、總監(jiān)理工程師職責(zé)
1)確定項(xiàng)目監(jiān)理機(jī)構(gòu)人員的分工和崗位職責(zé);
2)主持編寫(xiě)項(xiàng)目監(jiān)理規(guī)劃、審批項(xiàng)目監(jiān)理實(shí)施細(xì)則,并負(fù)責(zé)管理項(xiàng)目監(jiān)理機(jī)構(gòu)的 日常工作;
3)審查分包單位的資質(zhì),并提出審查意見(jiàn);
4)檢查和監(jiān)督監(jiān)理人員的工作,根據(jù)工程項(xiàng)目的進(jìn)展情況可進(jìn)行人員調(diào)配,對(duì)不 稱(chēng)職的人員應(yīng)調(diào)換基工作;
5)主持監(jiān)理工作會(huì)議,簽發(fā)項(xiàng)目監(jiān)理機(jī)構(gòu)的文件和指令;
6)審定承包單位提交的開(kāi)工報(bào)告、施工組織設(shè)計(jì)、技術(shù)方案、進(jìn)度計(jì)劃; 7)審核簽署承包單位的申請(qǐng)、支付證書(shū)和竣工結(jié)算; 8)審查和處理工程變更;
9)主持或參與工程質(zhì)量事故的調(diào)查;
10)調(diào)解業(yè)主與承包單位的合同爭(zhēng)議、處理索賠、審批工程延期;
11)組織編寫(xiě)并簽發(fā)監(jiān)理月報(bào)、監(jiān)理工作階段報(bào)告、專(zhuān)題報(bào)告和項(xiàng)目監(jiān)理工作總結(jié)報(bào)告; 12)審核簽認(rèn)分部分項(xiàng)和單位工程的質(zhì)量檢驗(yàn)評(píng)定資料,審查承包單位的竣工申請(qǐng),組織監(jiān)理人員對(duì)待驗(yàn)收的工程項(xiàng)目進(jìn)行質(zhì)量檢查,參與工程項(xiàng)目的竣工驗(yàn)收; 13)主持整理工程項(xiàng)目的監(jiān)理資料。2.專(zhuān)業(yè)監(jiān)理工程師應(yīng)履行以下職責(zé) 1)負(fù)責(zé)編制本專(zhuān)業(yè)的監(jiān)理實(shí)施細(xì)則; 2)負(fù)責(zé)本專(zhuān)業(yè)監(jiān)理工作的具體實(shí)施;
3)組織、指導(dǎo)、檢查的監(jiān)督本專(zhuān)業(yè)監(jiān)理人員的工作、當(dāng)人員需要調(diào)整時(shí),向總監(jiān)理工程師提出建議;
4)審查承包單位提交的涉及本專(zhuān)業(yè)的計(jì)劃、方案、申請(qǐng)、變更,并向總監(jiān)理工程師提出報(bào)告;
5)負(fù)責(zé)本專(zhuān)業(yè)分項(xiàng)工程驗(yàn)收及隱蔽工程驗(yàn)收;
6)定期向總監(jiān)理工程師提交本專(zhuān)業(yè)監(jiān)理工作實(shí)施情況報(bào)告,對(duì)重大問(wèn)題及時(shí)向總監(jiān)理工程師匯報(bào)和請(qǐng)示;
7)根據(jù)本專(zhuān)業(yè)監(jiān)理工程師實(shí)施情況做好監(jiān)理日記;
8)負(fù)責(zé)本專(zhuān)業(yè)監(jiān)理資料的收集、匯總及整理,參與編寫(xiě)監(jiān)理月報(bào);
9)核查進(jìn)場(chǎng)材料、設(shè)備、構(gòu)配件的原始憑證、檢測(cè)報(bào)告等質(zhì)量證明文件及其質(zhì)量情況,根據(jù)實(shí)際情況認(rèn)為有必要時(shí)對(duì)進(jìn)場(chǎng)材料、設(shè)備、構(gòu)配件進(jìn)行平行檢驗(yàn),合格時(shí)予以簽認(rèn); 10)負(fù)責(zé)本專(zhuān)業(yè)的工程計(jì)量工作,審核工程計(jì)量的數(shù)據(jù)和原始憑證。
3、監(jiān)理人員應(yīng)履行的職責(zé)
1)在專(zhuān)業(yè)監(jiān)理工程師的指導(dǎo)下開(kāi)展現(xiàn)場(chǎng)監(jiān)理工作;
2)檢查承包單位投入工程項(xiàng)目的人力、材料、主要設(shè)備及其使用、運(yùn)行情況,并做好檢查記錄;
3)復(fù)核或從施工現(xiàn)場(chǎng)直接獲取工程量計(jì)量的有關(guān)數(shù)據(jù)并簽署原始憑證;
4)按設(shè)計(jì)圖紙及有關(guān)標(biāo)準(zhǔn),對(duì)承包單位的工藝流程或施工工序進(jìn)行檢查和記錄,對(duì)加工制作及工序施工質(zhì)量檢查結(jié)果進(jìn)行記錄;
5)擔(dān)任旁站工作,發(fā)現(xiàn)問(wèn)題及時(shí)指出并向?qū)I(yè)監(jiān)理工程師報(bào)告; 6)做好監(jiān)理日記和有關(guān)的監(jiān)理記錄。
六、監(jiān)理工作內(nèi)容、方法和措施
本工程施工階段的監(jiān)理工作重點(diǎn)為質(zhì)量控制,并協(xié)助建設(shè)進(jìn)行進(jìn)度控制和投資控制,同時(shí)協(xié)助業(yè)主進(jìn)行施工安全文明管理。
1、質(zhì)量控制:
以事前、事中、事后控制相結(jié)合的方法,并以事前控制(預(yù)控)為主,加強(qiáng)事中控制,確保工程質(zhì)量。具體控制過(guò)程如下:
(一)施工測(cè)量放樣的控制
1)開(kāi)工前,審核批復(fù)承包商的施工測(cè)量放樣結(jié)果,并以此作為承包商申請(qǐng)開(kāi)工報(bào)告中測(cè)量準(zhǔn)備工作的依據(jù),具體工作內(nèi)容有: A.協(xié)助業(yè)主安排勘察設(shè)計(jì)單位向承包商交接樁,對(duì)設(shè)計(jì)的交樁進(jìn)行復(fù)核。
B.檢查承包商測(cè)量方面人員、儀器到位情況,查詢(xún)儀器的精度級(jí)別,必要時(shí)可指令承包商進(jìn)行復(fù)核儀器精度的測(cè)量。
C.檢查批復(fù)承包商對(duì)工程全線(xiàn)控制樁(平面、高程)恢復(fù)情況及復(fù)核精度。D.審核即將開(kāi)工路段和構(gòu)造物的施工測(cè)量及放樣情況。E.檢查承包商控制樁的制作、埋設(shè)保護(hù)情況。
2)施工中,隨時(shí)檢查承包商測(cè)量人員的測(cè)量記錄,檢查或旁站測(cè)量放樣工作,復(fù)核、審核測(cè)量結(jié)果并簽署意見(jiàn)。
3)竣工后,檢查承包商全線(xiàn)恢復(fù)定線(xiàn)和道路及其它構(gòu)造物竣工驗(yàn)收測(cè)量工作,審核測(cè)量報(bào)告,視情況組織部分路段復(fù)測(cè),核實(shí)因變更設(shè)計(jì)引起工程數(shù)量變動(dòng)所需的測(cè)量?jī)?nèi)容等。
(二)原材料及成品、半成品構(gòu)件的控制
1)承包商的原材料及成品、半成品構(gòu)件進(jìn)場(chǎng)前按施工規(guī)范和市政質(zhì)監(jiān)站規(guī)定的要求項(xiàng)目和頻率在監(jiān)理工程師見(jiàn)證下,進(jìn)行材料的送樣試驗(yàn)。首批進(jìn)場(chǎng)材料的質(zhì)量檢查結(jié)果,作為工程審批申請(qǐng)開(kāi)工報(bào)告的依據(jù)之一。
2)承包商所進(jìn)原材料(如水泥、石灰、鋼筋、標(biāo)準(zhǔn)磚等)以及半成品(道板、側(cè)平石等),需提供出廠(chǎng)證明、質(zhì)量保證書(shū)、市政質(zhì)監(jiān)站質(zhì)量認(rèn)可證書(shū)以及各種試驗(yàn)資料;材料到現(xiàn)場(chǎng)后,監(jiān)理將檢查其質(zhì)量情況,對(duì)質(zhì)量不合格的不允許使用,并清理出場(chǎng)。
3)承包商依照工程進(jìn)度按排材料進(jìn)場(chǎng)數(shù)量和規(guī)格;同時(shí)應(yīng)按規(guī)范要求搬運(yùn)及儲(chǔ)存材料,注意水泥防潮、鋼筋防銹、砂石分類(lèi)堆放等,各類(lèi)材料應(yīng)設(shè)標(biāo)簽;成品構(gòu)件運(yùn)輸及堆放應(yīng)符合施工規(guī)范的受力要求,避免產(chǎn)生不合理的附加應(yīng)力,使材料變形、受損、開(kāi)裂。
(三)雨水管線(xiàn)的控制
1)施工前,監(jiān)理檢查承包商進(jìn)場(chǎng)承插砼預(yù)制管道及UPVC管材的外觀質(zhì)量,并見(jiàn)證取樣進(jìn)行管材的試驗(yàn);不合格的管材一律不得使用。同時(shí)加強(qiáng)檢查接口橡膠圈的質(zhì)量及存放條件。2)溝槽開(kāi)挖關(guān)鍵對(duì)槽底寬度、高程、土質(zhì)及溝槽放坡、排水的檢查。墊層、基礎(chǔ)檢查砂石基礎(chǔ)及砼基礎(chǔ)的寬度、厚度、高程,并見(jiàn)證承包商砼試塊的制作,檢查砼試塊的養(yǎng)護(hù)情況。3)管道安裝重點(diǎn)檢查砼預(yù)制管道的吊管套拉、UPVC管材的上拱通病,保證管內(nèi)底標(biāo)高100%合格。
4)窨井砌筑重點(diǎn)控制砼基礎(chǔ)、井筒垂直、收口直順及磚墻的砌筑和抹面。
5)回填時(shí),槽內(nèi)應(yīng)無(wú)積水?;彝涟韬抿?yàn)收合格后才能進(jìn)行回填?;靥顣r(shí)嚴(yán)格檢查承包商的施工工藝和施工機(jī)械,并加強(qiáng)對(duì)灰土密實(shí)度的檢測(cè)和控制。
(四)道路路基的控制 1)路基施工
A.道路路基挖方作業(yè),必須按設(shè)計(jì)橫斷面整幅開(kāi)挖,控制亂挖和超挖,基底預(yù)留碾壓的沉降量。
B.檢查基底以下80CM范圍以?xún)?nèi)樹(shù)根及其它障礙物的清除情況。
C.快慢車(chē)道路基之間,由于新舊路基土層的承載力不等,軟硬程度不一,極易在連接部位產(chǎn)生路基承載力的不連續(xù),甚至不穩(wěn)定,從而發(fā)生路基整體性的破壞。因此,在挖到快慢車(chē)道搭接處,要控制承包商在快車(chē)道邊緣路基臺(tái)階的施工情況,其中臺(tái)階高不應(yīng)大于0.5米,臺(tái)階寬不小于1米。
D.在路基施工期間,要有效控制由于降水或附近地段流入路基的地面水及施工用水。2)路床整修及碾壓的質(zhì)量控制
A.為達(dá)到設(shè)計(jì)要求的路床頂面以下深30CM 的路基密實(shí)度(≥95%),需嚴(yán)格審查承包商路基施工人員、機(jī)具到位及配套情況,檢查承包商質(zhì)量自檢體系的建立及工作情況。嚴(yán)格控制路基的施工寬度、施工層厚、壓實(shí)機(jī)具和壓實(shí)工藝的執(zhí)行。B.為保證路面結(jié)構(gòu)厚度均勻,需加強(qiáng)對(duì)路床平整度、橫坡度和高程的檢查和整修。整修原則上是寧刮不墊。
(五)10%灰土底基層的控制
考慮到解放環(huán)路工程的地域性及文明施工,灰土應(yīng)盡量采用廠(chǎng)拌石灰土。
1)原材料的進(jìn)場(chǎng)及檢驗(yàn):檢查石灰的品質(zhì),鈣、鎂含量,使用期限、周期及粒徑要求;土質(zhì)的力學(xué)性能和粒徑;水質(zhì)情況。原材料的試驗(yàn)項(xiàng)目和頻率。
2)石灰土的施工控制:重點(diǎn)檢查石灰土的施工配合比、拌和設(shè)備、拌和工藝、混合料的運(yùn)輸卸放、攤鋪(松鋪厚度)、壓實(shí)及整修、養(yǎng)生。
3)石灰土的試驗(yàn)控制項(xiàng)目:灰劑量、含水量、壓實(shí)度、7天無(wú)側(cè)限抗壓強(qiáng)度、彎沉值等。
(六)水泥穩(wěn)定碎石的控制
水泥穩(wěn)定碎石基層全面開(kāi)工之前,承包商應(yīng)遞交水泥穩(wěn)定碎石的施工方案,并進(jìn)行試驗(yàn)段的施工。
1)原材料的質(zhì)量控制
A.水泥:宜采用有標(biāo)號(hào)、強(qiáng)度等級(jí)較低,初凝時(shí)間3小時(shí)以上,終凝時(shí)間不小于6小時(shí),安定性等指標(biāo)符合規(guī)范要求的各類(lèi)水泥。
B.碎石:采用粒徑不大于31.5mm,堅(jiān)硬、耐久、不含雜質(zhì)的顆粒級(jí)配,其壓碎值≯26%碎石級(jí)配盡可能接近要求級(jí)配范圍的中值,并控制級(jí)配中細(xì)粒料的含量,石粉的塑性指數(shù)。C.水:宜采用飲用水。2)混合料組成設(shè)計(jì)
水泥穩(wěn)定碎石的原材料在監(jiān)理工程師見(jiàn)證下,從承包商的拌和廠(chǎng)倉(cāng)庫(kù)料場(chǎng)取樣送檢市政檢測(cè)中心試驗(yàn)室。由檢測(cè)中心試驗(yàn)室根據(jù)見(jiàn)證取樣合格的原材料分五種水泥劑量進(jìn)行試配,確定適宜的配合比,水泥計(jì)量取低值為宜。3)水泥穩(wěn)定碎石的施工控制 A.混合料的集中拌和
承包商根據(jù)市政檢測(cè)中心試驗(yàn)室提供的配合比進(jìn)行拌和時(shí),首先應(yīng)檢測(cè)集料的含水量,同時(shí)根據(jù)施工設(shè)備、運(yùn)輸車(chē)輛、天氣因素等調(diào)整混合料的用水量及水泥劑量,其中用水量宜為+2~3%,水泥用量最大不宜超過(guò)+0.5%。拌和時(shí),應(yīng)先干拌均勻后加水濕拌至混合料色澤一致。
B.混合料的運(yùn)輸
拌好的混合料應(yīng)迅速運(yùn)至施工現(xiàn)場(chǎng)攤鋪。一工作班鋪料長(zhǎng)度應(yīng)根據(jù)拌和、壓實(shí)的能力而定,以保證從拌料至終壓能在3小時(shí)內(nèi)完成。C.混合料的試驗(yàn)段
正式攤鋪前應(yīng)進(jìn)行混合料試驗(yàn)段的鋪筑,試驗(yàn)段的長(zhǎng)度宜為100~200米。試驗(yàn)段的鋪筑是為驗(yàn)證施工的混合料配合比,確定混合料的松鋪厚度,確定適宜的施工工藝,確定每一工作班的合適長(zhǎng)度,為后續(xù)施工提供可靠的施工依據(jù)。D.混合料的攤鋪
攤鋪時(shí),根據(jù)試驗(yàn)段的松鋪系數(shù),在兩側(cè)指示樁上控制施工高程進(jìn)行攤鋪。同時(shí),在鋪好的混合料層上全厚挖取試料,見(jiàn)證封樣送市政檢測(cè)中心試驗(yàn)室做7天無(wú)側(cè)限抗壓強(qiáng)度試驗(yàn)及水泥劑量的試驗(yàn)。E.混合料的碾壓
混合料碾壓時(shí),先輕壓穩(wěn)壓1~2遍,后重壓振壓5~6遍,直至達(dá)到要求的密實(shí)度為止,基層兩側(cè)應(yīng)多壓1~2遍。碾壓結(jié)束后,對(duì)局部“彈簧”、“離析”、“松散”應(yīng)立即進(jìn)行翻拌處理壓實(shí)。
F.混合料的養(yǎng)生 養(yǎng)生是水泥穩(wěn)定碎石基層施工必須的施工工序,濕治養(yǎng)護(hù)不及時(shí),易產(chǎn)生表面裂縫、表皮松散、強(qiáng)度不足等質(zhì)量通病,因此,水泥穩(wěn)定碎石灑水養(yǎng)護(hù)是監(jiān)理部門(mén)質(zhì)量管理的重要環(huán)節(jié)。養(yǎng)生時(shí)禁止一切機(jī)動(dòng)車(chē)輛通行。4)水泥穩(wěn)定碎石接縫的處理 A.橫向接縫的處理
解放環(huán)路工程由于施工環(huán)境復(fù)雜,交叉口、道口較多,怎樣有條不紊組織好施工段落,減少橫向接縫的處理,是加強(qiáng)對(duì)橫向接縫質(zhì)量控制的重中之重。B.縱向接縫的控制
解放環(huán)路工程根據(jù)設(shè)計(jì)要求,對(duì)全部慢車(chē)道及部分快車(chē)道進(jìn)行改建,且采取半封閉施工,縱向裂縫無(wú)法避免,但施工時(shí)應(yīng)盡量避免縱向裂縫的出現(xiàn)。兩側(cè)慢車(chē)道改建段,一側(cè)可采用一臺(tái)攤鋪機(jī)攤鋪,快慢車(chē)道接縫處攤鋪瀝青時(shí)根據(jù)設(shè)計(jì)加鋪玻璃纖維土工格柵。全幅道路改建段,施工時(shí)可采用兩臺(tái)攤鋪機(jī)呈階梯形攤鋪,縱縫位置盡可能控制在道路中心線(xiàn)左右,并垂直相接,攤鋪瀝青時(shí)根據(jù)設(shè)計(jì)加鋪玻璃纖維土工格柵。
(七)瀝青砼路面的控制
解放環(huán)路工程本次路面的施工為瀝青結(jié)構(gòu)層,且瀝青面層為新工藝SBS瀝青砼,為此監(jiān)理組不僅需對(duì)現(xiàn)場(chǎng)施工進(jìn)行認(rèn)真監(jiān)控,還安排專(zhuān)業(yè)的試驗(yàn)監(jiān)理工程師深入承包商瀝青拌和廠(chǎng)加強(qiáng)原材料、生產(chǎn)過(guò)程的監(jiān)控,確保瀝青路面施工一次成型。1)瀝青砼路面開(kāi)工前準(zhǔn)備工作的控制
瀝青砼路面開(kāi)工前準(zhǔn)備工作的完善與否,將直接影響到瀝青砼路面施工的進(jìn)度、質(zhì)量,施工準(zhǔn)備工作的大體內(nèi)容有: A.集料的選擇
集料質(zhì)量的檢查監(jiān)控非常重要。集料質(zhì)量的控制需延伸到源頭,具體控制原則有:①集料質(zhì)量符合規(guī)范和設(shè)計(jì)的要求;②選擇生產(chǎn)規(guī)模大、生產(chǎn)量穩(wěn)定,碎石機(jī)械設(shè)備組合合理的供貨商;③盡量少選供貨商,減少集料質(zhì)量波動(dòng)大的現(xiàn)象。B.瀝青砼配合比試驗(yàn)
瀝青砼配合比設(shè)計(jì)根據(jù)規(guī)范要求需進(jìn)行分階段組成設(shè)計(jì),最終確定生產(chǎn)用的標(biāo)準(zhǔn)配合比。監(jiān)理組安排專(zhuān)業(yè)的試驗(yàn)工程師進(jìn)行全過(guò)程監(jiān)控。C.基層的驗(yàn)收及整修
在瀝青砼路面施工前需加強(qiáng)對(duì)路面基層的驗(yàn)收及整修。承包商提供水泥穩(wěn)定碎石基層的彎沉、密實(shí)度、強(qiáng)度等資料,經(jīng)監(jiān)理驗(yàn)收合格后才能攤鋪瀝青路面。因施工車(chē)輛的出入、半封閉施工等原因,造成在交叉口、道口、構(gòu)造物前端等地方出現(xiàn)的坑槽、松散等質(zhì)量通病,需進(jìn)行整修。如坑槽較大,需清除松散粒料,修整成規(guī)劃坑槽,然后用新料填補(bǔ)碾壓;如坑槽較小且深度小于3CM,只需在瀝青砼底基層施工時(shí)進(jìn)行填補(bǔ)。D.確定施工方案
瀝青砼路面施工前,承包商應(yīng)遞交施工方案報(bào)業(yè)主及監(jiān)理審批,并提供完整的瀝青砼分階段組成設(shè)計(jì)及各種原材料的試驗(yàn)資料;并對(duì)各種施工機(jī)械進(jìn)行全面的檢查及調(diào)試,保證瀝青砼路面施工的連續(xù)性。E.透層油或粘層油的施工
透層油施工前,應(yīng)清掃基層,對(duì)側(cè)平石及窨井等進(jìn)行適當(dāng)防護(hù),以防污染。灑布瀝青時(shí)應(yīng)按設(shè)計(jì)用量一次澆灑均勻,如有遺漏,采用人工補(bǔ)灑。灑布瀝青后,應(yīng)立即撒鋪適量的石屑,并用6~8T鋼筒式壓路機(jī)穩(wěn)壓一遍。在鋪筑瀝青砼底層時(shí),再清掃多余的浮動(dòng)石屑。
粘層油施工應(yīng)灑布均勻,在平石、收水井、窨井等側(cè)面無(wú)法機(jī)械灑布的地方,采用刷子人工涂刷;粘層油灑布后,禁止一切車(chē)輛及行人通行,并立即進(jìn)行瀝青砼的施工,但乳化瀝青需待破乳、水分蒸發(fā)完后鋪筑。2)瀝青砼路面施工控制要點(diǎn) A.瀝青砼混合料的拌和
①檢查承包商瀝青砼拌和設(shè)備的運(yùn)行和拌和工藝的落實(shí)情況; ②檢查施工配合比的執(zhí)行、自動(dòng)配料和配料準(zhǔn)確性的情況; ③檢查原材料預(yù)熱、混合料加熱等工藝確定和執(zhí)行情況; ④每天對(duì)承包商的抽樣試驗(yàn)及現(xiàn)場(chǎng)生產(chǎn)記錄進(jìn)行審核。B.瀝青砼混合料的運(yùn)輸
①檢查承包商瀝青砼運(yùn)輸車(chē)輛的保溫、保潔、防污染措施的落實(shí)情況;
②根據(jù)瀝青砼的運(yùn)距和工地?cái)備佀俣?,檢查運(yùn)輸車(chē)輛的配備情況,既要避免攤鋪機(jī)待料,也要避免待攤壓料情況的發(fā)生,以保證勻速、連續(xù)施工。C.瀝青砼混合料的攤鋪
①攤鋪前,先要檢查攤鋪機(jī)的攤鋪性能、刮平刀板、自動(dòng)找平裝置的調(diào)節(jié)情況;
②攤鋪時(shí),盡可能一次全幅攤鋪,分路幅攤鋪時(shí),要考慮接縫工藝及質(zhì)量要求。具體解放環(huán)路工程根據(jù)設(shè)計(jì)及現(xiàn)場(chǎng)情況,可考慮采用兩臺(tái)攤鋪機(jī)攤鋪,快慢車(chē)道間采用熱接縫工藝,道路中線(xiàn)為冷接縫,上下錯(cuò)縫,并將接縫位置控制在劃線(xiàn)范圍內(nèi);
③控制混合料攤鋪溫度不小于110℃;特別注意控制SBS瀝青砼混合料比中下層瀝青砼高10~20℃;
④經(jīng)常檢查瀝青砼松鋪系數(shù)執(zhí)行及調(diào)整情況; ⑤檢查平整度和路拱調(diào)整措施的落實(shí)。D.瀝青砼混合料的碾壓
①檢查碾壓工藝執(zhí)行,目測(cè)碾壓質(zhì)量;
②檢查窨井周?chē)捌渌鼧?gòu)筑物旁人工碾壓工具、工藝、碾壓質(zhì)量。E.其它
①施工縫設(shè)置及要求,上、下層錯(cuò)縫及距離要求的檢查; ②低溫、雨天施工安排和要求,冷料、濕料處理情況的檢查。3)瀝青砼路面試驗(yàn)檢測(cè)項(xiàng)目
①原材料檢測(cè):瀝青、集料(粗集料、細(xì)集料、填料)、抗剝落劑;
②混合料檢測(cè):馬歇爾穩(wěn)定度、流值、空隙率、飽和度、瀝青含量、礦料級(jí)配等; ③壓實(shí)度檢測(cè):取芯法等 ④層厚:取芯法
4)SBS瀝青面層施工控制要點(diǎn)
解放環(huán)路瀝青上面層設(shè)計(jì)采用SBS瀝青面層,此工藝在無(wú)錫市政工程上運(yùn)用較少,因此,在施工質(zhì)量控制時(shí)應(yīng)注意以下幾個(gè)環(huán)節(jié):
①做好施工前機(jī)械設(shè)備配套及施工人員交底工作;
②瀝青、集料、摻加劑等原材料要符合技術(shù)標(biāo)準(zhǔn),承包商需提供完整的三階段組成設(shè)計(jì)及混合料配合比設(shè)計(jì);
③SBS瀝青混合料出廠(chǎng)、攤鋪、碾壓等溫度要高于一般瀝青混合料10~20℃,所以嚴(yán)格掌握好三個(gè)關(guān)鍵工序的溫度是施工中重要的環(huán)節(jié);
④SBS瀝青混合料每盤(pán)拌和時(shí)間應(yīng)比普通瀝青混合料長(zhǎng)20秒左右;
⑤由于SBS結(jié)構(gòu)對(duì)路表的特定要求,碾壓時(shí)不得采用輪胎式壓路機(jī),用不少于3臺(tái)的8~10T雙鋼輪振動(dòng)式壓路機(jī)勻速碾壓,終壓溫度不得低于110℃; ⑥施工中應(yīng)及時(shí)檢查鋪裝后的透水系數(shù)、混合料空隙率極其配合比,否則將因空隙率大而透水,從而導(dǎo)致路面損壞。
(八)道路附屬設(shè)施的控制 1)側(cè)平石施工的控制
加強(qiáng)對(duì)承包商側(cè)平石預(yù)制品的質(zhì)量檢查,對(duì)缺角、損邊、尺寸不符等影響外觀質(zhì)量的側(cè)平石一律清除出場(chǎng)。鋪砌時(shí)控制好側(cè)平石的直順度、相鄰塊高差、縫寬等,對(duì)平坡段采取的“挑三壓三”措施加強(qiáng)監(jiān)控。2)收水井、收水管的控制
由于本次解放環(huán)路工程道路結(jié)構(gòu)層的原因,收水管的埋設(shè)深度應(yīng)控制在水泥穩(wěn)定碎石下,對(duì)埋設(shè)深度較淺的管線(xiàn)需采取措施進(jìn)行加固。收水井施工時(shí),需控制好井的軸線(xiàn)位置及落底的深度等。3)人行道的控制
等待景觀設(shè)計(jì)圖明確結(jié)構(gòu)層后再編寫(xiě)。
(九)沿河駁岸的監(jiān)理 1)擋墻砌筑
擋墻采用金山塊石砌筑,其面石為料石砌筑,以保證外觀的美觀。砌筑時(shí)要求錯(cuò)縫砌筑、砂漿飽滿(mǎn)、座漿砌筑、做到“兩順一丁”,以保證墻體的穩(wěn)定和牢固。對(duì)“三角縫”要求不能大于規(guī)范的要求。勾縫要美觀,牢固,勻稱(chēng)。
(十)工序交接檢查:
堅(jiān)持上道工序不經(jīng)檢查驗(yàn)收不準(zhǔn)進(jìn)行下道工序施工的原則,上道工序完成后,先由承包商進(jìn)行自檢,自檢認(rèn)為合格填報(bào)驗(yàn)單后再通知現(xiàn)場(chǎng)監(jiān)理工程師到現(xiàn)場(chǎng)會(huì)同檢驗(yàn),檢驗(yàn)合格后方能進(jìn)行下道工序。
(十一)工程變更和處理
工程變更由承包商書(shū)面提出工程變更書(shū),由監(jiān)理通知業(yè)主及設(shè)計(jì)單位來(lái)現(xiàn)場(chǎng)組織審核,協(xié)商提出是否同意變更,同意變更的由設(shè)計(jì)院出變更圖等書(shū)面文件。
(十二)行使質(zhì)量監(jiān)督,對(duì)違反操作規(guī)程的有權(quán)發(fā)布各種指令。
為了保證工程質(zhì)量,出現(xiàn)下列情況之一者,監(jiān)理工程師有權(quán)發(fā)布監(jiān)理工程師通知,直至停工整改通知。
A、未經(jīng)驗(yàn)收即進(jìn)行下道工序施工。B、工程質(zhì)量下降指出后,未采取有效改正措施或采取了一定措施而效果不好,繼續(xù)作業(yè)者。C、擅自采用未經(jīng)許可或批準(zhǔn)的材料。D、擅自變更設(shè)計(jì)圖紙的要求。E、擅自將工程轉(zhuǎn)包。
(十三)項(xiàng)目竣工驗(yàn)收:
整個(gè)工程竣工后,由承包商提供工程技術(shù)資料(含竣工圖)質(zhì)量簽證文件,工程結(jié)算資料報(bào)現(xiàn)場(chǎng)監(jiān)理工程師審閱確認(rèn)后,組織初驗(yàn),監(jiān)理對(duì)工程質(zhì)量等級(jí)評(píng)定提出建議意見(jiàn)。
2、進(jìn)度控制
本工程任務(wù)重、時(shí)間緊,因此必須加強(qiáng)進(jìn)度控制,及時(shí)發(fā)現(xiàn)問(wèn)題,及時(shí)解決問(wèn)題,確保合同工期的順利執(zhí)行。
1)監(jiān)理人員配合甲方協(xié)調(diào)承包商關(guān)系,合理平衡、調(diào)整進(jìn)度計(jì)劃,促使先行施工按時(shí)或提前完成,保證后續(xù)工程及時(shí)順利施工。
2)若實(shí)際進(jìn)度滯后計(jì)劃進(jìn)度時(shí),協(xié)助承包商分析原因,調(diào)整計(jì)劃,督促承包商采取有力措施(如增加人力、物力、機(jī)械或延長(zhǎng)工時(shí)等)加快施工進(jìn)度,確保進(jìn)度計(jì)劃的實(shí)施。
3、投資控制
1)以批準(zhǔn)的工程量清單為依據(jù),進(jìn)行工程計(jì)量和支付。嚴(yán)格審核每月有效工程量(已經(jīng)監(jiān)理簽字驗(yàn)收的),并簽注意見(jiàn),作為甲方撥付工程進(jìn)度款的依據(jù)。2)按業(yè)主的有關(guān)規(guī)定進(jìn)行變更工程量的簽證,審核變更工程量的合理性,無(wú)變更依據(jù)(設(shè)計(jì)變更、甲方指令等)一律不得簽證。
3)以預(yù)控方式盡量消除或避免承包商有向業(yè)主索賠的隱含行為,慎重處理索賠事宜做好工程計(jì)量臺(tái)帳,及時(shí)對(duì)照合同檢查費(fèi)用支付的增加或減少,分析其原因,必要時(shí)報(bào)告業(yè)主。
4、信息管理
1)及時(shí)完成監(jiān)理日記,規(guī)范使用監(jiān)理記錄。
2)及時(shí)完成監(jiān)理臺(tái)帳記錄,包括來(lái)發(fā)文登記表、試驗(yàn)記錄登記表、監(jiān)理工程師驗(yàn)收臺(tái)帳記錄等。
3)及時(shí)有效處理外來(lái)文件,執(zhí)行設(shè)計(jì)變更和甲方指令。
4)施工資料的歸檔按建設(shè)部221號(hào)文要求,監(jiān)理報(bào)驗(yàn)資料按江蘇省建設(shè)廳第三套監(jiān)理資料。
5、工程創(chuàng)優(yōu)措施
為保證工程達(dá)到優(yōu)良,我監(jiān)理公司擬采取如下措施:
1)組織強(qiáng)有力的監(jiān)理組,使其能貫徹好甲方及我公司的精神,把工程的質(zhì)量管好; 2)審查并督促承包商建立健全三級(jí)驗(yàn)收及質(zhì)保體系;
3)除開(kāi)工時(shí)的“施工組織設(shè)計(jì)”和“監(jiān)理交底”外,針對(duì)每一重點(diǎn)工序均要求承包商報(bào)施工方案,監(jiān)理將進(jìn)行審批和進(jìn)行專(zhuān)門(mén)的交底,并嚴(yán)格執(zhí)行分項(xiàng)工程開(kāi)工報(bào)告制度; 4)監(jiān)理過(guò)程中加強(qiáng)預(yù)控,現(xiàn)場(chǎng)加強(qiáng)旁站監(jiān)理,關(guān)鍵工序監(jiān)理要一直在現(xiàn)場(chǎng)監(jiān)理。
6、安全生產(chǎn)、文明施工管理
監(jiān)理組在施工監(jiān)理過(guò)程中應(yīng)堅(jiān)持“安全第一,預(yù)防為主”和貫徹“質(zhì)量第一”的方針,依靠管理和技術(shù)進(jìn)步,認(rèn)真履行有關(guān)安全生產(chǎn)、文明施工管理的相應(yīng)職責(zé),保障人身和工程安全,確保工程質(zhì)量。監(jiān)理組進(jìn)場(chǎng)后,就對(duì)所有監(jiān)理人員進(jìn)行施工現(xiàn)場(chǎng)安全生產(chǎn)、文明施工的監(jiān)理知識(shí)和能力的教育,使其掌握有關(guān)安全生產(chǎn)規(guī)章制度,認(rèn)真履行相應(yīng)職責(zé)和義務(wù)。在施工監(jiān)理過(guò)程中,監(jiān)理人員主要督促、檢查施工單位做好以下工作:
(一)安全生產(chǎn)
1)施工現(xiàn)場(chǎng)(工地)必須具備良好的施工環(huán)境和作業(yè)條件,實(shí)行安全生產(chǎn),避免發(fā)生人身傷亡和工程事故。進(jìn)入施工現(xiàn)場(chǎng)的所有人員必須遵守施工現(xiàn)場(chǎng)安全管理規(guī)定。
2)施工現(xiàn)場(chǎng)(工地)安全生產(chǎn)實(shí)行項(xiàng)目經(jīng)理負(fù)責(zé)制。應(yīng)建立健全工地安全組織保障體系,制定和完善安全管理制度,采取各項(xiàng)安全防護(hù)措施,確保施工正常進(jìn)行。
3)施工現(xiàn)場(chǎng)(工地)所有施工人員必須經(jīng)過(guò)上崗前的安全教育。應(yīng)備有各個(gè)工種安全生產(chǎn)手冊(cè)或須知,做到每個(gè)職工人手一冊(cè),使從事施工活動(dòng)的每個(gè)職工具備本工種的安全常識(shí),增強(qiáng)防范意識(shí)。特種工種須經(jīng)專(zhuān)業(yè)培訓(xùn),持證上崗。
4)進(jìn)入施工現(xiàn)場(chǎng)(工地)的所有人員,應(yīng)穿載、使用有關(guān)防護(hù)用品、用具。
5)施工現(xiàn)場(chǎng)(工地)應(yīng)設(shè)置必要的提示、警示、警告等各種安全防范標(biāo)志,避免施工現(xiàn)場(chǎng)人員可能發(fā)生的意外傷害。施工現(xiàn)場(chǎng)(工地)應(yīng)設(shè)置醒目的告示牌,禁止閑雜人員進(jìn)入。未經(jīng)許可、擅自闖入工地的任何人員應(yīng)對(duì)其行為及由此產(chǎn)生的后果承擔(dān)相應(yīng)責(zé)任。
6)施工現(xiàn)場(chǎng)(工地)必須杜絕違章指揮、違章作業(yè)、違反勞動(dòng)紀(jì)律的“三違”行為。7)施工現(xiàn)場(chǎng)(工地)必須做好防火、防電、防爆和防墜等防護(hù)工作。具體內(nèi)容如下:(1)必須遵守國(guó)家有關(guān)消防規(guī)定,各種消防設(shè)施配置齊全,并由專(zhuān)人負(fù)責(zé),經(jīng)常檢查和定期更換。油庫(kù)、易燃品存儲(chǔ)等重點(diǎn)防火區(qū)域必須禁止火源進(jìn)入。
(2)供電線(xiàn)路布設(shè)及施工用電必須遵守有關(guān)安全用電的規(guī)程的規(guī)定,應(yīng)避免妨礙作業(yè)和交通。
(3)高壓氣瓶、氧氣瓶等易爆物品的使用和管理性能必須遵守國(guó)家有關(guān)安全規(guī)定,并保持足夠的安全距離,確保安全。(4)高處作業(yè)必須遵守有關(guān)作業(yè)規(guī)程,設(shè)置必要的安全防護(hù)網(wǎng)或防護(hù)欄桿。特殊情況下應(yīng)使用安全帶。
8)施工現(xiàn)場(chǎng)(工地)應(yīng)建立完善的機(jī)具設(shè)備例保、檢修制度,保證機(jī)械設(shè)備正常安全動(dòng)作。9)施工企業(yè)對(duì)施工現(xiàn)場(chǎng)(工地)安全生產(chǎn)負(fù)有直接領(lǐng)導(dǎo)責(zé)任。對(duì)施工現(xiàn)場(chǎng)存在的事故隱患必須責(zé)令項(xiàng)目經(jīng)理予以整改。施工企業(yè)對(duì)施工現(xiàn)場(chǎng)(工地)發(fā)生的重大事故應(yīng)按照“三不放過(guò)”原則,除按規(guī)定的程序上報(bào)有關(guān)部門(mén)外,同時(shí)應(yīng)向行政主管部門(mén)及建設(shè)單位提交事故報(bào)告,不得隱瞞不報(bào)。
(二)、文明施工
1)施工現(xiàn)場(chǎng)(工地)應(yīng)建立文明施工管理和監(jiān)督管理網(wǎng)絡(luò),建立以項(xiàng)目經(jīng)理為第一負(fù)責(zé)人的組織保證體系。推行現(xiàn)代管理方法,組織科學(xué)施工,創(chuàng)造一個(gè)良好的施工環(huán)境和作業(yè)條件,保護(hù)職工的健康,確保施工活動(dòng)正常進(jìn)行。
2)施工現(xiàn)場(chǎng)(工地)項(xiàng)目經(jīng)理部必須實(shí)行目標(biāo)管理。應(yīng)將目標(biāo)計(jì)劃和管理網(wǎng)絡(luò)制成圖表上墻,并按季、月進(jìn)行目標(biāo)細(xì)化,根據(jù)實(shí)際進(jìn)度進(jìn)行動(dòng)態(tài)跟蹤管理,一級(jí)施工企業(yè)應(yīng)推行計(jì)算機(jī)動(dòng)態(tài)跟蹤管理。
3)施工單位應(yīng)按照?qǐng)龅乜偲矫鎴D設(shè)置各項(xiàng)臨時(shí)設(shè)施,必須布局合理,文明責(zé)任區(qū)劃分明確,并有明顯標(biāo)記。同時(shí)應(yīng)設(shè)置明顯的標(biāo)牌,標(biāo)明工程項(xiàng)目名稱(chēng)、工程概況、建設(shè)單位、設(shè)計(jì)單位、監(jiān)理單位、施工單位、項(xiàng)目經(jīng)理和技術(shù)負(fù)責(zé)人的姓名,開(kāi)、竣工日期。
4)施工現(xiàn)場(chǎng)(工地)作業(yè)區(qū)道路平整、設(shè)有路標(biāo)。機(jī)具材料應(yīng)做到“二整”:施工機(jī)械設(shè)備應(yīng)保持狀況良好、停置整齊;施工材料堆放有序、存儲(chǔ)合理規(guī)整。
5)作業(yè)區(qū)道路和現(xiàn)場(chǎng)按工程需要須有足夠的照明設(shè)施;施工電源要集中布置,統(tǒng)一接線(xiàn),專(zhuān)人負(fù)責(zé),并定期檢查。
6)工地現(xiàn)場(chǎng)外觀應(yīng)做到“三潔”:施工場(chǎng)地整潔、生活環(huán)境清潔、施工產(chǎn)品美觀凈潔。場(chǎng)區(qū)及施工范圍內(nèi)的溝道、地面無(wú)廢料、垃圾和油垢,應(yīng)做到工完料盡場(chǎng)地清。辦公室、作業(yè)區(qū)、倉(cāng)庫(kù)等場(chǎng)所內(nèi)部應(yīng)符合衛(wèi)生通風(fēng)照明等要求,職工宿舍內(nèi)外應(yīng)保持清潔、衛(wèi)生,施工產(chǎn)品符合規(guī)范要求,外觀潔凈、美觀。
7)禁煙區(qū)嚴(yán)禁吸煙。禁止邊作業(yè)邊吸煙。
8)施工現(xiàn)場(chǎng)(工地)項(xiàng)目經(jīng)理部應(yīng)對(duì)全體施工現(xiàn)場(chǎng)人員進(jìn)行文明施工教育?,F(xiàn)場(chǎng)管理員應(yīng)統(tǒng)一著裝,胸前佩掛證卡,并應(yīng)自覺(jué)遵守工地各項(xiàng)規(guī)章制度和勞動(dòng)紀(jì)律,杜絕“三違”現(xiàn)象。9)必須遵守國(guó)家有關(guān)環(huán)境保護(hù)規(guī)定,避免和降低灰塵等對(duì)周?chē)h(huán)境的污染。
對(duì)未按規(guī)定施工,導(dǎo)致施工現(xiàn)場(chǎng)存有事故隱患的施工單位,要求其限期整改,到期未作整改的,令其暫停施工,并上報(bào)業(yè)主作進(jìn)一步處理。
七、監(jiān)理工作程序
見(jiàn)下圖
八、監(jiān)理工作制度
1、設(shè)計(jì)文件、圖紙審查制度
2、技術(shù)交底制度
3、材料、構(gòu)件檢驗(yàn)及復(fù)驗(yàn)制度
4、設(shè)計(jì)變更制度
5、隱蔽工程檢查制度
6、工程質(zhì)量監(jiān)理制度
7、工程質(zhì)量檢驗(yàn)制度
8、工程質(zhì)量事故處理制度
9、工程進(jìn)度檢查制度
10、工程投資監(jiān)督制度
11、監(jiān)理報(bào)告制度
12、竣工驗(yàn)收制度
13、監(jiān)理日志和會(huì)議制度
九、監(jiān)理設(shè)施
1、工程檢測(cè)設(shè)備(見(jiàn)附表)
2、工程試驗(yàn)設(shè)備(見(jiàn)附表)
3、交通通信設(shè)備(見(jiàn)附表)
第五篇:市政道路監(jiān)理規(guī)劃
市政道路監(jiān)理規(guī)劃范本通用1
發(fā)包方(全稱(chēng)):__________________(以下簡(jiǎn)稱(chēng)甲方)
承包方(全稱(chēng)):__________________(以下簡(jiǎn)稱(chēng)乙方)
依照《合同法》和《建筑安裝工程承包合同條款》及其他有關(guān)法律、行政法規(guī),遵循平等、自愿、公平和誠(chéng)實(shí)信用的原則,甲方將負(fù)責(zé)施工的_________市政道路工程承包給乙方。為了保證本工程的、文明施工、質(zhì)量和進(jìn)度,明確甲乙雙方的權(quán)利和義務(wù),經(jīng)甲乙雙方就有關(guān)__________________市政道路工程施工事項(xiàng)協(xié)商一致,特訂立本施工承包合同,以資共同遵守,具體條款如下:
一、工程概況
1、工程名稱(chēng):___________________________
2、工程地點(diǎn):___________________________
3、建設(shè)單位:___________________________
二、工程承包方式、范圍和內(nèi)容
1、工程承包方式為包工包料、包機(jī)械(含進(jìn)出場(chǎng))、包、文明施工、包質(zhì)量、包工期。
2、工程承包范圍為市政道路工程施工,具體工程量以施工圖、單、甲方認(rèn)定的市政道路工程量為準(zhǔn)。
3、工程承包內(nèi)容為市政道路工程的材料供應(yīng)、材料檢驗(yàn)和施工涉及的內(nèi)容及施工全過(guò)程涉及的全部質(zhì)量檢驗(yàn),全部技術(shù)資料的收集、整理、匯總成冊(cè)和臨電、臨水、臨時(shí)設(shè)施及工程決算等有關(guān)施工內(nèi)容。
三、工程造價(jià)及計(jì)價(jià)依據(jù)
1、本工程采用方式,此價(jià)格涵蓋了完成該工程項(xiàng)目所需的包括所有土建安裝費(fèi)用、質(zhì)檢費(fèi)用、水電費(fèi)、管理費(fèi)、利潤(rùn)、稅金、勞務(wù)、監(jiān)督、機(jī)械進(jìn)出場(chǎng)費(fèi)、文明施工費(fèi)用。該單價(jià)在合同實(shí)施期間保持不變。
2、設(shè)計(jì)變更所增加的費(fèi)用,有合同單價(jià)的按合同單價(jià),沒(méi)有合同單價(jià)的根據(jù)岳陽(yáng)市20市政定額再結(jié)合岳陽(yáng)市有關(guān)文件進(jìn)行編制,如定額中沒(méi)有的子項(xiàng),可套用土建定額中相應(yīng)的子項(xiàng),費(fèi)率按市政定額計(jì)取.設(shè)計(jì)變更中所增加的材料:報(bào)價(jià)書(shū)中有的按報(bào)價(jià)書(shū),報(bào)價(jià)書(shū)中沒(méi)有的承包人應(yīng)報(bào)所需材料的名稱(chēng)、品牌、規(guī)格型號(hào)、等級(jí)、產(chǎn)地、價(jià)格,經(jīng)發(fā)包人審定后方可使用,并作為結(jié)算依據(jù)。
3、竣工結(jié)算,工程量按實(shí)結(jié)算。
四、工程工期
1、開(kāi)工日期:_________年_________月_________日
2、竣工日期:_________年_________月_________日
3、本工程施工工期必須在保證工程質(zhì)量前提下按甲方指定的工期完成。乙方按甲方指定工期延期_________天后,第_________天開(kāi)始每延一天按_________元處罰,罰最多不超過(guò)工程造價(jià)的_________%。
4、遇人力不可抗拒因素,工期按監(jiān)理、建設(shè)單位簽證累計(jì)工期順延,乙方發(fā)生的增加費(fèi)用由建設(shè)單位簽證。乙方在上述情況發(fā)生_________天內(nèi),就延誤時(shí)間、內(nèi)容和因此發(fā)生的增加費(fèi)用支出向甲方及時(shí)提出報(bào)告,由甲方、監(jiān)理協(xié)助簽證。
五、工程質(zhì)量
甲乙雙方約定的市政道路工程質(zhì)量為按現(xiàn)行有關(guān)質(zhì)量驗(yàn)收標(biāo)準(zhǔn)驗(yàn)收(包括材料),必須確保一次性合格,且必須具備優(yōu)質(zhì)工程質(zhì)量驗(yàn)評(píng)要求和甲方企業(yè)標(biāo)準(zhǔn)要求,不準(zhǔn)出現(xiàn)由于乙方的材料或乙方施工質(zhì)量問(wèn)題引起對(duì)工
六、甲乙雙方責(zé)任
1、甲方責(zé)任
(1)全面履行合同,確保乙方正常施工。
(2)乙方要求的有關(guān)本工程的技術(shù)資料。
(3)及時(shí)協(xié)助乙方做好有關(guān)簽證工作,對(duì)乙方提交的簽證報(bào)告在3天內(nèi)簽復(fù)。
(4)負(fù)責(zé)辦好施工手續(xù)。
(5)督促乙方做好管理,文明施工。
(6)向乙方堆場(chǎng)、道路、設(shè)備作業(yè)等場(chǎng)地。
(7)甲方應(yīng)為乙方布置臨時(shí)設(shè)施的場(chǎng)地和臨時(shí)用水水源、臨時(shí)用電電源,乙方員工住宿由乙方自理,施工用電線(xiàn)電纜、開(kāi)關(guān)箱、照明燈具和機(jī)具、水費(fèi)、電費(fèi)等由乙方負(fù)責(zé)承擔(dān)。
2、乙方責(zé)任
(1)全面履行施工合同,嚴(yán)格按現(xiàn)行標(biāo)準(zhǔn)、規(guī)程、規(guī)范和設(shè)計(jì)要求組織施工,嚴(yán)格履行質(zhì)量、、文明施工,工期的合同要求,確保正常施工。
(2)服從甲方、監(jiān)理單位的指揮和管理。
(3)服從甲方現(xiàn)場(chǎng)有關(guān)部門(mén)和職能人員的監(jiān)督管理。
(4)負(fù)責(zé)其施工機(jī)具、設(shè)備和人員調(diào)配,乙方保證進(jìn)場(chǎng)的機(jī)具設(shè)備能滿(mǎn)足施工和甲方管理的`需要,人員調(diào)配投入計(jì)劃必須征得甲方同意,現(xiàn)場(chǎng)管理力量必須滿(mǎn)足施工和甲方管理的要求。
(5)因乙方原因造成的質(zhì)量事故,乙方必須無(wú)條件按甲方和甲、乙雙方合同的要求返工至合格,并承擔(dān)由此產(chǎn)生的全部施工增加費(fèi)用。
(6)進(jìn)場(chǎng)后,按甲方要求及時(shí)向甲方提交甲方(或質(zhì)監(jiān)部門(mén))認(rèn)定為齊全完整有效的相關(guān)工程技術(shù)資料及其他相關(guān)資料。
(7)全力配合有關(guān)部門(mén)對(duì)施工現(xiàn)場(chǎng)的各項(xiàng)檢查和監(jiān)督管理等。
(8)工種之間必須友好相處,相互配合,不得相互推諉扯皮。
(9)乙方施工人員家屬探親,禁止上工地現(xiàn)場(chǎng),工地不安排住宿。如遇特殊情況必須由甲方批準(zhǔn)許可,并由本人做好家屬的教育工作,小孩更應(yīng)由家屬?lài)?yán)加看管。如發(fā)生意外概由乙方承擔(dān)責(zé)任和全部費(fèi)用。
(10)嚴(yán)禁在宿舍內(nèi)用火燒飯、隨意拉電線(xiàn)和使用電飯煲,一經(jīng)查實(shí)處沒(méi)收器具并每次罰款_________元。
(11)施工期間發(fā)生矛盾,應(yīng)及時(shí)向現(xiàn)場(chǎng)負(fù)責(zé)人匯報(bào),尋求商量解決,嚴(yán)禁聚眾斗毆,如在施工現(xiàn)場(chǎng)發(fā)生聚眾斗毆,不論有無(wú)理由每次罰款伍仟元;嚴(yán)禁在工地或宿舍內(nèi)**,發(fā)現(xiàn)時(shí)每次罰款貳仟元,罰金在工程款中扣除。如因違反法律、行政法規(guī)被押送公安機(jī)關(guān)處理,甲方不予承擔(dān)任何責(zé)任和經(jīng)濟(jì)費(fèi)用。
(12)乙方與甲方簽訂勞務(wù)合同,員工工資按勞務(wù)合同要求保證發(fā)放到每個(gè)員工。乙方勞務(wù)人員進(jìn)入現(xiàn)場(chǎng)施工,必須進(jìn)行三級(jí)教育,嚴(yán)格執(zhí)行規(guī)章制度,一旦發(fā)生事故,查清原因如屬乙方責(zé)任,按事故的實(shí)際損失由乙方自負(fù)外,同時(shí)追究相關(guān)責(zé)任,并視責(zé)任輕重采取重罰措施。
(13)發(fā)生事故應(yīng)立即組織搶救,并保護(hù)好現(xiàn)場(chǎng),即刻上報(bào)甲方,嚴(yán)禁隱瞞事故不報(bào)。
(14)積極配合甲方工作,做好上情下達(dá),及時(shí)簽訂各級(jí)責(zé)任書(shū),層層落實(shí)生產(chǎn)責(zé)任制。
(15)乙方本合同經(jīng)濟(jì)責(zé)任人,為甲乙雙方約定的市政道路工程施工的責(zé)任人,應(yīng)帶頭遵紀(jì)守法,不準(zhǔn)違章指揮,準(zhǔn)確把握、質(zhì)量、進(jìn)度、效益的關(guān)系,保證全員,施工順利進(jìn)行。
(16)積極配合各項(xiàng)目部組織的知識(shí),宣傳及業(yè)余上課,并落實(shí)到每個(gè)職工,真正做到、預(yù)防為主,增強(qiáng)以人為本的現(xiàn)場(chǎng)氣氛。
(17)乙方必須確保專(zhuān)職技術(shù)、質(zhì)量、員的到位,并嚴(yán)格履行職責(zé),如不到位甲方有權(quán)對(duì)乙方作出每人每天100元的處罰。
七、生產(chǎn)、文明施工
乙方在施工中應(yīng)嚴(yán)格按甲方要求進(jìn)行管理,遵守生產(chǎn)操作規(guī)程,設(shè)置專(zhuān)職員,并采取必要的防護(hù)措施,以確保施工。如因乙方違章指揮、違章操作而引起事故或其他事故,均由乙方負(fù)全部責(zé)任和承擔(dān)全部經(jīng)濟(jì)損失及費(fèi)用。乙方負(fù)責(zé)做好現(xiàn)場(chǎng)文明施工和相關(guān)的生產(chǎn)、文明施工資料。
八、材料供應(yīng)
本工程甲乙雙方約定的市政道路施工所用的材料按照甲方要求,由乙方按設(shè)計(jì)和有關(guān)質(zhì)量驗(yàn)收標(biāo)準(zhǔn)要求自行采購(gòu),各種材料質(zhì)量必須由甲方、監(jiān)理按有關(guān)質(zhì)量檢驗(yàn)標(biāo)準(zhǔn),會(huì)同乙方隨機(jī)抽樣且經(jīng)法定部門(mén)檢驗(yàn)合格后方可使用,及時(shí)做好進(jìn)場(chǎng)材料臺(tái)帳資料。
九、質(zhì)量驗(yàn)收
工程具備質(zhì)量驗(yàn)收條件,乙方經(jīng)甲方同意按現(xiàn)行相關(guān)標(biāo)準(zhǔn)、規(guī)范、規(guī)程等要求組織質(zhì)量驗(yàn)收,并通知甲方報(bào)送有關(guān)部門(mén)。甲方在收到乙方送交的資料以及驗(yàn)收?qǐng)?bào)告后,積極協(xié)助乙方進(jìn)行質(zhì)量驗(yàn)收。如甲方在整個(gè)工程質(zhì)量創(chuàng)優(yōu)中涉及到乙方工作內(nèi)容,乙方應(yīng)無(wú)條件配合。
十工程款支付
1、工程開(kāi)工后五日內(nèi)預(yù)付工程造價(jià) %。月進(jìn)度款在確認(rèn)計(jì)量結(jié)果后14天內(nèi),發(fā)包人應(yīng)向承包人支付工程款(進(jìn)度款),工程完工經(jīng)甲方、監(jiān)理驗(yàn)收合格后,甲方向乙方支付至合同總價(jià)的_________%;
2、工程結(jié)算后,支付至工程結(jié)算總價(jià)的 %,其余 %的質(zhì)量保證金,待質(zhì)量保期滿(mǎn)一年后支付,如保修期內(nèi)由于承包單位原因產(chǎn)生的質(zhì)量問(wèn)題,由承包單位免費(fèi)維修,如承包單位_________天內(nèi)不到,由發(fā)包人處理,所發(fā)生費(fèi)用加_________%的管理費(fèi)由承包人承擔(dān)
十一、合同份數(shù)
1、本合同正本貳份,雙方各執(zhí)壹份,具有同等法律效力;
2、副本陸份,雙方各執(zhí)叁份。
本合同其它未盡事宜雙方可另行簽訂補(bǔ)充協(xié)議明確。
甲方(公章):_________乙方(公章):_________
法定代表人(簽字):_________法定代表人(簽字):_________
_________年____月____日_________年____月____日
市政道路監(jiān)理規(guī)劃范本通用2
發(fā)包人(以下簡(jiǎn)稱(chēng)甲方):
承包人(以下簡(jiǎn)稱(chēng)乙方):
依照《合同法》及其他相關(guān)法律、法規(guī),遵照平等、自愿、公平、誠(chéng)信的原則,甲方將蘇北路二標(biāo)段(茂名路東文化路西) ,人行道、側(cè)石、平石等工程分項(xiàng)發(fā)包給乙方,為了保證工程質(zhì)量和進(jìn)度,明確甲乙雙方的權(quán)利和義務(wù),經(jīng)甲乙雙方協(xié)商一致,特立本施工承包合同,供雙方共同遵守,具體條款約定如下:
一、項(xiàng)目概況及承包范圍
1、工程名稱(chēng):
2、工程:
3、承包范圍:完成本工程人行道路原路面拆除及外運(yùn)、混凝土的澆筑、步磚鋪設(shè)、側(cè)石、平石鋪設(shè)、前期原瀝青老路面的切割等工作。
二、承包方式
1、包質(zhì)量、包進(jìn)度、包、包文明施工、包驗(yàn)收、包與其他專(zhuān)業(yè)配合。
2、包所有人工作用具工具機(jī)械等。
三、工程款支付方式
工程款支付:
甲方按四次付清,次路面切割、拆除及外運(yùn)完成支付 元。第二次混凝土的'澆筑完成支付 元。第三次側(cè)石平石鋪設(shè)完成支付 元。第四次步道磚完成支付 元。工程竣工驗(yàn)收合格后,甲方于一周內(nèi)同乙方辦理完工程結(jié)算,并足額支付乙方的所有工程款。
四、違約金
雙方特別約定在違約情況發(fā)生付違約方除需按上述規(guī)定向守約方承擔(dān),違約責(zé)任外還需額外向守約方負(fù)擔(dān)壹萬(wàn)元/次的違約金。
五、合同生效
1、合同履行過(guò)程中若發(fā)生糾紛,雙方應(yīng)積極主動(dòng)協(xié)商解決或申請(qǐng)有關(guān)部門(mén)調(diào)解,調(diào)解不成,向工程所在地人民法院起訴。
2、本合同一式兩份,甲乙雙方各執(zhí)一份。
3、本合同由甲乙雙方負(fù)責(zé)人簽字、蓋章后生效,竣工結(jié)算工程款支付完畢后終止。
甲方(公章):_________乙方(公章):_________
法定代表人(簽字):_________法定代表人(簽字):_________
_________年____月____日 _________年____月____日